Elm Road (Details) (USD $)
12 Months Ended
Dec. 31, 2011
Elm Road [Line Items]  
Total liquidated damages $ 250,000
MGE's share of liquidated damages 21,000
Loss Contingency, Settlement Agreement, Terms Pursuant to the terms of the 2009 settlement agreement and a change order signed concurrent with the turnover of Unit 2, Bechtel was granted total schedule relief of 120 days for Unit 1 and 81 days for Unit 2. Therefore, Bechtel is responsible for 5 days of liquidated damages for Unit 1 and 23 days for Unit 2.
Elm Road Units [Member]
 
Elm Road [Line Items]  
Elm Road placed in-service 195,900,000
Estimated total project cost over-run 181,000,000
Estimated ratio of total cost over-run to approved project costs 8.30%
MGE's Share of the estimated total project cost over-run $ 14,000,000
Cap on construction cost above approved project cost 5.00%
MGE Power Elm Road [Member] | Elm Road Units [Member]
 
Elm Road Units ownership [Line Items]  
Ownership interest in jointly owned plant 8.33%
Plant capacity - MW 615