XML 23 R9.htm IDEA: XBRL DOCUMENT v3.8.0.1
Costs and Estimated Earnings on Uncompleted Contracts
12 Months Ended
Dec. 31, 2017
Contractors [Abstract]  
Costs and Estimated Earnings on Uncompleted Contracts
Costs and Estimated Earnings on Uncompleted Contracts
Long-term fixed-price electrical construction contracts in progress accounted for using the percentage-of-completion method as of December 31 for the years as indicated:
 
2017
 
2016
Costs incurred on uncompleted contracts
$
48,681,608

 
$
47,282,570

Estimated earnings
16,076,125

 
18,644,216

 
64,757,733

 
65,926,786

Less billings to date
58,849,655

 
59,458,744

Total
$
5,908,078

 
$
6,468,042

Included in the consolidated balance sheets under the following captions
 
 
 
Costs and estimated earnings in excess of billings on uncompleted contracts
$
6,074,346

 
$
7,313,099

Billings in excess of costs and estimated earnings on uncompleted contracts
(166,268
)
 
(845,057
)
Total
$
5,908,078

 
$
6,468,042


The amounts billed but not paid by customers pursuant to retention provisions of long-term electrical construction contracts were $3.3 million and $3.2 million as of December 31, 2017 and 2016, respectively, and are included in the accompanying consolidated balance sheets in accounts receivable and accrued billings. Retainage is expected to be collected within the next twelve months.