XML 75 R11.htm IDEA: XBRL DOCUMENT v2.4.0.8
Rate Matters
6 Months Ended
Jun. 30, 2013
Rate Matters

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, our subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within our 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

Regulatory Assets Not Yet Being Recovered      
     June 30, December 31,
     2013 2012
     (in millions)
 Noncurrent Regulatory Assets      
 Regulatory assets not yet being recovered pending future proceedings:      
          
 Regulatory Assets Currently Earning a Return      
  Storm Related Costs $ 22 $ 23
  Economic Development Rider   14   13
  Other Regulatory Assets Not Yet Being Recovered   3   1
 Regulatory Assets Currently Not Earning a Return      
  Storm Related Costs   142   172
  Virginia Environmental Rate Adjustment Clause   29   29
  Ormet Delayed Payment Arrangement   20   5
  Mountaineer Carbon Capture and Storage Product Validation Facility   14   14
  Litigation Settlement   -   11
  Other Regulatory Assets Not Yet Being Recovered   44   36
 Total Regulatory Assets Not Yet Being Recovered $ 288 $ 304

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters

 

Ohio Electric Security Plan Filing

 

2009 – 2011 ESP

 

The PUCO issued an order in March 2009 that modified and approved the ESP which established rates at the start of the April 2009 billing cycle through 2011. OPCo collected the 2009 annualized revenue increase over the last nine months of 2009. The order also provided a phase-in FAC, which was authorized to be recovered through a non-bypassable surcharge over the period 2012 through 2018. The PUCO's March 2009 order was appealed to the Supreme Court of Ohio, which issued an opinion and remanded certain issues back to the PUCO.

 

In October 2011, the PUCO issued an order in the remand proceeding. As a result, OPCo ceased collection of POLR billings in November 2011 and recorded a write-off in 2011 related to POLR collections for the period June 2011 through October 2011. In February 2012, the Ohio Consumers' Counsel and the IEU filed appeals of that order with the Supreme Court of Ohio challenging various issues, including the PUCO's refusal to order retrospective relief concerning the POLR charges collected during 2009 – 2011 and various aspects of the approved environmental carrying charge, which, if ordered, could reduce OPCo's net deferred fuel costs up to the total balance. As of June 30, 2013, OPCo's net deferred fuel balance was $484 million, excluding unrecognized equity carrying costs. A decision from the Supreme Court of Ohio is pending.

 

In January 2011, the PUCO issued an order on the 2009 SEET filing, which resulted in a write-off in 2010 and a subsequent refund to customers during 2011. The IEU and the Ohio Energy Group filed appeals with the Supreme Court of Ohio challenging the PUCO's SEET decision. In December 2012, the Supreme Court of Ohio issued an order which rejected all of the intervenors' challenges and affirmed the PUCO decision.

 

The 2009 SEET order gave consideration for a future commitment to invest $20 million to support the development of a large solar farm. In January 2013, the PUCO found there was not a need for the large solar farm. The PUCO noted that OPCo remains obligated to spend $20 million on this solar project or another project by the end of 2013. Management continues to evaluate other investment alternatives.

 

In July 2011, OPCo filed its 2010 SEET filing with the PUCO based upon the approach in the PUCO's 2009 order. Subsequent testimony and legal briefs from intervenors recommended a refund of up to $62 million of 2010 earnings, which included off-system sales in the SEET calculation. In December 2011, the PUCO staff filed testimony that recommended a $23 million refund of 2010 earnings. OPCo provided a reserve based upon management's estimate of the probable amount for a PUCO-ordered SEET refund. OPCo is required to file its 2011 SEET filing with the PUCO on a separate CSPCo and OPCo company basis. The PUCO approved OPCo's requests to file the SEET for 2011 and 2012 one month after the PUCO issues an order on the 2010 SEET. Management does not currently believe that there were significantly excessive earnings in 2011 for either CSPCo or OPCo or in 2012 for OPCo. Additionally, management does not currently believe that there will be significantly excessive earnings in 2013 for OPCo.

 

In August 2012, the PUCO issued an order in a separate proceeding which implemented a Phase-In Recovery Rider (PIRR) to recover deferred fuel costs in rates beginning September 2012. The PUCO ruled that carrying charges should be calculated without an offset for accumulated deferred income taxes and that a long-term debt rate should be applied when collections begin. In November 2012, OPCo filed an appeal at the Supreme Court of Ohio claiming a long-term debt rate modified the previously adjudicated 2009 – 2011 ESP order, which granted a weighted average cost of capital rate. The IEU and the Ohio Consumers' Counsel also filed appeals at the Supreme Court of Ohio in November 2012 arguing that the PUCO should have reduced the deferred fuel balance to reflect the prior “improper” collection of POLR revenues and reduced carrying costs due to an accumulated deferred income tax credit. These appeals could reduce OPCo's net deferred fuel balance up to the total balance, which could reduce future net income and cash flows. A decision from the Supreme Court of Ohio is pending.

 

Management is unable to predict the outcome of the unresolved litigation discussed above. Depending on the rulings in these proceedings, it could reduce future net income and cash flows and impact financial condition.

 

June 2012 – May 2015 ESP Including Capacity Charge

 

In August 2012, the PUCO issued an order which adopted and modified a new ESP that establishes base generation rates through May 2015, which was generally upheld in rehearing orders in January and March 2013.

 

As part of the ESP decision, the PUCO ordered OPCo to conduct an energy-only auction for 10% of the SSO load with delivery beginning six months after the receipt of final orders in both the ESP and corporate separation cases and extending through May 2015. The initiation of the auction is pending the issuance of an order by the PUCO in a separate docket. The PUCO also ordered OPCo to conduct energy-only auctions for an additional 50% of the SSO load with delivery beginning June 2014 through May 2015 and for the remaining 40% of the SSO load for delivery from January 2015 through May 2015. OPCo will conduct energy and capacity auctions for its entire SSO load for delivery starting in June 2015.

 

In July 2012, the PUCO issued an order in a separate capacity proceeding which stated that OPCo must charge CRES providers the Reliability Pricing Model (RPM) price and authorized OPCo to defer a portion of its incurred capacity costs not recovered from CRES providers up to $188.88/MW day. The RPM price is approximately $33/MW day through May 2014. In December 2012, various parties filed notices of appeal of the capacity costs decision with the Supreme Court of Ohio. As of June 30, 2013, OPCo's incurred deferred capacity costs balance of $171 million, including debt carrying costs, was recorded in Regulatory Assets on the balance sheet.

 

As part of the August 2012 ESP order, the PUCO established a non-bypassable Retail Stability Rider (RSR), effective September 2012. The RSR is expected to provide approximately $500 million of revenue over the ESP period and will be collected from customers at $3.50/MWh through May 2014 and $4.00/MWh for the period June 2014 through May 2015, with $1.00/MWh applied to the recovery of deferred capacity costs. In August 2012, the IEU filed an action with the Supreme Court of Ohio stating, among other things, that OPCo's collection of its capacity costs is illegal. In April 2013, the Supreme Court of Ohio dismissed the IEU's action.

 

In January and March 2013, the PUCO issued its Orders on Rehearing for the ESP which generally upheld its August 2012 order including the implementation of the RSR. The PUCO clarified that a final reconciliation of revenues and costs would be permitted for any over- or under-recovery on several riders including fuel. In addition, the PUCO addressed certain issues around the energy auctions while other SSO issues related to the energy auctions were deferred to a separate docket related to the competitive bid process (CBP). In April and May 2013, OPCo and various intervenors filed appeals with the Supreme Court of Ohio challenging portions of the PUCO's ESP order.

 

In June 2013, intervenors in the competitive bid process (CBP) docket filed recommendations that include prospective rate reductions for capacity and non-energy FAC issues.  OPCo maintains that the August 2012 ESP order fixed OPCo's non-energy generation rates through December 31, 2014 and ordered the application of a $188.88/MW day price for capacity for non-shopping customers effective January 1, 2015. However, intervenors maintained that OPCo's non-energy generation rates should be reduced prior to January 1, 2015 to blend the $188.88/MW day capacity price in proportion to the percentage of energy planned to be auctioned (10% prior to June 2014 and 60% for the period June 1, 2014 through December 31, 2014). An additional proposal to prospectively offset deferred capacity costs based upon the results of the energy-only auctions was not quantified and OPCo maintains that proposal should not be adopted in light of prior PUCO orders. Hearings related to the CBP were held at the PUCO in June and July 2013. 

 

If OPCo is ultimately not permitted to fully collect its ESP rates including the RSR, and its deferred capacity costs, it could reduce future net income and cash flows and impact financial condition.

Corporate Separation

 

In October 2012, the PUCO issued an order which approved the corporate separation of OPCo's generation assets including the transfer of OPCo's generation assets at net book value to AEPGenCo. AEPGenCo will also assume the associated generation liabilities. In June 2013, the IEU filed an appeal with the Supreme Court of Ohio claiming the PUCO order approving the corporate separation was unlawful.

 

Also in October 2012, filings at the FERC were submitted related to corporate separation. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo. Results of operations related to generation in Ohio will be largely determined by prevailing market conditions effective January 1, 2014. See the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters.

Storm Damage Recovery Rider (SDRR)

 

In December 2012, OPCo submitted an application with the PUCO to establish initial SDRR rates. The SDRR seeks recovery of 2012 incremental storm distribution expenses over twelve months starting with the effective date of the SDRR as approved by the PUCO. OPCo also requested approval of a weighted average cost of capital carrying charge if recovery of these costs did not begin prior to April 2013. In May 2013, intervenors filed comments with various recommendations including reductions in the amount of storm costs recoverable up to the amount deferred, an extended recovery period, and an additional review of the storm costs including the allocation of costs to capital. As of June 30, 2013, OPCo recorded $61 million in Regulatory Assets on the balance sheet related to 2012 storm damage. If OPCo is not ultimately permitted to recover these storm costs, it could reduce future net income and cash flows and impact financial condition.

