Electric utility segment - Major Project Interim Recovery and Performance Incentive Mechanisms (Details) - Hawaiian Electric Company, Inc. and Subsidiaries
1 Months Ended 3 Months Ended 12 Months Ended
Feb. 07, 2020
USD ($)
Mar. 25, 2019
contract
Apr. 27, 2017
USD ($)
Dec. 31, 2019
USD ($)
May 31, 2019
USD ($)
Feb. 28, 2019
USD ($)
Dec. 31, 2018
USD ($)
Mar. 31, 2019
USD ($)
Dec. 31, 2019
USD ($)
Dec. 31, 2018
USD ($)
$ / kWh
Regulatory Projects and Legal Obligations [Line Items]                    
Threshold of capital expenditures in excess of customer contributions for qualification for major project interim recovery     $ 2,500,000              
Major project interim recovery requested amount     $ 3,600,000     $ 19,800,000        
Target performance historical measurement period                 10 years  
Service reliability, maximum penalty, percent of return on equity                 0.20%  
Maximum penalty, pending adjusted amount                 $ 6,700,000  
Dead band percentage above or below target                 3.00%  
Call center performance, maximum penalty, percent                 0.80%  
Call center performance, maximum penalty, pending adjusted amount                 $ 1,300,000  
Call center performance, maximum penalty amount       $ 300,000 $ 1,300,000   $ 2,100,000      
Performance incentive mechanism, savings calculation, energy price, renewable projects with storage capacity | $ / kWh                   0.115
Performance incentive mechanism, savings calculation, energy price, renewable energy-only projects | $ / kWh                   0.095
Performance incentive mechanism, expected savings percentage, phase 1                   20.00%
Performance incentive mechanism, savings calculation, incentive cap               $ 3,000,000   $ 3,500,000
Performance incentive mechanism, expected savings in Phase 2, January 2019               15.00%    
Performance incentive mechanism, expected savings in Phase 2, February 2019               10.00%    
Performance incentive mechanism, expected savings in Phase 2, March 2019               5.00%    
Performance incentive mechanism, penalty                 $ 0  
Number of contracts which qualified for incentives | contract   6                
Public utility, incentives accrued               $ 1,700,000    
Subsequent Event                    
Regulatory Projects and Legal Obligations [Line Items]                    
Major project interim recovery requested amount $ 24,200,000                  
Schofield Generation Station | Subsequent Event                    
Regulatory Projects and Legal Obligations [Line Items]                    
Major project interim recovery requested amount 19,200,000                  
West Loch PV Project | Subsequent Event                    
Regulatory Projects and Legal Obligations [Line Items]                    
Major project interim recovery requested amount 4,500,000                  
Grid Modernization Strategy Phase 1 Project | Subsequent Event                    
Regulatory Projects and Legal Obligations [Line Items]                    
Major project interim recovery requested amount $ 500,000