XML 103 R14.htm IDEA: XBRL DOCUMENT v2.4.1.9
Property and Equipment (including Concession Assets)
12 Months Ended
Dec. 31, 2014
Property, Plant and Equipment [Abstract]  
Property and Equipment (including Concession Assets)
Property and Equipment (including Concession Assets)
The following tables list the major categories of property and equipment, including concession assets, as well as the weighted-average composite depreciation rate for each category (in millions):
As of December 31, 2014
Cost
 
Accumulated
Depreciation
 
Net Book
Value
 
Depreciation
Rates for 2014
Land
$
216.8

 
$
—

 
$
216.8

 
N/A

Concession land rights
141.2

 
(22.3
)
 
118.9

 
1.0
%
Rail and other track material
1,707.6

 
(361.1
)
 
1,346.5

 
1.9-3.2%

Ties
1,484.7

 
(312.6
)
 
1,172.1

 
2.0-4.2%

Grading
839.6

 
(137.9
)
 
701.7

 
1.0
%
Bridges and tunnels
669.5

 
(123.8
)
 
545.7

 
1.2
%
Ballast
649.8

 
(170.0
)
 
479.8

 
2.7-4.8%

Other (a)
943.5

 
(275.6
)
 
667.9

 
3.1
%
Total road property
6,294.7

 
(1,381.0
)
 
4,913.7

 
2.8
%
Locomotives
1,310.3

 
(238.3
)
 
1,072.0

 
4.7
%
Freight cars
610.6

 
(98.3
)
 
512.3

 
5.3
%
Other equipment
59.0

 
(18.5
)
 
40.5

 
8.2
%
Total equipment
1,979.9

 
(355.1
)
 
1,624.8

 
5.0
%
Technology and other
160.9

 
(121.9
)
 
39.0

 
13.2
%
Construction in progress
241.5

 
—

 
241.5

 
N/A

Total property and equipment (including concession assets)
$
9,035.0

 
$
(1,880.3
)
 
$
7,154.7

 
N/A

_____________
(a)
Other includes signals, buildings and other road assets.
As of December 31, 2013
Cost
 
Accumulated
Depreciation
 
Net Book
Value
 
Depreciation
Rates for 2013
Land
$
216.4

 
$
—

 
$
216.4

 
N/A

Concession land rights
141.2

 
(20.9
)
 
120.3

 
1.0
%
Rail and other track material
1,617.8

 
(341.1
)
 
1,276.7

 
1.8-3.1%

Ties
1,425.1

 
(303.7
)
 
1,121.4

 
2.0-4.3%

Grading
829.6

 
(129.7
)
 
699.9

 
1.1
%
Bridges and tunnels
606.4

 
(116.5
)
 
489.9

 
1.2
%
Ballast
602.7

 
(155.2
)
 
447.5

 
2.6-4.8%

Other (a)
874.1

 
(252.8
)
 
621.3

 
2.9
%
Total road property
5,955.7

 
(1,299.0
)
 
4,656.7

 
2.7
%
Locomotives
1,017.4

 
(193.2
)
 
824.2

 
5.0
%
Freight cars
362.2

 
(78.9
)
 
283.3

 
3.9
%
Other equipment
56.6

 
(14.1
)
 
42.5

 
7.4
%
Total equipment
1,436.2

 
(286.2
)
 
1,150.0

 
4.8
%
Technology and other
152.8

 
(111.3
)
 
41.5

 
11.6
%
Construction in progress
171.4

 
—

 
171.4

 
N/A

Total property and equipment (including
concession assets)
$
8,073.7

 
$
(1,717.4
)
 
$
6,356.3

 
N/A

_____________
(a)
Other includes signals, buildings and other road assets.
Concession assets, net of accumulated amortization of $483.1 million and $444.1 million, totaled $2,007.6 million and $1,951.0 million at December 31, 2014 and 2013, respectively.
The Company capitalized $0.9 million, $1.1 million, and $0.9 million of interest for the years ended December 31, 2014, 2013, and 2012, respectively.
Depreciation and amortization of property and equipment (including concession assets) totaled $258.1 million, $223.3 million and $198.8 million, for 2014, 2013, and 2012, respectively.