2009 Fuel Adjustment Clause Audit

 

The PUCO selected an outside consultant to conduct an audit of OPCo's FAC for 2009. The outside consultant provided its audit report to the PUCO. In January 2012, the PUCO ordered that the remaining $65 million in proceeds from a 2008 coal contract settlement agreement be applied against OPCo's under-recovered fuel balance. In April 2012, on rehearing, the PUCO ordered that the settlement credit only needed to reflect the Ohio retail jurisdictional share of the gain not already flowed through the FAC with carrying charges. OPCo recorded a $30 million net favorable adjustment on the statement of income in the second quarter of 2012. The January 2012 PUCO order also stated that a consultant should be hired to review the coal reserve valuation and recommend whether any additional value should benefit ratepayers. Management is unable to predict the outcome of any future consultant recommendation regarding valuation of the coal reserve. If the PUCO ultimately determines that additional amounts should benefit ratepayers as a result of the consultant's review of the coal reserve valuation, it could reduce future net income and cash flows and impact financial condition.

 

In August 2012, intervenors filed an appeal with the Supreme Court of Ohio claiming the settlement credit ordered by the PUCO should have reflected the remaining gain not already flowed through the FAC with carrying charges, which, if ordered, would be $35 million plus carrying charges. If the Supreme Court of Ohio ultimately determines that additional amounts should benefit ratepayers, it could reduce future net income and cash flows and impact financial condition.

2010 and 2011 Fuel Adjustment Clause Audits

 

The PUCO-selected outside consultant issued its 2010 and 2011 FAC audit reports which included a recommendation that the PUCO reexamine the carrying costs on the deferred FAC balance and determine whether the carrying costs on the balance should be net of accumulated income taxes. As of June 30, 2013, the amount of OPCo's carrying costs that could potentially be reduced due to the accumulated income tax issue is estimated to be $34 million, including $18 million of unrecognized equity carrying costs. These amounts include the carrying costs exposure of the 2009 FAC audit, which has been appealed by an intervenor to the Supreme Court of Ohio. Decisions from the PUCO are pending. Management is unable to predict the outcome of these proceedings. If the PUCO orders result in a reduction to the FAC deferral, it could reduce future net income and cash flows and impact financial condition.

Ormet Interim Arrangement

 

Ormet, a large aluminum company, filed an application with the PUCO for approval of an interim arrangement governing the provision of generation service to Ormet. This interim arrangement was approved by the PUCO and was effective from January 2009 through September 2009. In March 2009, the PUCO approved a FAC in the ESP filing and the FAC aspect of the ESP order was upheld by the Supreme Court of Ohio. The approval of the FAC as part of the ESP, together with the PUCO approval of the interim arrangement, provided the basis to record a regulatory asset for the difference between the approved market price and the rate paid by Ormet. Through September 2009, the last month of the interim arrangement, OPCo had $64 million of deferred FAC costs related to the interim arrangement, excluding $2 million of unrecognized equity carrying costs. In November 2009, OPCo requested that the PUCO approve recovery of the deferral under the interim agreement plus a weighted average cost of capital carrying charge. The deferral amount is included in OPCo's FAC phase-in deferral balance. In the 2009 – 2011 ESP proceeding, intervenors requested that OPCo be required to refund the Ormet-related regulatory asset and requested that the PUCO prevent OPCo from collecting the Ormet-related revenues in the future. The PUCO did not take any action on this request. The intervenors raised the issue again in response to OPCo's November 2009 filing to approve recovery of the deferral under the interim agreement. This issue remains pending before the PUCO. If OPCo is not ultimately permitted to fully recover its requested deferrals under the interim arrangement, it could reduce future net income and cash flows and impact financial condition.

 

Special Rate Mechanism for Ormet

 

In October 2012, the PUCO issued an order approving a delayed payment plan for Ormet's October and November 2012 power billings totaling $27 million to be paid in equal monthly installments over the period January 2014 to May 2015 without interest. In the event Ormet does not pay its $27 million obligation, the PUCO permitted OPCo to recover the unpaid balance, up to $20 million, in the economic development rider. To the extent unpaid amounts exceed $20 million, it could reduce future net income and cash flows and impact financial condition.

 

In February 2013, Ormet filed Chapter 11 bankruptcy proceedings in the state of Delaware but is current on all payments due to OPCo. In June 2013, Ormet filed a motion with the PUCO to amend its contract with OPCo which currently provides for services through 2018. The proposed amendments would allow Ormet to purchase power from a third party beginning January 2014. In July 2013, OPCo filed its objections with the PUCO which included a recommendation to have Ormet pay an exit fee as a potential resolution to address the financial concerns associated with amending the current contract. Hearings at the PUCO are scheduled for August 2013. As of June 30, 2013, OPCo has a regulatory asset of $20 million and a net receivable of $6 million recorded related to the special rate mechanism for Ormet.

Ohio IGCC Plant

 

In March 2005, OPCo filed an application with the PUCO seeking authority to recover costs of building and operating an IGCC power plant. As of June 30, 2013, OPCo has collected $24 million in pre-construction costs authorized in a June 2006 PUCO order. Intervenors have filed motions with the PUCO requesting OPCo refund all collected pre-construction costs to Ohio ratepayers with interest.

 

Management cannot predict the outcome of these proceedings concerning the Ohio IGCC plant or what effect, if any, these proceedings could have on future net income and cash flows. However, if OPCo is required to refund pre-construction costs collected, it could reduce future net income and cash flows and impact financial condition.

SWEPCo Rate Matters

 

Turk Plant

 

SWEPCo constructed the Turk Plant, a new base load 600 MW pulverized coal ultra-supercritical generating unit in Arkansas, which was placed into service in December 2012. SWEPCo owns 73% (440 MW) of the Turk Plant and operates the facility. As of June 30, 2013, excluding costs attributable to its joint owners and a $62 million provision for a Texas capital cost cap, SWEPCo has capitalized approximately $1.8 billion of expenditures, including AFUDC and capitalized interest of $328 million and related transmission costs of $118 million.

 

The APSC granted approval for SWEPCo to build the Turk Plant by issuing a Certificate of Environmental Compatibility and Public Need (CECPN) for the SWEPCo Arkansas jurisdictional share of the Turk Plant (approximately 20%). Following an appeal by certain intervenors, the Arkansas Supreme Court issued a decision that reversed the APSC's grant of the CECPN. In June 2010, in response to an Arkansas Supreme Court decision, the APSC issued an order which reversed and set aside the previously granted CECPN. The Arkansas portion of the Turk Plant output is currently not subject to cost-based rate recovery and is being sold into the SPP market.

 

The PUCT approved a Certificate of Convenience and Necessity (CCN) for the Turk Plant with the following conditions: (a) a cap on the recovery of jurisdictional capital costs for the Turk Plant based on the previously estimated $1.522 billion projected construction cost, excluding AFUDC and related transmission costs, (b) a cap on recovery of annual CO2 emission costs at $28 per ton through the year 2030 and (c) a requirement to hold Texas ratepayers financially harmless from any adverse impact related to the Turk Plant not being fully subscribed to by other utilities or wholesale customers. SWEPCo appealed the PUCT's order contending the two cost cap restrictions are unlawful. The Texas Industrial Energy Consumers (TIEC) filed an appeal contending that the PUCT's grant of a conditional CCN for the Turk Plant should be revoked because the Turk Plant is unnecessary to serve retail customers. The Texas District Court and the Texas Court of Appeals affirmed the PUCT's order in all respects. In April 2012, SWEPCo and the TIEC filed petitions for review at the Supreme Court of Texas, which were denied in March 2013. In April 2013, SWEPCo and the TIEC filed motions for rehearing at the Supreme Court of Texas. In May 2013, the Supreme Court of Texas requested the PUCT and the TIEC respond to SWEPCo's motion.

 

If SWEPCo cannot recover all of its investment and expenses related to the Turk Plant, it could reduce future net income and cash flows and impact financial condition.

 

2012 Texas Base Rate Case

 

In July 2012, SWEPCo filed a request with the PUCT to increase annual base rates by $83 million, primarily due to the Turk Plant, based upon an 11.25% return on common equity to be effective January 2013. The requested base rate increase included a return on and of the Texas jurisdictional share (approximately 33%) of the Turk Plant generation investment as of December 2011, total Turk Plant related estimated transmission investment costs and associated operation and maintenance costs. The filing also (a) increased depreciation expense due to the decrease in the average remaining life of the Welsh Plant to account for the change in the retirement date of the Welsh Plant, Unit 2 from 2040 to 2016, (b) proposed increased vegetation management expenditures and (c) included a return on and of the Stall Unit as of December 2011 and associated operation and maintenance costs.

 

In September 2012, an Administrative Law Judge (ALJ) issued an order that granted the establishment of SWEPCo's existing rates as temporary rates beginning in late January 2013, subject to true-up to the final PUCT-approved rates.

 

In December 2012, several intervenors, including the PUCT staff, filed testimony that recommended an annual base rate increase between $16 million and $51 million based upon a return on common equity between 9% and 9.55%. In addition, two intervenors recommended that the Turk Plant be excluded from rate base. In May 2013, the ALJ issued a proposal for decision (PFD) and added clarifications in July 2013. The PFD, as clarified, made various recommendations including (a) an annual base rate increase of approximately $41 million based upon a return on common equity of 9.65%, (b) the disallowance of the Turk Plant capital costs in excess of the investment and committed costs as of June 2010 plus the cost to retrofit Welsh Plant, Unit 2 which, as of June 30, 2013, SWEPCo estimates could result in a write-off of approximately $74 million (in excess of the $62 million reserve previously recorded related to the Texas capital cost cap) and (c) the exclusion, until SWEPCo's next Texas base rate case, of the Turk Plant transmission line investment that was not in service at the end of the test year. A decision from the PUCT is expected in the third quarter of 2013. If the PUCT does not approve full cost recovery of SWEPCo's Texas jurisdictional share of assets, it could reduce future net income and cash flows and impact financial condition.

2012 Louisiana Formula Rate Filing

 

In 2012, SWEPCo initiated a proceeding to establish new formula base rates in Louisiana, including recovery of the Louisiana jurisdictional share (approximately 29%) of the Turk Plant. In February 2013, a settlement was filed and approved by the LPSC. The settlement increased Louisiana total rates by approximately $2 million annually, effective March 2013, which consisted of an increase in base rates of approximately $85 million annually offset by a decrease in fuel and other rates of approximately $83 million annually. The March 2013 base rates are based on a 10% return on common equity and cost recovery of the Louisiana jurisdictional share of the Turk Plant and Stall Unit, subject to refund based on the staff review of the cost of service and the prudence review of the Turk Plant. The settlement also provided that the LPSC will review base rates in 2014 and 2015 and that SWEPCo will recover all non-fuel Turk Plant costs and a full weighted-average cost of capital return on the Turk Plant portion of rate base, effective January 2013. In May 2013, SWEPCo filed testimony in the prudence review of the Turk Plant. If the LPSC orders refunds based upon the pending staff review of the cost of service or the prudence review of the Turk Plant, it could reduce future net income and cash flows and impact financial condition.

