XML 72 R69.htm IDEA: XBRL DOCUMENT v3.19.3
Commitments and Contingencies (Details)
9 Months Ended
Sep. 30, 2019
USD ($)
site
Purchase Obligations  
Remaining three months of 2019 $ 217,000,000
2020 745,000,000
2021 614,000,000
2022 412,000,000
2023 330,000,000
2024 265,000,000
2025 and beyond $ 1,846,000,000
Performance Guarantees & Product Warranties [Abstract]  
Number of surety bond obligations outstanding 63
Performance guarantee obligations outstanding face amount $ 627,000,000
Percentage of work yet to be completed on projects with open surety bonds 35.00%
Guarantor obligations, maximum exposure, undiscounted $ 498,000,000
Legal, Environmental and Other Matters  
Asset retirement obligation 75,000,000
Minimum [Member]  
Legal, Environmental and Other Matters  
Estimated capital expenditure to clean ash ponds 60,000,000
Maximum [Member]  
Legal, Environmental and Other Matters  
Estimated capital expenditure to clean ash ponds 80,000,000
Minnesota Service Territory [Member]  
Legal, Environmental and Other Matters  
Liability recorded for environmental loss contingencies 9,000,000
Minnesota Service Territory [Member] | Minimum [Member]  
Legal, Environmental and Other Matters  
Estimated remediation costs for the Minnesota sites $ 7,000,000
Years to resolve contingency 5 years
Minnesota Service Territory [Member] | Maximum [Member]  
Legal, Environmental and Other Matters  
Estimated remediation costs for the Minnesota sites $ 51,000,000
Years to resolve contingency 50 years
Indiana Gas Service Territory [Member]  
Legal, Environmental and Other Matters  
Environmental remediation number of sites with potential remedial responsibility | site 26
CERC Corp [Member]  
Purchase Obligations  
Remaining three months of 2019 $ 160,000,000
2020 528,000,000
2021 429,000,000
2022 235,000,000
2023 177,000,000
2024 169,000,000
2025 and beyond 1,483,000,000
CERC Corp [Member] | Minnesota Service Territory [Member]  
Legal, Environmental and Other Matters  
Liability recorded for environmental loss contingencies 7,000,000
CERC Corp [Member] | Minnesota Service Territory [Member] | Minimum [Member]  
Legal, Environmental and Other Matters  
Estimated remediation costs for the Minnesota sites $ 4,000,000
Years to resolve contingency 30 years
CERC Corp [Member] | Minnesota Service Territory [Member] | Maximum [Member]  
Legal, Environmental and Other Matters  
Estimated remediation costs for the Minnesota sites $ 32,000,000
Years to resolve contingency 50 years
Minnehaha Academy Gas Explosion [Member]  
Legal, Environmental and Other Matters  
Contested amount of fines imposed $ 200,000
Minnehaha Academy Gas Explosion [Member] | CERC Corp [Member]  
Legal, Environmental and Other Matters  
Contested amount of fines imposed $ 200,000