21.       Elm Road - MGE Energy and MGE.

 

MGE Power Elm Road owns an 8.33% ownership interest in each of two 615 MW coal-fired generating units in Oak Creek, Wisconsin. Unit 1 entered commercial operation in February 2010 and Unit 2 entered commercial operation in January 2011. MGE Power Elm Road's sole principal asset is that ownership interest in those generating units. Each generating unit owner provides its own financing and reflects its respective portion of the facility and costs in its financial statements. MGE Power Elm Road has leased the Elm Road Units to MGE pursuant to separate facility lease agreements for each unit. These leases were authorized by order of the PSCW in accordance with applicable provisions of Wisconsin law that authorized financing of new generation through facility leases. The PSCW order establishes a cap on the construction costs that may be passed through the lease agreements to MGE and its customers, through rates. Additional costs attributable to force majeure events, as defined in the leases, do not count against this cap, but are subject to PSCW review and determination that the costs were prudently incurred.

 

As of December 31, 2011, $195.9 million (including capitalized interest) related to this project was placed in-service on MGE Energy's and MGE's consolidated balance sheets.

 

MGE Energy received notice from Elm Road Services, LLC, the project manager for the construction of the Elm Road Units, that the estimated total cost over-run of the units is $181 million or 8.3% over the amount initially approved by the PSCW, of which our share is approximately $14 million. The additional amount included the amounts payable to Bechtel, the builder of the Elm Road Units, pursuant to a settlement agreement entered into in 2009. The PSCW order approving the construction provides for recovery of excess costs of up to 5% of the total project, subject to a prudence review by the PSCW. Costs above the 5% cap would also be included in lease payments and recovered from customers if the PSCW finds that such costs were prudently incurred and were the result of force majeure conditions, an excused event and/or event of loss. The leases provide for a guaranteed in-service date of September 29, 2009 for Unit 1 and September 29, 2010 for Unit 2, and imposes liquidated damages on ERS of $250,000 per day, of which our share is approximately $21,000 per day, for failure to achieve the guaranteed in-service date unless the delays result from force majeure conditions or an excused event. In light of the weather delays incurred on the project and other factors, we expect to request authorization from the PSCW to recover all costs associated with the Units and we expect the PSCW will grant relief from liquidated damages.

 

ERS is entitled to receive $250,000 per day, of which our share is approximately $21,000 per day, from Bechtel under the construction contract with Bechtel for each day Bechtel failed to achieve the guaranteed in-service dates of September 29, 2009 and September 29, 2010, unless the delays resulted from force majeure conditions or an excused event. Pursuant to the terms of the 2009 settlement agreement and a change order signed concurrent with the turnover of Unit 2, Bechtel was granted total schedule relief of 120 days for Unit 1 and 81 days for Unit 2. Therefore, Bechtel is responsible for 5 days of liquidated damages for Unit 1 and 23 days for Unit 2. All liquidated damages collected are for the benefit of our customers. Although we anticipate the PSCW will agree that the excused delays were caused by force majeure and other excusable conditions, there is no guarantee that it will grant the same schedule relief as has been granted to Bechtel.