Flint Creek Plant Environmental Controls

 

In February 2012, SWEPCo filed a petition with the APSC seeking a declaratory order to install environmental controls at the Flint Creek Plant to comply with the standards established by the CAA. The estimated cost of the project is $408 million, excluding AFUDC and company overheads. As a joint owner of the Flint Creek Plant, SWEPCo's portion of those costs is estimated at $204 million. As of June 30, 2013, SWEPCo has incurred $24 million related to this project, including AFUDC and company overheads. In July 2013, the APSC approved the request to install environmental controls at the Flint Creek Plant.

APCo and WPCo Rate Matters

Plant Transfers

 

In October 2012, the AEP East Companies submitted several filings with the FERC regarding the transfer of certain generation plants within the AEP System. See the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters. In December 2012, APCo and WPCo filed requests with the Virginia SCC and the WVPSC for approval to transfer at net book value to APCo a two-thirds interest in Amos Plant, Unit 3 and a one-half interest in the Mitchell Plant, comprising 1,647 MW of average annual generating capacity presently owned by OPCo. In April 2013, several intervenors filed testimony with the Virginia SCC and made recommendations relating to APCo's proposed asset transfers including the issuance of a Request for Proposal (RFP) for APCo's resource needs. In May 2013, Virginia SCC staff filed testimony making recommendations including several alternatives to the asset transfers as proposed including the recommendation to approve only the Amos Plant, Unit 3 asset transfer and limiting the non-contractual liabilities to be assumed by APCo. Hearings were held at the Virginia SCC in June 2013. In June 2013, intervenors filed testimony with the WVPSC and made recommendations relating to APCo's proposed asset transfers including the transfer of only one plant, the issuance of a RFP for any additional capacity and energy requirements and limiting the liabilities to the types and amounts reflected in the net book value of the asset transfers. Hearings were held at the WVPSC in July 2013. APCo is currently pursuing cost recovery of these plants in West Virginia and plans to pursue cost recovery in Virginia. If APCo and WPCo are not ultimately permitted to recover their incurred costs, it could reduce future net income and cash flows and impact financial condition.

APCo IGCC Plant

 

As of June 30, 2013, APCo deferred for future recovery pre-construction IGCC costs of approximately $9 million applicable to its West Virginia jurisdiction, approximately $2 million applicable to its FERC jurisdiction and approximately $10 million applicable to its Virginia jurisdiction. If the costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2013 Virginia Environmental Rate Adjustment Clause (Environmental RAC) Filing

 

In March 2013, APCo filed with the Virginia SCC for approval of an environmental RAC to recover $39 million related to 2012 and 2011 environmental compliance costs effective February 2014 over a one-year period. In March 2013, the environmental RAC surcharge expired related to the collection of 2009 and 2010 environmental compliance costs. APCo has deferred $28 million as of June 30, 2013 for the Virginia portion of unrecovered environmental RAC costs incurred in 2012 and 2011, excluding $11 million of unrecognized equity carrying costs. Hearings at the Virginia SCC are scheduled for August 2013. If the Virginia SCC were to disallow any portion of the environmental RAC, it could reduce future net income and cash flows.

2013 Virginia Generation Rate Adjustment Clause (Generation RAC) Filing

 

In March 2013, APCo filed with the Virginia SCC for an increase in its generation RAC revenues of $12 million for a total of $38 million annually to collect costs related to the Dresden Plant. The generation RAC increase is expected to be effective in March 2014. APCo has deferred $4 million as of June 30, 2013 for the Virginia portion of unrecovered costs of the Dresden Plant, excluding $4 million of unrecognized equity carrying costs. Hearings at the Virginia SCC are scheduled for August 2013. If the Virginia SCC were to disallow any portion of the generation RAC, it could reduce future net income and cash flows.

2012 West Virginia Expanded Net Energy Charge (ENEC) Filing

 

In March 2012, West Virginia passed securitization legislation which allows the WVPSC to establish a regulatory framework for electric utilities to securitize certain deferred ENEC balances and other ENEC-related assets. In August 2012, APCo and WPCo filed a request with the WVPSC for a financing order to securitize a total of $422 million related to the December 2011 under-recovered ENEC deferral balance including other ENEC-related assets of $13 million and related future financing costs of $7 million. Upon completion of the securitization, APCo would offset its current ENEC rates by an amount to recover the securitized balance over the securitization period. In March 2013, APCo, WPCo and intervenors filed a settlement agreement with the WVPSC which recommended the WVPSC authorize APCo to securitize $376 million plus upfront financing costs. Hearings at the WVPSC on the securitization are scheduled for July 2013. As of June 30, 2013, APCo's ENEC under-recovery balance of $287 million, net of 2012 and 2013 over-recovery, was recorded in Regulatory Assets on the balance sheet, excluding $3 million of unrecognized equity carrying costs and $15 million of other ENEC-related assets.

 

In April 2013, APCo and WPCo filed to keep total rates unchanged with a portion of the ENEC to be specifically identified for the amount to be securitized in accordance with the proposed securitization settlement agreement. The remaining ENEC rate is proposed to include (a) the proposed transfer of certain generation facilities from OPCo and the APCo/WPCo merger, (b) construction surcharges and (c) ongoing ENEC costs. Management is currently reviewing intervenor testimony filed in July 2013 that recommends lower ENEC revenues. Hearings at the WVPSC are scheduled for August 2013. If the WVPSC were to disallow any portion of the ENEC, it could reduce future net income and cash flows.

Virginia Storm Costs

 

In March 2013, due to the 2013 enactment of a Virginia law, APCo wrote off $30 million of previously deferred 2012 Virginia storm costs. The change in law affected the test years to be included in APCo's next biennial Virginia base rate filing in March 2014 and the determination of how these costs are treated in the Virginia jurisdictional biennial earnings test for 2012 actual results and 2013 estimated results. The 2013 earnings component will be reviewed quarterly to determine if any storm costs can be deferred. As of June 30, 2013, there were no Virginia deferred storm costs. If this quarterly test allows APCo to recover previously expensed storm costs, it could increase future net income and cash flows.

PSO Rate Matters

 

Oklahoma Environmental Compliance Plan

 

In September 2012, based upon an agreement with the Federal EPA, the State of Oklahoma and other parties, PSO filed an environmental compliance plan with the OCC reflecting the retirement of Northeastern Station (NES) Unit 4 in 2016 and additional environmental controls on NES Unit 3 to continue operations through 2026. The plan requested approval for (a) an estimated $210 million of new environmental investment, excluding AFUDC and overheads of $46 million, that will be incurred prior to 2016 at NES Unit 3, (b) accelerated recovery through 2026 of the net book value of NES Units 3 and 4 (combined net book value of the two units is $231 million as of June 30, 2013), (c) an estimated $83 million of new investment incurred through 2016 at various gas units and (d) a new 15-year purchase power agreement (PPA) with a nonaffiliated entity, effective in 2016, with cost recovery through a rider, including an annual earnings component of $3 million. Although the environmental compliance plan does not seek to put any new costs into rates at this time, PSO anticipates seeking cost recovery in a future rate proceeding.

 

In January 2013, testimony filed by the OCC staff and the Oklahoma Office of the Attorney General (OOAG) recommended no earnings component on the PPA and to delay final decisions until 2020 on parts of the plan including cost recovery of the net book value of NES Unit 3 and any increases in fuel costs due to reductions in the output of energy from NES Unit 3 beginning in 2021. The testimony recommended that cost recovery could extend past 2026 on parts of the plan and recommended a $175 million cost cap on NES Unit 3 environmental investment, excluding AFUDC and overheads.

 

In March 2013, the OCC staff and the OOAG filed additional testimony revising the recommended cost cap on NES Unit 3 to $210 million, excluding AFUDC and overheads, and recommended conditional approval of the planned NES Unit 3 retirement subject to OCC approval in 2020 provided the planned retirement is consistent with environmental rules at that time.

 

Also, an intervenor representing some of PSO's large industrial users opposed the majority of PSO's plan, including recommending no cost recovery of NES Units 3 and 4 book value amounts not recovered at the time of their retirement and no recovery of the PPA costs, including earnings on the PPA. In February 2013, the OCC staff requested a stay in this proceeding, which was granted by the OCC in March 2013. In July 2013, the OCC staff filed a motion to lift the stay and dismiss PSO's environmental compliance plan case without prejudice. A hearing on the motion will be held in August 2013. If this case is dismissed, PSO will address the environmental compliance plan issues in future regulatory proceedings when it seeks cost recovery of the plan.

 

If PSO is ultimately not permitted to fully recover its net book value of NES Units 3 and 4 and other environmental compliance costs, it could reduce future net income and cash flows and impact financial condition.

I&M Rate Matters

 

2011 Indiana Base Rate Case

 

In February 2013, the IURC issued an order that granted an $85 million annual increase in base rates based upon a return on common equity of 10.2%. In a March 2013 order, the IURC approved an adjustment which increased the authorized annual increase in base rates from $85 million to $92 million. In March 2013, the Indiana Office of Utility Consumer Counselor (OUCC) filed a request for reconsideration with the IURC, which was denied. Also in March 2013, the OUCC filed an appeal of the order with the Indiana Court of Appeals. If the order is overturned by the Indiana Court of Appeals, it could reduce future net income and cash flows.

 

Cook Plant Life Cycle Management Project (LCM Project)

 

In April and May 2012, I&M filed a petition with the IURC and the MPSC, respectively, for approval of the LCM Project, which consists of a group of capital projects to ensure the safe and reliable operations of the Cook Plant through its extended licensed life (2034 for Unit 1 and 2037 for Unit 2). The estimated cost of the LCM Project is $1.2 billion to be incurred through 2018, excluding AFUDC. As of June 30, 2013, I&M has incurred $240 million related to the LCM Project, including AFUDC.

 

In April 2012, I&M filed a petition with the IURC for recovery of project costs, including interest, through a new rider. In July 2013, the IURC approved I&M's proposed project with the exception of an estimated $23 million related to certain items that might accommodate a future potential power uprate which the IURC stated could be sought for recovery in a base rate case. I&M was granted recovery through an LCM rider which will be determined by a mid-September 2013 proceeding and semi-annual proceedings thereafter. The IURC authorized deferral accounting for I&M's incurred project costs effective January 2012 to the extent such costs are not reflected in its rates.

