XML 99 R77.htm IDEA: XBRL DOCUMENT v3.25.0.1
Electric utility segment - Regulatory Proceedings (Details)
$ in Thousands
12 Months Ended
Dec. 04, 2024
Dec. 23, 2020
USD ($)
Dec. 31, 2024
USD ($)
MWh
project
Dec. 31, 2021
contract
Jun. 30, 2024
USD ($)
Mar. 31, 2024
USD ($)
agreement
Mar. 11, 2024
USD ($)
Dec. 31, 2023
USD ($)
Jun. 30, 2023
USD ($)
Jun. 17, 2022
mechanism
Dec. 31, 2020
USD ($)
Regulatory Projects and Legal Obligations [Line Items]                      
PUC proposal period (in days)   45 days                  
Public utilities, modified pilot process proposal period (in days)     15 days                
Pilot process annual cap     $ 10,000                
Pilot processes, deferred and recovered annual expenditures, period     12 months                
Low-to-moderate income energy efficiency PIM, accrued award                 $ 10    
Hawaiian Electric Company, Inc. and Subsidiaries                      
Regulatory Projects and Legal Obligations [Line Items]                      
Number of performance incentive mechanisms | mechanism                   2  
Multi-year rate period (in years)   5 years                  
Customer dividend, negative adjustment percentage   0.22%                  
Savings commitment liability, annual rate   $ 6,600                  
Actual return on equity, dead band percentage, above or below target     3.00%                
Authorized ROE     9.50%                
Percentage sharing between customers and utilities     0.50                
Actual earnings, above or below dead band     1.50%                
Percentage sharing for any further difference     0.90                
MPIR and EPRM requested amount     $ 38,000                
EPRM number of projects approved | project     4                
EPRM project costs     $ 218,500                
EPRM number of projects | project     2                
EPRM total project costs     $ 294,200                
Deferred cost recovery approved             $ 3,000        
Request period 12 months                    
Target performance historical measurement period (in years)     10 years                
Service reliability, maximum penalty, percent of return on equity     20.00%                
Maximum penalty, pending adjusted amount     $ 3,600                
Service reliability, estimated penalties     $ 1,000                
Dead band percentage above or below target     3.00%                
Call center performance, maximum penalty, percent     8.00%                
Call center performance, maximum penalty, pending adjusted amount     $ 1,400                
Number of contracts which qualified for incentives | contract       7              
Public utility, incentives accrued                     $ 1,700
Number of incentive earned power purchase agreements | agreement           2          
Interpolated statutory RPS goal rate | MWh     20                
Interpolated statutory RPS goal rate, year three | MWh     15                
Interpolated statutory RPS goal rate, remainder of MRP | MWh     10                
Penalty rate for failure to meet RPS targets | MWh     20                
Public utilities, renewable portfolio standard performance incentive mechanism, accrued estimated rewards     $ 1,900                
Interconnection approval PIM, annual maximum reward     3,000                
Interconnection approval PIM, annual maximum penalty     900                
Interconnection approval PIM, accrued estimated rewards     2,400                
Low-to-moderate income energy efficiency PIM, rewards cap     $ 2,000                
Target performance historical measurement period (in years)     10 years                
Maximum penalty, percent of return on equity     0.03%                
Pending adjusted amount     $ 1,000                
Target performance period (in months)     10 months                
Target deadband period (in months)     2 months                
Accrued estimated rewards, net of penalties     $ 6,200                
Hawaiian Electric Company, Inc. and Subsidiaries | Schofield Generation Station                      
Regulatory Projects and Legal Obligations [Line Items]                      
Major project interim recovery requested amount     16,100                
Hawaiian Electric Company, Inc. and Subsidiaries | West Loch PV Project                      
Regulatory Projects and Legal Obligations [Line Items]                      
Major project interim recovery requested amount     3,200                
Hawaiian Electric Company, Inc. and Subsidiaries | Grid Modernization Strategy Phase 1 Project                      
Regulatory Projects and Legal Obligations [Line Items]                      
Major project interim recovery requested amount     16,100                
Hawaiian Electric Company, Inc. and Subsidiaries | Waiawa UFLS Project                      
Regulatory Projects and Legal Obligations [Line Items]                      
EPRM requested amount     100                
Hawaiian Electric Company, Inc. and Subsidiaries | Waena Switchyard/Synchronous Project                      
Regulatory Projects and Legal Obligations [Line Items]                      
EPRM requested amount     $ 2,500                
Hawaiian Electric                      
Regulatory Projects and Legal Obligations [Line Items]                      
Public utility, incentives accrued           $ 100   $ 100      
Public utilities retained percentage     20.00%                
Accrued estimated rewards, net of penalties     $ 2,500                
Hawaii Electric Light                      
Regulatory Projects and Legal Obligations [Line Items]                      
Public utility, incentives accrued         $ 100            
Interconnection approval PIM, accrued estimated rewards     2,800                
Accrued penalties     100                
Accrued estimated rewards, net of penalties     3,400                
Maui Electric                      
Regulatory Projects and Legal Obligations [Line Items]                      
Accrued estimated rewards, net of penalties     $ 300