XML 68 R55.htm IDEA: XBRL DOCUMENT v3.25.3
Electric utility segment - Public Utility, Measured under Performance (Details)
$ in Millions
9 Months Ended 12 Months Ended
Sep. 30, 2025
USD ($)
MWh
Dec. 31, 2024
USD ($)
Regulatory Projects and Legal Obligations [Line Items]    
Interconnection requirements study, (penalties) rewards   $ 0.0
Hawaiian Electric Company, Inc. and Subsidiaries    
Regulatory Projects and Legal Obligations [Line Items]    
Transmission and distribution-caused, maximum penalty $ 3.6  
Transmission and distribution-caused, (penalties) rewards   (1.0)
Call center performance, maximum penalty or reward $ 1.4  
Call center, (penalties) rewards   0.0
Interpolated RPS rate goal, after year three (in dollars per MWh) | MWh 10  
Failure to meet RPS targets, penalty rate (in dollars per MWh) | MWh 20  
Renewable portfolio standard, (penalties) rewards   1.9
Interconnection approval, maximum reward $ 3.0  
Interconnection approval, maximum penalty 0.9  
Interconnection approval, (penalties) rewards   2.4
Generated-caused, maximum penalties 1.0  
Performance incentive mechanism, (penalties) rewards $ 0.3 6.2
Hawaii Electric Light Company, Inc    
Regulatory Projects and Legal Obligations [Line Items]    
Phase 1 RFP, (penalties) rewards   0.2
Generation caused, (penalties) rewards   (0.1)
Collective shared savings mechanism, (penalties) rewards   2.8
Performance incentive mechanism, (penalties) rewards   3.4
Hawaiian Electric, Parent    
Regulatory Projects and Legal Obligations [Line Items]    
Collective shared savings mechanism, retained percentage 20.00%  
Performance incentive mechanism, (penalties) rewards   2.5
Maui Electric    
Regulatory Projects and Legal Obligations [Line Items]    
Phase 1 RFP, (penalties) rewards $ 0.3  
Performance incentive mechanism, (penalties) rewards   $ 0.3