 

In January 2013, the MPSC approved a Certificate of Need (CON) for the LCM Project. In February 2013, intervenors filed appeals with the Michigan Court of Appeals objecting to the issuance of the CON as well as the amount of the CON related to the LCM Project. If I&M is not ultimately permitted to recover its LCM Project costs, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant Clean Coal Technology Project (CCT Project)

 

In April 2013, I&M filed an application with the IURC seeking approval of a Certificate of Public Convenience and Necessity (CPCN) to retrofit both of its units at the Rockport Plant with a Dry Sorbent Injection system. The estimated cost in the application was $285 million, excluding AFUDC. The application requested deferral treatment of any unrecovered carrying costs incurred during construction and incremental post in-service depreciation expense and operation and maintenance expenses until such costs are recognized and recovered in a rider. I&M also requested cost recovery associated with the retrofit using the Clean Coal Technology Rider recovery mechanism.

 

In July 2013, a settlement agreement was filed with the IURC. The settlement agreement includes the approval of the CPCN with an updated estimated CCT Project cost of $258 million, excluding AFUDC, and the recovery of the Indiana jurisdictional share of I&M's direct ownership share. The settlement agreement specifies that 80% of the recoverable I&M direct ownership share of CCT Project costs will be recovered through a Federal Mandate Rider with the remaining 20% deferred until rates are established in a subsequent rate case. If the IURC approves the settlement agreement, I&M's Indiana allocated share of the CCT Project costs received in the form of purchased power from AEGCo will be recovered in subsequent I&M rate cases. Hearings at the IURC are scheduled for August 2013. A decision is expected by November 2013. As of June 30, 2013, we have incurred costs of $77 million related to the CCT Project, including AFUDC. If we are not ultimately permitted to recover our incurred costs, it could reduce future net income and cash flows.

KPCo Rate Matters

Plant Transfer

 

In October 2012, the AEP East Companies submitted several filings with the FERC. See the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters. In December 2012, KPCo filed a request with the KPSC for approval to transfer at net book value to KPCo a one-half interest in the Mitchell Plant, comprising 780 MW of average annual generating capacity presently owned by OPCo. KPCo also requested costs related to the Big Sandy Plant, Unit 2 FGD project be established as a regulatory asset. KPCo is currently seeking recovery of these costs with the KPSC. In March 2013, KPCo issued a Request for Proposal (RFP) to purchase up to 250 MW of long-term capacity and energy to replace the capacity from the retirement of Big Sandy Plant, Unit 1. In June 2013, KPCo filed the results of its RFP with the KPSC. As of June 30, 2013, KPCo has incurred $28 million related to the FGD project, which is recorded in Deferred Charges and Other Noncurrent Assets on the balance sheet.

 

In May 2013, a memorandum of understanding (MOU) between KPCo, KIUC and the Sierra Club was filed with the KPSC. The MOU includes (a) the transfer of a one-half interest in the Mitchell Plant to KPCo at net book value on December 31, 2013 (b) the implementation of an Asset Transfer Rider to collect $44 million annually effective January 2014, subject to true-up, (c) the authorization to record FGD project costs as a regulatory asset, (d) the conversion of Big Sandy Plant, Unit 1 to natural gas and (e) any off-system sales margins above the $15.3 million annual level in base rates be retained by KPCo. In July 2013, KPCo, KIUC and the Sierra Club filed a settlement agreement with the KPSC pursuant to the MOU as modified. The settlement agreement also addressed potential greenhouse gas initiatives on the Mitchell Plant. The Attorney General was not a party to the settlement agreement. If approved, KPCo will withdraw the current base rate case request and current rates will remain in effect until at least May 2015. Hearings were held at the KPSC in July 2013. If KPCo is not ultimately permitted to recover its incurred costs, it could reduce future net income and cash flows and impact financial condition.

2013 Kentucky Base Rate Case

 

In June 2013, KPCo filed a request with the KPSC for an annual increase in base rates of $114 million based upon a return on common equity of 10.65% to be effective January 2014. The proposed revenue increase includes cost recovery of the pending transfer of the one-half interest in the Mitchell Plant (780 MW) and cost recovery of Big Sandy Plant, Units 1 and 2. The filing also includes requests for recovery of deferrals totaling $48 million including $28 million related to the Big Sandy Plant FGD project and $12 million related to 2012 storm costs which are recorded in Deferred Charges and Other Noncurrent Assets and Regulatory Assets, respectively, on the balance sheet. Additionally, KPCo proposed that Big Sandy Plant, Unit 2 expenses incurred over the period January 2014 through May 2015 be deferred and recovered over five years beginning January 2014. Also in June 2013, a settlement agreement between KPCo, Kentucky Industrial Utility Customers, Inc. and the Sierra Club was filed with the KPSC which supported the Mitchell plant transfer discussed above. If the settlement agreement is approved, KPCo will withdraw this base rate case request and current rates will remain in effect until at least May 2015. If KPCo is not ultimately permitted to recover its incurred costs, it could reduce future net income and cash flows and impact financial condition.

 

FERC Rate Matters

 

Corporate Separation and Termination of Interconnection Agreement

 

In October 2012, the AEP East Companies submitted several filings with the FERC seeking approval to fully separate OPCo's generation assets from its distribution and transmission operations. The filings requested approval to transfer at net book value (NBV) approximately 9,200 MW of OPCo-owned generation assets to a new wholly-owned company, AEPGenCo. The AEP East Companies also requested FERC approval to transfer at NBV OPCo's current two-thirds ownership (867 MW) in Amos Plant, Unit 3 to APCo and transfer at NBV OPCo's Mitchell Plant to APCo and KPCo in equal one-half interests (780 MW each). These transfers are proposed to be effective December 31, 2013. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo, the Amos Plant and Mitchell Plant asset transfers to APCo and KPCo and the merger of APCo and WPCo. In May 2013, the IEU petitioned the FERC for rehearing of its order granting OPCo authority to implement corporate separation by transferring its generation assets to AEPGenCo. OPCo has contested the petition for rehearing, which remains pending before the FERC. Similar asset transfer filings have been made at the KPSC, the Virginia SCC and the WVPSC. See the “Plant Transfers” section of APCo and WPCo Rate Matters and the “Plant Transfer” section of KPCo Rate Matters.

 

Additionally, the AEP East Companies requested FERC approval, effective January 1, 2014, to terminate the existing Interconnection Agreement and approve a Power Coordination Agreement (PCA) among APCo, I&M and KPCo with AEPSC as the agent to coordinate the participants' respective power supply resources. Under the PCA, APCo, I&M and KPCo would be individually responsible for planning their respective capacity obligations and there would be no capacity equalization charges/credits on deficit/surplus companies. Further, the PCA allows, but does not obligate, APCo, I&M and KPCo to participate collectively under a common fixed resource requirement capacity plan in PJM and to participate in specified collective off-system sales and purchase activities. Intervenors have opposed several of these filings. The AEP East Companies responded to intervenor comments and filed a revised PCA at the FERC in March 2013. The revised PCA included certain clarifying wording changes that have been agreed upon by intervenors. A decision is pending at the FERC.

 

Additionally, FERC approval was sought for a power supply agreement between AEPGenCo and OPCo. This agreement provides for AEPGenCo to supply capacity for OPCo's switched and non-switched retail load for the period January 1, 2014 through May 31, 2015 and to supply the energy needs of OPCo's non-switched retail load that is not acquired through an auction from January 1, 2014 through December 31, 2014.

 

If approved as filed, for any AEPGenCo generation not serving OPCo's retail load, AEPGenCo's results of operations will be largely determined by prevailing market conditions effective January 1, 2014. If incurred costs are not ultimately recovered, it could reduce future net income and cash flows and impact financial condition.

Appalachian Power Co [Member]
 
Rate Matters

Plant Transfers

 

In October 2012, the AEP East Companies submitted several filings with the FERC regarding the transfer of certain generation plants within the AEP System. See the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters. In December 2012, APCo and WPCo filed requests with the Virginia SCC and the WVPSC for approval to transfer at net book value to APCo a two-thirds interest in Amos Plant, Unit 3 and a one-half interest in the Mitchell Plant, comprising 1,647 MW of average annual generating capacity presently owned by OPCo. In April 2013, several intervenors filed testimony with the Virginia SCC and made recommendations relating to APCo's proposed asset transfers including the issuance of a Request for Proposal (RFP) for APCo's resource needs. In May 2013, Virginia SCC staff filed testimony making recommendations including several alternatives to the asset transfers as proposed including the recommendation to approve only the Amos Plant, Unit 3 asset transfer and limiting the non-contractual liabilities to be assumed by APCo. Hearings were held at the Virginia SCC in June 2013. In June 2013, intervenors filed testimony with the WVPSC and made recommendations relating to APCo's proposed asset transfers including the transfer of only one plant, the issuance of a RFP for any additional capacity and energy requirements and limiting the liabilities to the types and amounts reflected in the net book value of the asset transfers. Hearings were held at the WVPSC in July 2013. APCo is currently pursuing cost recovery of these plants in West Virginia and plans to pursue cost recovery in Virginia. If APCo and WPCo are not ultimately permitted to recover their incurred costs, it could reduce future net income and cash flows and impact financial condition.

APCo IGCC Plant

 

As of June 30, 2013, APCo deferred for future recovery pre-construction IGCC costs of approximately $9 million applicable to its West Virginia jurisdiction, approximately $2 million applicable to its FERC jurisdiction and approximately $10 million applicable to its Virginia jurisdiction. If the costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2013 Virginia Environmental Rate Adjustment Clause (Environmental RAC) Filing

 

In March 2013, APCo filed with the Virginia SCC for approval of an environmental RAC to recover $39 million related to 2012 and 2011 environmental compliance costs effective February 2014 over a one-year period. In March 2013, the environmental RAC surcharge expired related to the collection of 2009 and 2010 environmental compliance costs. APCo has deferred $28 million as of June 30, 2013 for the Virginia portion of unrecovered environmental RAC costs incurred in 2012 and 2011, excluding $11 million of unrecognized equity carrying costs. Hearings at the Virginia SCC are scheduled for August 2013. If the Virginia SCC were to disallow any portion of the environmental RAC, it could reduce future net income and cash flows.

