XML 37 R86.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies (Details) (USD $)
12 Months Ended
Dec. 31, 2011
MW
Dec. 31, 2010
Dec. 31, 2009
Capital Contribution Commitment [Abstract]      
Investment capital contribution commitment $ 200,000    
Venture Debt Investment Commitment [Abstract]      
Venture debt investment commitment 1,000,000    
Venture debt remaining investment commitment 400,000    
Green Energy Projects Commitment [Abstract]      
Green energy projects expenditures 300,000    
Lease Commitments [Abstract]      
Rental expense under operating leases 3,200,000 3,200,000 3,100,000
Smart Grid Investment Grant [Abstract]      
Smart Grid grant approval amount 5,500,000    
Total cost of Smart Grid projects 11,000,000    
Smart grid expenditures to date 6,000,000    
Purchase power agreement [Abstract]      
Purchase power agreement with Osceola Windpower II, LLC - MW 50    
Chattel Paper Purchase Agreement [Abstract]      
Chattel paper purchase agreement maximum interest 10,000,000    
Outstanding interest in chattel paper receivables 4,300,000 3,600,000 3,700,000
Servicing asset recognized 200,000 100,000 100,000
Chattel paper gain on sales of loans 100,000 100,000 100,000
Servicing asset amortized 100,000    
Chattel paper loan sales 1,500,000 500,000 600,000
Chattel paper agreement principal payments 800,000 700,000 800,000
Receivable - margin account [Abstract]      
Margin account held at MF Global 700,000    
Wind development rights termination [Abstract]      
Wind development rights termination capacity - MW 175    
Wind development rights termination payments 2,000,000    
Wind deveopment rights termination outstanding balance 1,000,000    
Lenz Oil Site [Abstract]      
Total remedy amount 2,200,000    
MGE's portion of remedy 100,000    
Energy Efficiency and Renewables [Abstract]      
Minimum electricity generated from renewables 10.00%    
Air Quality Regulations [Abstract]      
Minimum capacity to be regulated by CSAPR/CAIR - MW 25    
CAIR phase one emission reductions for NOx 55.00%    
CAIR phase one emission reductions for SO2 40.00%    
CAIR phase two emission reductions for NOx 65.00%    
CAIR phase two emission reductions for SO2 70.00%    
Minimum amount of fleet-wide mercury reduction in Wisconsin - Phase one 40.00%    
Coal-fired electric generating units - MW requirement 150    
Minimum amount of fleet-wide mercury reduction in Wisconsin - Phase two 90.00%    
Columbia Units [Member]
     
Columbia Units [Line Items]      
Generating capability - MW 225    
Jointly owned plant's share of MGE's net generating capability 29.00%    
Ownership interest in jointly owned plant 22.00%    
WPL ownership interest of Columbia 46.20%    
WPSC ownership interest of Columbia 31.80%    
Columbia Certificate Of Authority [Abstract]      
MGE's share of total capital expenditures 140,000,000    
Carrying cost on pre-construction costs - AFUDC rate 100.00%    
Incurred costs to date 4,400,000    
Columbia Clean Air Act Litigation [Abstract]      
Possible Columbia clean air act litigation civil penalties 37,500    
One Year From Balance Sheet Date [Member]
     
Operating expense purchase contracts [Abstract]      
Coal commitments 25,087,000    
Natural Gas Commitments [Abstract]      
Natural gas transportation and storage commitments 17,285,000    
Natural gas supply commitments 16,062,000    
Purchase power commitments 37,507,000    
Other commitments 948,000    
Total operating expense purchase contracts 96,889,000    
Columbia Commitments [Abstract]      
Columbia environmental project commitments 1,500,000    
Green Energy Projects Commitment [Abstract]      
Green energy projects commitment 400,000    
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Wind Easements Commitment [Abstract]      
Wind easements commitment 100,000    
Chattel Paper Agreement Principal Payments [Abstract]      
Principal payment commitments 563,000    
Lease Commitments [Abstract]      
Lease Commitments 2,595,000    
Smart Grid Investment Grant [Abstract]      
Smart grid commitments to date 800,000    
More Than One And Within Two Years From Balance Sheet Date [Member]
     
Operating expense purchase contracts [Abstract]      
Coal commitments 19,101,000    
Natural Gas Commitments [Abstract]      
Natural gas transportation and storage commitments 17,037,000    
Natural gas supply commitments 0    
Purchase power commitments 45,739,000    
Other commitments 0    
Total operating expense purchase contracts 81,877,000    
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Wind Easements Commitment [Abstract]      
Wind easements commitment 100,000    
Chattel Paper Agreement Principal Payments [Abstract]      
Principal payment commitments 633,000    
Lease Commitments [Abstract]      
Lease Commitments 2,409,000    
More Than Two And Within Three Years From Balance Sheet Date [Member]
     
Operating expense purchase contracts [Abstract]      
Coal commitments 3,599,000    
Natural Gas Commitments [Abstract]      
Natural gas transportation and storage commitments 16,843,000    
Natural gas supply commitments 0    
Purchase power commitments 43,056,000    
Other commitments 0    
Total operating expense purchase contracts 63,498,000    
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Wind Easements Commitment [Abstract]      
Wind easements commitment 100,000    
Chattel Paper Agreement Principal Payments [Abstract]      
Principal payment commitments 447,000    
Lease Commitments [Abstract]      
Lease Commitments 1,462,000    
More Than Three And Within Four Years From Balance Sheet Date [Member]
     
Operating expense purchase contracts [Abstract]      
Coal commitments 0    
Natural Gas Commitments [Abstract]      
Natural gas transportation and storage commitments 16,688,000    
Natural gas supply commitments 0    
Purchase power commitments 40,717,000    
Other commitments 0    
Total operating expense purchase contracts 57,405,000    
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Wind Easements Commitment [Abstract]      
Wind easements commitment 100,000    
Chattel Paper Agreement Principal Payments [Abstract]      
Principal payment commitments 758,000    
Lease Commitments [Abstract]      
Lease Commitments 1,025,000    
More Than Four And Within Five Years From Balance Sheet Date [Member]
     
Operating expense purchase contracts [Abstract]      
Coal commitments 0    
Natural Gas Commitments [Abstract]      
Natural gas transportation and storage commitments 9,075,000    
Natural gas supply commitments 0    
Purchase power commitments 41,357,000    
Other commitments 0    
Total operating expense purchase contracts 50,432,000    
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Wind Easements Commitment [Abstract]      
Wind easements commitment 100,000    
Chattel Paper Agreement Principal Payments [Abstract]      
Principal payment commitments 682,000    
Lease Commitments [Abstract]      
Lease Commitments 785,000    
More than Five Years from Balance Sheet Date and Thereafter [Member]
     
WPDES Permit [Abstract]      
WPDES permit payment 300,000    
Lease Commitments [Abstract]      
Lease Commitments $ 9,264,000