XML 22 R11.htm IDEA: XBRL DOCUMENT v3.24.3
Property, Plant and Equipment
9 Months Ended
Sep. 30, 2024
Property, Plant and Equipment [Abstract]  
Property, Plant and Equipment

4. Property, Plant and Equipment

 

Property, plant and equipment consist of the following at:

 

(Dollars in thousands)  September 30,
2024
   December 31,
2023
 
Land and land improvements  $1,553   $1,538 
Buildings and leasehold improvements   25,384    25,369 
Computers and related software   11,459    11,764 
Machinery and equipment   9,142    9,054 
Office furniture and fixtures   35    28 
Construction in progress   4,295    1,111 
Property, plant and equipment, gross   51,868    48,864 
Less: Accumulated depreciation   (8,397)   (4,292)
Property, plant and equipment, net  $43,471   $44,572 

 

Depreciation expense was approximately $1.5 million and $1.2 million for the three months ended September 30, 2024 and 2023, respectively. Depreciation expense was approximately $4.6 million and $2.4 million for the nine months ended September 30, 2024 and 2023, respectively

 

There was no loss on sale of equipment for the three months ended September 30, 2024. The Company had a loss on sale of equipment of approximately $21 thousand for the nine months ended September 30, 2024, in which related to equipment held for sale and in storage. The Company received proceeds on the sale of equipment of approximately $215 thousand for the nine months ended September 30, 2024, in which the net book value was approximately $236 thousand. For the three and nine months ended September 30, 2023, the Company incurred a loss on sale of fixed assets of approximately $373 thousand and $404 thousand in relation to the sale of miners for Project Sophie and sale of the remaining Project Marie fixed assets including the Tesseracks (mobile, Bitcoin Mining Equipment).

 

There were no impairment charges for the three months ended September 30, 2024. During the nine months ended September 30, 2024, the Company had impairment charges of approximately $130 thousand. This charge related to the sale of S19 miners that occurred in April 2024, whereas the Company wrote down the net book value of the miners to the subsequent sales price. The Company had impairment charges of approximately $41 thousand for the three months ended September 30, 2023 due to revaluing the M31 and M32 miners to the current market conditions. During the nine months ended September 30, 2023, the Company had impairment charges of approximately $418 thousand in which related to impairment of approximately $165 thousand for power supply units (PSUs) at the Sophie location, $84 thousand for M31 miners based on sales of other recent M31 miners, in which the Company wrote down the net book value to sale price of the sold M32 miners, and $169 thousand due to revaluing the S19 miners to the current market conditions.

 

Equipment held for sale

 

In April 2023, Project Sophie entered into a 25 MW hosting contract with a sustainability-focused Bitcoin miner, which has shifted the Company’s business model at the Company’s modular data center at Project Sophie from proprietary mining to hosting Bitcoin miners for the customer. The Company obtained Board of Director approval to sell all remaining miners at the Sophie location and as of December 31, 2023, approximately $107 thousand remained outstanding whereas the Company expected to be sold within a year. For the nine months ended, September 30, 2024, the Company has sold all remaining Sophie assets held for sale for approximately $82 thousand. In March 2024, Project Dorothy 1B began to look to sell certain miners due to interest from third parties and sold $133 thousand of miners that were included as equipment held for sale as of March 31, 2024, therefore there is no remaining balance related to Dorothy 1B as of September 30, 2024. A balance of approximately $28 thousand in remaining outstanding as of September 30, 2024 related to Marie assets.