2013 Virginia Generation Rate Adjustment Clause (Generation RAC) Filing

 

In March 2013, APCo filed with the Virginia SCC for an increase in its generation RAC revenues of $12 million for a total of $38 million annually to collect costs related to the Dresden Plant. The generation RAC increase is expected to be effective in March 2014. APCo has deferred $4 million as of June 30, 2013 for the Virginia portion of unrecovered costs of the Dresden Plant, excluding $4 million of unrecognized equity carrying costs. Hearings at the Virginia SCC are scheduled for August 2013. If the Virginia SCC were to disallow any portion of the generation RAC, it could reduce future net income and cash flows.

2012 West Virginia Expanded Net Energy Charge (ENEC) Filing

 

In March 2012, West Virginia passed securitization legislation which allows the WVPSC to establish a regulatory framework for electric utilities to securitize certain deferred ENEC balances and other ENEC-related assets. In August 2012, APCo and WPCo filed a request with the WVPSC for a financing order to securitize a total of $422 million related to the December 2011 under-recovered ENEC deferral balance including other ENEC-related assets of $13 million and related future financing costs of $7 million. Upon completion of the securitization, APCo would offset its current ENEC rates by an amount to recover the securitized balance over the securitization period. In March 2013, APCo, WPCo and intervenors filed a settlement agreement with the WVPSC which recommended the WVPSC authorize APCo to securitize $376 million plus upfront financing costs. Hearings at the WVPSC on the securitization are scheduled for July 2013. As of June 30, 2013, APCo's ENEC under-recovery balance of $287 million, net of 2012 and 2013 over-recovery, was recorded in Regulatory Assets on the balance sheet, excluding $3 million of unrecognized equity carrying costs and $15 million of other ENEC-related assets.

 

In April 2013, APCo and WPCo filed to keep total rates unchanged with a portion of the ENEC to be specifically identified for the amount to be securitized in accordance with the proposed securitization settlement agreement. The remaining ENEC rate is proposed to include (a) the proposed transfer of certain generation facilities from OPCo and the APCo/WPCo merger, (b) construction surcharges and (c) ongoing ENEC costs. Management is currently reviewing intervenor testimony filed in July 2013 that recommends lower ENEC revenues. Hearings at the WVPSC are scheduled for August 2013. If the WVPSC were to disallow any portion of the ENEC, it could reduce future net income and cash flows.

Virginia Storm Costs

 

In March 2013, due to the 2013 enactment of a Virginia law, APCo wrote off $30 million of previously deferred 2012 Virginia storm costs. The change in law affected the test years to be included in APCo's next biennial Virginia base rate filing in March 2014 and the determination of how these costs are treated in the Virginia jurisdictional biennial earnings test for 2012 actual results and 2013 estimated results. The 2013 earnings component will be reviewed quarterly to determine if any storm costs can be deferred. As of June 30, 2013, there were no Virginia deferred storm costs. If this quarterly test allows APCo to recover previously expensed storm costs, it could increase future net income and cash flows.

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, the Registrant Subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

 

Regulatory Assets Not Yet Being Recovered

     APCo
     June 30, December 31,
     2013 2012
 Noncurrent Regulatory Assets (in thousands)
 Regulatory assets not yet being recovered pending future proceedings:       
          
 Regulatory Assets Currently Not Earning a Return      
  Storm Related Costs $ 65,206 $ 94,458
  Virginia Environmental Rate Adjustment Clause   28,777   29,320
  Mountaineer Carbon Capture and Storage      
   Product Validation Facility   14,155   14,155
  Dresden Plant Operating Costs   8,760   8,758
  Deferred Wind Power Costs   -   5,143
  Transmission Agreement Phase-In   3,267   2,992
  Mountaineer Carbon Capture and Storage      
   Commercial Scale Facility   1,287   1,287
  Other Regulatory Assets Not Yet Being Recovered   3,652   1,447
 Total Regulatory Assets Not Yet Being Recovered $ 125,104 $ 157,560

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

APCo Rate Matters

WPCo Merger with APCo

 

In December 2011, APCo and WPCo filed an application with the WVPSC requesting approval to merge WPCo into APCo. In December 2012, APCo and WPCo filed merger applications with the Virginia SCC and the FERC. In April 2013, the FERC approved the WPCo merger into APCo. In May 2013, Virginia SCC staff filed testimony that included a recommendation that the Virginia SCC not approve the proposed merger as there is no qualitative benefit and the impact on Virginia rates cannot be determined. Hearings were held at the Virginia SCC in June 2013. In June 2013, the WVPSC issued an order consolidating this case with APCo's plant asset transfer case. In June 2013, WVPSC staff filed testimony that included a recommendation that the WVPSC approve the proposed merger. Hearings were held at the WVPSC in July 2013. See the “Plant Transfers” section of APCo Rate Matters and the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters.

FERC Rate Matters

 

Corporate Separation and Termination of Interconnection Agreement – Affecting APCo, I&M and OPCo

 

In October 2012, the AEP East Companies submitted several filings with the FERC seeking approval to fully separate OPCo's generation assets from its distribution and transmission operations. The filings requested approval to transfer at net book value approximately 9,200 MW of OPCo-owned generation assets to a new wholly-owned company, AEPGenCo. The AEP East Companies also requested FERC approval to transfer at net book value OPCo's current two-thirds ownership (867 MW) in Amos Plant, Unit 3 to APCo and transfer at net book value OPCo's Mitchell Plant to APCo and KPCo in equal one-half interests (780 MW each). These transfers are proposed to be effective December 31, 2013. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo, the Amos Plant and Mitchell Plant asset transfers to APCo and KPCo and the merger of APCo and WPCo. In May 2013, the IEU petitioned the FERC for rehearing of its order granting OPCo authority to implement corporate separation by transferring its generation assets to AEPGenCo. OPCo has contested the petition for rehearing, which remains pending before the FERC. Similar asset transfer filings have been made at the Virginia SCC and the WVPSC. See the “Plant Transfers” section of APCo Rate Matters.

 

Additionally, the AEP East Companies requested FERC approval, effective January 1, 2014, to terminate the existing Interconnection Agreement and approve a Power Coordination Agreement (PCA) among APCo, I&M and KPCo with AEPSC as the agent to coordinate the participants' respective power supply resources. Under the PCA, APCo and I&M would be individually responsible for planning their respective capacity obligations and there would be no capacity equalization charges/credits on deficit/surplus companies. Further, the PCA allows, but does not obligate, APCo and I&M to participate collectively under a common fixed resource requirement capacity plan in PJM and to participate in specified collective off-system sales and purchase activities. Intervenors have opposed several of these filings. The AEP East Companies responded to intervenor comments and filed a revised PCA at the FERC in March 2013. The revised PCA included certain clarifying wording changes that have been agreed upon by intervenors. A decision is pending at the FERC.

 

If APCo and/or I&M experience decreases in revenues or increases in expenses as a result of changes to their relationship with affiliates and are unable to recover the change in revenues and costs through rates, prices or additional sales, it could reduce future net income and cash flows.

Indiana Michigan Power Co [Member]
 
Rate Matters

I&M Rate Matters

 

2011 Indiana Base Rate Case

 

In February 2013, the IURC issued an order that granted an $85 million annual increase in base rates based upon a return on common equity of 10.2%. In a March 2013 order, the IURC approved an adjustment which increased the authorized annual increase in base rates from $85 million to $92 million. In March 2013, the Indiana Office of Utility Consumer Counselor (OUCC) filed a request for reconsideration with the IURC, which was denied. Also in March 2013, the OUCC filed an appeal of the order with the Indiana Court of Appeals. If the order is overturned by the Indiana Court of Appeals, it could reduce future net income and cash flows.

 

Cook Plant Life Cycle Management Project (LCM Project)

 

In April and May 2012, I&M filed a petition with the IURC and the MPSC, respectively, for approval of the LCM Project, which consists of a group of capital projects to ensure the safe and reliable operations of the Cook Plant through its extended licensed life (2034 for Unit 1 and 2037 for Unit 2). The estimated cost of the LCM Project is $1.2 billion to be incurred through 2018, excluding AFUDC. As of June 30, 2013, I&M has incurred $240 million related to the LCM Project, including AFUDC.

 

In April 2012, I&M filed a petition with the IURC for recovery of project costs, including interest, through a new rider. In July 2013, the IURC approved I&M's proposed project with the exception of an estimated $23 million related to certain items that might accommodate a future potential power uprate which the IURC stated could be sought for recovery in a base rate case. I&M was granted recovery through an LCM rider which will be determined by a mid-September 2013 proceeding and semi-annual proceedings thereafter. The IURC authorized deferral accounting for I&M's incurred project costs effective January 2012 to the extent such costs are not reflected in its rates.

 

In January 2013, the MPSC approved a Certificate of Need (CON) for the LCM Project. In February 2013, intervenors filed appeals with the Michigan Court of Appeals objecting to the issuance of the CON as well as the amount of the CON related to the LCM Project. If I&M is not ultimately permitted to recover its LCM Project costs, it could reduce future net income and cash flows and impact financial condition.

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, the Registrant Subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

 

Regulatory Assets Not Yet Being Recovered

     I&M
     June 30, December 31,
     2013 2012
 Noncurrent Regulatory Assets (in thousands)
 Regulatory assets not yet being recovered pending future proceedings:      
          
 Regulatory Assets Currently Not Earning a Return      
  Litigation Settlement $ - $ 11,098
  Mountaineer Carbon Capture and Storage      
   Commercial Scale Facility   -   1,380
  Under-Recovered Capacity Costs   10,792   -
  Other Regulatory Asset Not Yet Being Recovered   2,634   786
 Total Regulatory Assets Not Yet Being Recovered $ 13,426 $ 13,264

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

Rockport Plant Clean Coal Technology Project (CCT Project)

 

In April 2013, I&M filed an application with the IURC seeking approval of a Certificate of Public Convenience and Necessity (CPCN) to retrofit both of the units at the Rockport Plant with a Dry Sorbent Injection system. The estimated cost of the CCT Project was $285 million, excluding AFUDC, of which I&M's ownership share is $142 million. The application requested deferral treatment of any unrecovered carrying costs incurred during construction and incremental post in-service depreciation expense and operation and maintenance expenses until such costs are recognized and recovered in a rider. I&M also requested cost recovery associated with the retrofit using the Clean Coal Technology Rider recovery mechanism.

 

In July 2013, a settlement agreement was filed with the IURC. The settlement agreement includes the approval of the CPCN with an updated estimated CCT Project cost of $258 million, excluding AFUDC, and the recovery of the Indiana jurisdictional share of I&M's direct ownership share of $129 million. The settlement agreement specifies that 80% of the recoverable I&M direct ownership share of CCT Project costs will be recovered through a Federal Mandate Rider with the remaining 20% deferred until rates are established in a subsequent rate case. If the IURC approves the settlement agreement, I&M's Indiana allocated share of the CCT Project costs received in the form of purchased power from AEGCo will be recovered in subsequent I&M rate cases. Hearings at the IURC are scheduled for August 2013. A decision is expected by November 2013. As of June 30, 2013, I&M has incurred costs of $39 million related to the CCT Project, including AFUDC. If I&M is not ultimately permitted to recover its incurred costs, it could reduce future net income and cash flows.

FERC Rate Matters

 

Corporate Separation and Termination of Interconnection Agreement – Affecting APCo, I&M and OPCo

 

In October 2012, the AEP East Companies submitted several filings with the FERC seeking approval to fully separate OPCo's generation assets from its distribution and transmission operations. The filings requested approval to transfer at net book value approximately 9,200 MW of OPCo-owned generation assets to a new wholly-owned company, AEPGenCo. The AEP East Companies also requested FERC approval to transfer at net book value OPCo's current two-thirds ownership (867 MW) in Amos Plant, Unit 3 to APCo and transfer at net book value OPCo's Mitchell Plant to APCo and KPCo in equal one-half interests (780 MW each). These transfers are proposed to be effective December 31, 2013. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo, the Amos Plant and Mitchell Plant asset transfers to APCo and KPCo and the merger of APCo and WPCo. In May 2013, the IEU petitioned the FERC for rehearing of its order granting OPCo authority to implement corporate separation by transferring its generation assets to AEPGenCo. OPCo has contested the petition for rehearing, which remains pending before the FERC. Similar asset transfer filings have been made at the Virginia SCC and the WVPSC. See the “Plant Transfers” section of APCo Rate Matters.

 

Additionally, the AEP East Companies requested FERC approval, effective January 1, 2014, to terminate the existing Interconnection Agreement and approve a Power Coordination Agreement (PCA) among APCo, I&M and KPCo with AEPSC as the agent to coordinate the participants' respective power supply resources. Under the PCA, APCo and I&M would be individually responsible for planning their respective capacity obligations and there would be no capacity equalization charges/credits on deficit/surplus companies. Further, the PCA allows, but does not obligate, APCo and I&M to participate collectively under a common fixed resource requirement capacity plan in PJM and to participate in specified collective off-system sales and purchase activities. Intervenors have opposed several of these filings. The AEP East Companies responded to intervenor comments and filed a revised PCA at the FERC in March 2013. The revised PCA included certain clarifying wording changes that have been agreed upon by intervenors. A decision is pending at the FERC.

 

If APCo and/or I&M experience decreases in revenues or increases in expenses as a result of changes to their relationship with affiliates and are unable to recover the change in revenues and costs through rates, prices or additional sales, it could reduce future net income and cash flows.

Ohio Power Co [Member]
 
Rate Matters

OPCo Rate Matters

 

Ohio Electric Security Plan Filing

 

2009 – 2011 ESP

 

The PUCO issued an order in March 2009 that modified and approved the ESP which established rates at the start of the April 2009 billing cycle through 2011. OPCo collected the 2009 annualized revenue increase over the last nine months of 2009. The order also provided a phase-in FAC, which was authorized to be recovered through a non-bypassable surcharge over the period 2012 through 2018. The PUCO's March 2009 order was appealed to the Supreme Court of Ohio, which issued an opinion and remanded certain issues back to the PUCO.

 

In October 2011, the PUCO issued an order in the remand proceeding. As a result, OPCo ceased collection of POLR billings in November 2011 and recorded a write-off in 2011 related to POLR collections for the period June 2011 through October 2011. In February 2012, the Ohio Consumers' Counsel and the IEU filed appeals of that order with the Supreme Court of Ohio challenging various issues, including the PUCO's refusal to order retrospective relief concerning the POLR charges collected during 2009 – 2011 and various aspects of the approved environmental carrying charge, which, if ordered, could reduce OPCo's net deferred fuel costs up to the total balance. As of June 30, 2013, OPCo's net deferred fuel balance was $484 million, excluding unrecognized equity carrying costs. A decision from the Supreme Court of Ohio is pending.

 

In January 2011, the PUCO issued an order on the 2009 SEET filing, which resulted in a write-off in 2010 and a subsequent refund to customers during 2011. The IEU and the Ohio Energy Group filed appeals with the Supreme Court of Ohio challenging the PUCO's SEET decision. In December 2012, the Supreme Court of Ohio issued an order which rejected all of the intervenors' challenges and affirmed the PUCO decision.

 

The 2009 SEET order gave consideration for a future commitment to invest $20 million to support the development of a large solar farm. In January 2013, the PUCO found there was not a need for the large solar farm. The PUCO noted that OPCo remains obligated to spend $20 million on this solar project or another project by the end of 2013. Management continues to evaluate other investment alternatives.

 

In July 2011, OPCo filed its 2010 SEET filing with the PUCO based upon the approach in the PUCO's 2009 order. Subsequent testimony and legal briefs from intervenors recommended a refund of up to $62 million of 2010 earnings, which included off-system sales in the SEET calculation. In December 2011, the PUCO staff filed testimony that recommended a $23 million refund of 2010 earnings. OPCo provided a reserve based upon management's estimate of the probable amount for a PUCO-ordered SEET refund. OPCo is required to file its 2011 SEET filing with the PUCO on a separate CSPCo and OPCo company basis. The PUCO approved OPCo's requests to file the SEET for 2011 and 2012 one month after the PUCO issues an order on the 2010 SEET. Management does not currently believe that there were significantly excessive earnings in 2011 for either CSPCo or OPCo or in 2012 for OPCo. Additionally, management does not currently believe that there will be significantly excessive earnings in 2013 for OPCo.

 

In August 2012, the PUCO issued an order in a separate proceeding which implemented a Phase-In Recovery Rider (PIRR) to recover deferred fuel costs in rates beginning September 2012. The PUCO ruled that carrying charges should be calculated without an offset for accumulated deferred income taxes and that a long-term debt rate should be applied when collections begin. In November 2012, OPCo filed an appeal at the Supreme Court of Ohio claiming a long-term debt rate modified the previously adjudicated 2009 – 2011 ESP order, which granted a weighted average cost of capital rate. The IEU and the Ohio Consumers' Counsel also filed appeals at the Supreme Court of Ohio in November 2012 arguing that the PUCO should have reduced the deferred fuel balance to reflect the prior “improper” collection of POLR revenues and reduced carrying costs due to an accumulated deferred income tax credit. These appeals could reduce OPCo's net deferred fuel balance up to the total balance, which could reduce future net income and cash flows. A decision from the Supreme Court of Ohio is pending.

 

Management is unable to predict the outcome of the unresolved litigation discussed above. Depending on the rulings in these proceedings, it could reduce future net income and cash flows and impact financial condition.

 

June 2012 – May 2015 ESP Including Capacity Charge

 

In August 2012, the PUCO issued an order which adopted and modified a new ESP that establishes base generation rates through May 2015, which was generally upheld in rehearing orders in January and March 2013.

 

As part of the ESP decision, the PUCO ordered OPCo to conduct an energy-only auction for 10% of the SSO load with delivery beginning six months after the receipt of final orders in both the ESP and corporate separation cases and extending through May 2015. The initiation of the auction is pending the issuance of an order by the PUCO in a separate docket. The PUCO also ordered OPCo to conduct energy-only auctions for an additional 50% of the SSO load with delivery beginning June 2014 through May 2015 and for the remaining 40% of the SSO load for delivery from January 2015 through May 2015. OPCo will conduct energy and capacity auctions for its entire SSO load for delivery starting in June 2015.

 

In July 2012, the PUCO issued an order in a separate capacity proceeding which stated that OPCo must charge CRES providers the Reliability Pricing Model (RPM) price and authorized OPCo to defer a portion of its incurred capacity costs not recovered from CRES providers up to $188.88/MW day. The RPM price is approximately $33/MW day through May 2014. In December 2012, various parties filed notices of appeal of the capacity costs decision with the Supreme Court of Ohio. As of June 30, 2013, OPCo's incurred deferred capacity costs balance of $171 million, including debt carrying costs, was recorded in Regulatory Assets on the balance sheet.

 

As part of the August 2012 ESP order, the PUCO established a non-bypassable Retail Stability Rider (RSR), effective September 2012. The RSR is expected to provide approximately $500 million of revenue over the ESP period and will be collected from customers at $3.50/MWh through May 2014 and $4.00/MWh for the period June 2014 through May 2015, with $1.00/MWh applied to the recovery of deferred capacity costs. In August 2012, the IEU filed an action with the Supreme Court of Ohio stating, among other things, that OPCo's collection of its capacity costs is illegal. In April 2013, the Supreme Court of Ohio dismissed the IEU's action.

 

In January and March 2013, the PUCO issued its Orders on Rehearing for the ESP which generally upheld its August 2012 order including the implementation of the RSR. The PUCO clarified that a final reconciliation of revenues and costs would be permitted for any over- or under-recovery on several riders including fuel. In addition, the PUCO addressed certain issues around the energy auctions while other SSO issues related to the energy auctions were deferred to a separate docket related to the competitive bid process (CBP). In April and May 2013, OPCo and various intervenors filed appeals with the Supreme Court of Ohio challenging portions of the PUCO's ESP order.

 

In June 2013, intervenors in the competitive bid process (CBP) docket filed recommendations that include prospective rate reductions for capacity and non-energy FAC issues.  OPCo maintains that the August 2012 ESP order fixed OPCo's non-energy generation rates through December 31, 2014 and ordered the application of a $188.88/MW day price for capacity for non-shopping customers effective January 1, 2015. However, intervenors maintained that OPCo's non-energy generation rates should be reduced prior to January 1, 2015 to blend the $188.88/MW day capacity price in proportion to the percentage of energy planned to be auctioned (10% prior to June 2014 and 60% for the period June 1, 2014 through December 31, 2014). An additional proposal to prospectively offset deferred capacity costs based upon the results of the energy-only auctions was not quantified and OPCo maintains that proposal should not be adopted in light of prior PUCO orders. Hearings related to the CBP were held at the PUCO in June and July 2013. 

 

If OPCo is ultimately not permitted to fully collect its ESP rates including the RSR, and its deferred capacity costs, it could reduce future net income and cash flows and impact financial condition.

Storm Damage Recovery Rider (SDRR)

 

In December 2012, OPCo submitted an application with the PUCO to establish initial SDRR rates. The SDRR seeks recovery of 2012 incremental storm distribution expenses over twelve months starting with the effective date of the SDRR as approved by the PUCO. OPCo also requested approval of a weighted average cost of capital carrying charge if recovery of these costs did not begin prior to April 2013. In May 2013, intervenors filed comments with various recommendations including reductions in the amount of storm costs recoverable up to the amount deferred, an extended recovery period, and an additional review of the storm costs including the allocation of costs to capital. As of June 30, 2013, OPCo recorded $61 million in Regulatory Assets on the balance sheet related to 2012 storm damage. If OPCo is not ultimately permitted to recover these storm costs, it could reduce future net income and cash flows and impact financial condition.

2009 Fuel Adjustment Clause Audit

 

The PUCO selected an outside consultant to conduct an audit of OPCo's FAC for 2009. The outside consultant provided its audit report to the PUCO. In January 2012, the PUCO ordered that the remaining $65 million in proceeds from a 2008 coal contract settlement agreement be applied against OPCo's under-recovered fuel balance. In April 2012, on rehearing, the PUCO ordered that the settlement credit only needed to reflect the Ohio retail jurisdictional share of the gain not already flowed through the FAC with carrying charges. OPCo recorded a $30 million net favorable adjustment on the statement of income in the second quarter of 2012. The January 2012 PUCO order also stated that a consultant should be hired to review the coal reserve valuation and recommend whether any additional value should benefit ratepayers. Management is unable to predict the outcome of any future consultant recommendation regarding valuation of the coal reserve. If the PUCO ultimately determines that additional amounts should benefit ratepayers as a result of the consultant's review of the coal reserve valuation, it could reduce future net income and cash flows and impact financial condition.

 

In August 2012, intervenors filed an appeal with the Supreme Court of Ohio claiming the settlement credit ordered by the PUCO should have reflected the remaining gain not already flowed through the FAC with carrying charges, which, if ordered, would be $35 million plus carrying charges. If the Supreme Court of Ohio ultimately determines that additional amounts should benefit ratepayers, it could reduce future net income and cash flows and impact financial condition.

2010 and 2011 Fuel Adjustment Clause Audits

 

The PUCO-selected outside consultant issued its 2010 and 2011 FAC audit reports which included a recommendation that the PUCO reexamine the carrying costs on the deferred FAC balance and determine whether the carrying costs on the balance should be net of accumulated income taxes. As of June 30, 2013, the amount of OPCo's carrying costs that could potentially be reduced due to the accumulated income tax issue is estimated to be $34 million, including $18 million of unrecognized equity carrying costs. These amounts include the carrying costs exposure of the 2009 FAC audit, which has been appealed by an intervenor to the Supreme Court of Ohio. Decisions from the PUCO are pending. Management is unable to predict the outcome of these proceedings. If the PUCO orders result in a reduction to the FAC deferral, it could reduce future net income and cash flows and impact financial condition.

Ormet Interim Arrangement

 

Ormet, a large aluminum company, filed an application with the PUCO for approval of an interim arrangement governing the provision of generation service to Ormet. This interim arrangement was approved by the PUCO and was effective from January 2009 through September 2009. In March 2009, the PUCO approved a FAC in the ESP filing and the FAC aspect of the ESP order was upheld by the Supreme Court of Ohio. The approval of the FAC as part of the ESP, together with the PUCO approval of the interim arrangement, provided the basis to record a regulatory asset for the difference between the approved market price and the rate paid by Ormet. Through September 2009, the last month of the interim arrangement, OPCo had $64 million of deferred FAC costs related to the interim arrangement, excluding $2 million of unrecognized equity carrying costs. In November 2009, OPCo requested that the PUCO approve recovery of the deferral under the interim agreement plus a weighted average cost of capital carrying charge. The deferral amount is included in OPCo's FAC phase-in deferral balance. In the 2009 – 2011 ESP proceeding, intervenors requested that OPCo be required to refund the Ormet-related regulatory asset and requested that the PUCO prevent OPCo from collecting the Ormet-related revenues in the future. The PUCO did not take any action on this request. The intervenors raised the issue again in response to OPCo's November 2009 filing to approve recovery of the deferral under the interim agreement. This issue remains pending before the PUCO. If OPCo is not ultimately permitted to fully recover its requested deferrals under the interim arrangement, it could reduce future net income and cash flows and impact financial condition.

 

Special Rate Mechanism for Ormet

 

In October 2012, the PUCO issued an order approving a delayed payment plan for Ormet's October and November 2012 power billings totaling $27 million to be paid in equal monthly installments over the period January 2014 to May 2015 without interest. In the event Ormet does not pay its $27 million obligation, the PUCO permitted OPCo to recover the unpaid balance, up to $20 million, in the economic development rider. To the extent unpaid amounts exceed $20 million, it could reduce future net income and cash flows and impact financial condition.

 

In February 2013, Ormet filed Chapter 11 bankruptcy proceedings in the state of Delaware but is current on all payments due to OPCo. In June 2013, Ormet filed a motion with the PUCO to amend its contract with OPCo which currently provides for services through 2018. The proposed amendments would allow Ormet to purchase power from a third party beginning January 2014. In July 2013, OPCo filed its objections with the PUCO which included a recommendation to have Ormet pay an exit fee as a potential resolution to address the financial concerns associated with amending the current contract. Hearings at the PUCO are scheduled for August 2013. As of June 30, 2013, OPCo has a regulatory asset of $20 million and a net receivable of $6 million recorded related to the special rate mechanism for Ormet.

Ohio IGCC Plant

 

In March 2005, OPCo filed an application with the PUCO seeking authority to recover costs of building and operating an IGCC power plant. As of June 30, 2013, OPCo has collected $24 million in pre-construction costs authorized in a June 2006 PUCO order. Intervenors have filed motions with the PUCO requesting OPCo refund all collected pre-construction costs to Ohio ratepayers with interest.

 

Management cannot predict the outcome of these proceedings concerning the Ohio IGCC plant or what effect, if any, these proceedings could have on future net income and cash flows. However, if OPCo is required to refund pre-construction costs collected, it could reduce future net income and cash flows and impact financial condition.

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, the Registrant Subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

 

Regulatory Assets Not Yet Being Recovered

     OPCo
     June 30, December 31,
     2013 2012
 Noncurrent Regulatory Assets (in thousands)
 Regulatory assets not yet being recovered pending future proceedings:      
          
 Regulatory Assets Currently Earning a Return      
  Economic Development Rider $ 13,533 $ 13,213
 Regulatory Assets Currently Not Earning a Return      
  Storm Related Costs   58,512   61,828
  Ormet Delayed Payment Arrangement   20,000   5,453
  Other Regulatory Assets Not Yet Being Recovered   706   30
 Total Regulatory Assets Not Yet Being Recovered $ 92,751 $ 80,524

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

Corporate Separation

 

In October 2012, the PUCO issued an order which approved the corporate separation of OPCo's generation assets including the transfer of OPCo's generation assets at net book value to AEPGenCo. AEPGenCo will also assume the associated generation liabilities. In June 2013, the IEU filed an appeal with the Supreme Court of Ohio claiming the PUCO order approving the corporate separation was unlawful.

 

Also in October 2012, filings at the FERC were submitted related to corporate separation. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo. See the “Corporate Separation and Termination of Interconnection Agreement” section of FERC Rate Matters.

FERC Rate Matters

 

Corporate Separation and Termination of Interconnection Agreement – Affecting APCo, I&M and OPCo

 

In October 2012, the AEP East Companies submitted several filings with the FERC seeking approval to fully separate OPCo's generation assets from its distribution and transmission operations. The filings requested approval to transfer at net book value approximately 9,200 MW of OPCo-owned generation assets to a new wholly-owned company, AEPGenCo. The AEP East Companies also requested FERC approval to transfer at net book value OPCo's current two-thirds ownership (867 MW) in Amos Plant, Unit 3 to APCo and transfer at net book value OPCo's Mitchell Plant to APCo and KPCo in equal one-half interests (780 MW each). These transfers are proposed to be effective December 31, 2013. In April 2013, the FERC issued orders approving the transfer of OPCo's generation assets to AEPGenCo, the Amos Plant and Mitchell Plant asset transfers to APCo and KPCo and the merger of APCo and WPCo. In May 2013, the IEU petitioned the FERC for rehearing of its order granting OPCo authority to implement corporate separation by transferring its generation assets to AEPGenCo. OPCo has contested the petition for rehearing, which remains pending before the FERC. Similar asset transfer filings have been made at the Virginia SCC and the WVPSC. See the “Plant Transfers” section of APCo Rate Matters.

 

Additionally, the AEP East Companies requested FERC approval, effective January 1, 2014, to terminate the existing Interconnection Agreement and approve a Power Coordination Agreement (PCA) among APCo, I&M and KPCo with AEPSC as the agent to coordinate the participants' respective power supply resources. Under the PCA, APCo and I&M would be individually responsible for planning their respective capacity obligations and there would be no capacity equalization charges/credits on deficit/surplus companies. Further, the PCA allows, but does not obligate, APCo and I&M to participate collectively under a common fixed resource requirement capacity plan in PJM and to participate in specified collective off-system sales and purchase activities. Intervenors have opposed several of these filings. The AEP East Companies responded to intervenor comments and filed a revised PCA at the FERC in March 2013. The revised PCA included certain clarifying wording changes that have been agreed upon by intervenors. A decision is pending at the FERC.

 

If APCo and/or I&M experience decreases in revenues or increases in expenses as a result of changes to their relationship with affiliates and are unable to recover the change in revenues and costs through rates, prices or additional sales, it could reduce future net income and cash flows.

Public Service Co Of Oklahoma [Member]
 
Rate Matters

PSO Rate Matters

 

Oklahoma Environmental Compliance Plan

 

In September 2012, based upon an agreement with the Federal EPA, the State of Oklahoma and other parties, PSO filed an environmental compliance plan with the OCC reflecting the retirement of Northeastern Station (NES) Unit 4 in 2016 and additional environmental controls on NES Unit 3 to continue operations through 2026. The plan requested approval for (a) an estimated $210 million of new environmental investment, excluding AFUDC and overheads of $46 million, that will be incurred prior to 2016 at NES Unit 3, (b) accelerated recovery through 2026 of the net book value of NES Units 3 and 4 (combined net book value of the two units is $231 million as of June 30, 2013), (c) an estimated $83 million of new investment incurred through 2016 at various gas units and (d) a new 15-year purchase power agreement (PPA) with a nonaffiliated entity, effective in 2016, with cost recovery through a rider, including an annual earnings component of $3 million. Although the environmental compliance plan does not seek to put any new costs into rates at this time, PSO anticipates seeking cost recovery in a future rate proceeding.

 

In January 2013, testimony filed by the OCC staff and the Oklahoma Office of the Attorney General (OOAG) recommended no earnings component on the PPA and to delay final decisions until 2020 on parts of the plan including cost recovery of the net book value of NES Unit 3 and any increases in fuel costs due to reductions in the output of energy from NES Unit 3 beginning in 2021. The testimony recommended that cost recovery could extend past 2026 on parts of the plan and recommended a $175 million cost cap on NES Unit 3 environmental investment, excluding AFUDC and overheads.

 

In March 2013, the OCC staff and the OOAG filed additional testimony revising the recommended cost cap on NES Unit 3 to $210 million, excluding AFUDC and overheads, and recommended conditional approval of the planned NES Unit 3 retirement subject to OCC approval in 2020 provided the planned retirement is consistent with environmental rules at that time.

 

Also, an intervenor representing some of PSO's large industrial users opposed the majority of PSO's plan, including recommending no cost recovery of NES Units 3 and 4 book value amounts not recovered at the time of their retirement and no recovery of the PPA costs, including earnings on the PPA. In February 2013, the OCC staff requested a stay in this proceeding, which was granted by the OCC in March 2013. In July 2013, the OCC staff filed a motion to lift the stay and dismiss PSO's environmental compliance plan case without prejudice. A hearing on the motion will be held in August 2013. If this case is dismissed, PSO will address the environmental compliance plan issues in future regulatory proceedings when it seeks cost recovery of the plan.

 

If PSO is ultimately not permitted to fully recover its net book value of NES Units 3 and 4 and other environmental compliance costs, it could reduce future net income and cash flows and impact financial condition.

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, the Registrant Subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

 

Regulatory Assets Not Yet Being Recovered

     PSO
     June 30, December 31,
     2013 2012
 Noncurrent Regulatory Assets (in thousands)
 Regulatory assets not yet being recovered pending future proceedings:      
          
 Regulatory Assets Currently Not Earning a Return      
  Other Regulatory Assets Not Yet Being Recovered $ 803 $ 423
 Total Regulatory Assets Not Yet Being Recovered $ 803 $ 423

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.

Southwestern Electric Power Co [Member]
 
Rate Matters

SWEPCo Rate Matters

 

Turk Plant

 

SWEPCo constructed the Turk Plant, a new base load 600 MW pulverized coal ultra-supercritical generating unit in Arkansas, which was placed into service in December 2012. SWEPCo owns 73% (440 MW) of the Turk Plant and operates the facility. As of June 30, 2013, excluding costs attributable to its joint owners and a $62 million provision for a Texas capital cost cap, SWEPCo has capitalized approximately $1.8 billion of expenditures, including AFUDC and capitalized interest of $328 million and related transmission costs of $118 million.

 

The APSC granted approval for SWEPCo to build the Turk Plant by issuing a Certificate of Environmental Compatibility and Public Need (CECPN) for the SWEPCo Arkansas jurisdictional share of the Turk Plant (approximately 20%). Following an appeal by certain intervenors, the Arkansas Supreme Court issued a decision that reversed the APSC's grant of the CECPN. In June 2010, in response to an Arkansas Supreme Court decision, the APSC issued an order which reversed and set aside the previously granted CECPN. The Arkansas portion of the Turk Plant output is currently not subject to cost-based rate recovery and is being sold into the SPP market.

 

The PUCT approved a Certificate of Convenience and Necessity (CCN) for the Turk Plant with the following conditions: (a) a cap on the recovery of jurisdictional capital costs for the Turk Plant based on the previously estimated $1.522 billion projected construction cost, excluding AFUDC and related transmission costs, (b) a cap on recovery of annual CO2 emission costs at $28 per ton through the year 2030 and (c) a requirement to hold Texas ratepayers financially harmless from any adverse impact related to the Turk Plant not being fully subscribed to by other utilities or wholesale customers. SWEPCo appealed the PUCT's order contending the two cost cap restrictions are unlawful. The Texas Industrial Energy Consumers (TIEC) filed an appeal contending that the PUCT's grant of a conditional CCN for the Turk Plant should be revoked because the Turk Plant is unnecessary to serve retail customers. The Texas District Court and the Texas Court of Appeals affirmed the PUCT's order in all respects. In April 2012, SWEPCo and the TIEC filed petitions for review at the Supreme Court of Texas, which were denied in March 2013. In April 2013, SWEPCo and the TIEC filed motions for rehearing at the Supreme Court of Texas. In May 2013, the Supreme Court of Texas requested the PUCT and the TIEC respond to SWEPCo's motion.

 

If SWEPCo cannot recover all of its investment and expenses related to the Turk Plant, it could reduce future net income and cash flows and impact financial condition.

 

2012 Texas Base Rate Case

 

In July 2012, SWEPCo filed a request with the PUCT to increase annual base rates by $83 million, primarily due to the Turk Plant, based upon an 11.25% return on common equity to be effective January 2013. The requested base rate increase included a return on and of the Texas jurisdictional share (approximately 33%) of the Turk Plant generation investment as of December 2011, total Turk Plant related estimated transmission investment costs and associated operation and maintenance costs. The filing also (a) increased depreciation expense due to the decrease in the average remaining life of the Welsh Plant to account for the change in the retirement date of the Welsh Plant, Unit 2 from 2040 to 2016, (b) proposed increased vegetation management expenditures and (c) included a return on and of the Stall Unit as of December 2011 and associated operation and maintenance costs.

 

In September 2012, an Administrative Law Judge (ALJ) issued an order that granted the establishment of SWEPCo's existing rates as temporary rates beginning in late January 2013, subject to true-up to the final PUCT-approved rates.

 

In December 2012, several intervenors, including the PUCT staff, filed testimony that recommended an annual base rate increase between $16 million and $51 million based upon a return on common equity between 9% and 9.55%. In addition, two intervenors recommended that the Turk Plant be excluded from rate base. In May 2013, the ALJ issued a proposal for decision (PFD) and added clarifications in July 2013. The PFD, as clarified, made various recommendations including (a) an annual base rate increase of approximately $41 million based upon a return on common equity of 9.65%, (b) the disallowance of the Turk Plant capital costs in excess of the investment and committed costs as of June 2010 plus the cost to retrofit Welsh Plant, Unit 2 which, as of June 30, 2013, SWEPCo estimates could result in a write-off of approximately $74 million (in excess of the $62 million reserve previously recorded related to the Texas capital cost cap) and (c) the exclusion, until SWEPCo's next Texas base rate case, of the Turk Plant transmission line investment that was not in service at the end of the test year. A decision from the PUCT is expected in the third quarter of 2013. If the PUCT does not approve full cost recovery of SWEPCo's Texas jurisdictional share of assets, it could reduce future net income and cash flows and impact financial condition.

2012 Louisiana Formula Rate Filing

 

In 2012, SWEPCo initiated a proceeding to establish new formula base rates in Louisiana, including recovery of the Louisiana jurisdictional share (approximately 29%) of the Turk Plant. In February 2013, a settlement was filed and approved by the LPSC. The settlement increased Louisiana total rates by approximately $2 million annually, effective March 2013, which consisted of an increase in base rates of approximately $85 million annually offset by a decrease in fuel and other rates of approximately $83 million annually. The March 2013 base rates are based on a 10% return on common equity and cost recovery of the Louisiana jurisdictional share of the Turk Plant and Stall Unit, subject to refund based on the staff review of the cost of service and the prudence review of the Turk Plant. The settlement also provided that the LPSC will review base rates in 2014 and 2015 and that SWEPCo will recover all non-fuel Turk Plant costs and a full weighted-average cost of capital return on the Turk Plant portion of rate base, effective January 2013. In May 2013, SWEPCo filed testimony in the prudence review of the Turk Plant. If the LPSC orders refunds based upon the pending staff review of the cost of service or the prudence review of the Turk Plant, it could reduce future net income and cash flows and impact financial condition.

Flint Creek Plant Environmental Controls

 

In February 2012, SWEPCo filed a petition with the APSC seeking a declaratory order to install environmental controls at the Flint Creek Plant to comply with the standards established by the CAA. The estimated cost of the project is $408 million, excluding AFUDC and company overheads. As a joint owner of the Flint Creek Plant, SWEPCo's portion of those costs is estimated at $204 million. As of June 30, 2013, SWEPCo has incurred $24 million related to this project, including AFUDC and company overheads. In July 2013, the APSC approved the request to install environmental controls at the Flint Creek Plant.

3. RATE MATTERS

 

As discussed in the 2012 Annual Report, the Registrant Subsidiaries are involved in rate and regulatory proceedings at the FERC and their state commissions. The Rate Matters note within the 2012 Annual Report should be read in conjunction with this report to gain a complete understanding of material rate matters still pending that could impact net income, cash flows and possibly financial condition. The following discusses ratemaking developments in 2013 and updates the 2012 Annual Report.

 

Regulatory Assets Not Yet Being Recovered

     SWEPCo
     June 30, December 31,
     2013 2012
 Noncurrent Regulatory Assets (in thousands)
 Regulatory assets not yet being recovered pending future proceedings:      
          
 Regulatory Assets Currently Not Earning a Return      
  Rate Case Expenses $ 7,234 $ 4,517
  Mountaineer Carbon Capture and Storage      
   Commercial Scale Facility   2,295   2,295
  Other Regulatory Assets Not Yet Being Recovered   2,373   2,188
 Total Regulatory Assets Not Yet Being Recovered $ 11,902 $ 9,000

If these costs are ultimately determined not to be recoverable, it could reduce future net income and cash flows and impact financial condition.