NOTE 23. COMMITMENTS, GUARANTEES, PRODUCT WARRANTIES AND OTHER LOSS CONTINGENCIES
COMMITMENTS. We had total investment commitments of $3,648 million and unfunded lending commitments, primarily at EFS, of $582 million at March 31, 2024. The investment commitments primarily comprise investments by our run-off insurance operations in other assets and investment securities of $3,570 million and included within these commitments are obligations to make investments in unconsolidated VIEs of $3,515 million. See Note 22 for further information.

As of March 31, 2024, in our Aerospace segment, we have committed to provide financing assistance of $2,676 million of future customer acquisitions of aircraft equipped with our engines.

GUARANTEES. Credit support. We have provided $909 million of credit support on behalf of certain customers or associated companies, predominantly joint ventures and partnerships, using arrangements such as standby letters of credit and performance guarantees, and a line of credit to support our consolidated subsidiaries. The liability for such credit support was $17 million.

Indemnification agreements – Continuing Operations. GE has obligations under the Tax Matters Agreement to indemnify GE HealthCare for certain tax costs and other indemnifications of $35 million, which are fully reserved. In addition, we have $285 million of other indemnification commitments, including representations and warranties in sales of business assets, for which we recorded a liability of $71 million.

Indemnification agreements - Discontinued Operations. Following the Separation of GE HealthCare on January 3, 2023, GE has remaining performance and bank guarantees on behalf of its former HealthCare business, with a maximum aggregate exposure of $25 million. GE also has obligations under the Transition Services Agreement and Tax Matters Agreement to indemnify GE HealthCare for certain technology and tax costs of $77 million, which are fully reserved. In addition, we have provided specific indemnities to other buyers of assets of our business that, in the aggregate, represent a maximum potential claim of $710 million with related reserves of $69 million. See Note 24 for further information on GE Vernova.

PRODUCT WARRANTIES. We provide for estimated product warranty expenses when we sell the related products. Because warranty estimates are forecasts that are based on the best available information, mostly historical claims experience, claims costs may differ from amounts provided. The liability for product warranties was $1,999 million and $2,053 million at March 31, 2024 and December 31, 2023.

LEGAL MATTERS. The following information supplements and amends the discussion of Legal Matters in Note 24 to the consolidated financial statements in our Annual Report on Form 10-K for the year ended December 31, 2023; refer to that discussion for information about previously reported legal matters that are not updated below. In the normal course of our business, we are involved from time to time in various arbitrations, class actions, commercial litigation, investigations and other legal, regulatory or governmental actions, including the significant matters described below that could have a material impact on our results of operations. In many proceedings, including the specific matters described below, it is inherently difficult to determine whether any loss is probable or even reasonably possible or to estimate the size or range of the possible loss, and accruals for legal matters are not recorded until a loss for a particular matter is considered probable and reasonably estimable. Given the nature of legal matters and the complexities involved, it is often difficult to predict and determine a meaningful estimate of loss or range of loss until we know, among other factors, the particular claims involved, the likelihood of success of our defenses to those claims, the damages or other relief sought, how discovery or other procedural considerations will affect the outcome, the settlement posture of other parties and other factors that may have a material effect on the outcome. For these matters, unless otherwise specified, we do not believe it is possible to provide a meaningful estimate of loss at this time. Moreover, it is not uncommon for legal matters to be resolved over many years, during which time relevant developments and new information must be continuously evaluated.
Alstom legacy legal matters. In 2015, GE acquired the Steam Power, Renewables and Grid businesses from Alstom, which prior to our acquisition were the subject of significant cases involving anti-competitive activities and improper payments. We had reserves of $391 million and $393 million at March 31, 2024 and December 31, 2023, respectively, for legal and compliance matters related to the legacy business practices that were the subject of cases in various jurisdictions. Allegations in these cases relate to claimed anti-competitive conduct or improper payments in the pre-acquisition period as the source of legal violations or damages. Given the significant litigation and compliance activity related to these matters and the ongoing efforts to resolve them, it is difficult to assess whether the disbursements will ultimately be consistent with the reserve established. The estimation of this reserve may not reflect the full range of uncertainties and unpredictable outcomes inherent in litigation and investigations of this nature, and at this time we are unable to develop a meaningful estimate of the range of reasonably possible additional losses beyond the amount of this reserve. Factors that can affect the ultimate amount of losses associated with these and related matters include the way cooperation is assessed and valued, prosecutorial discretion in the determination of damages, formulas for determining disgorgement, fines or penalties, the duration and amount of legal and investigative resources applied, political and social influences within each jurisdiction, and tax consequences of any settlements or previous deductions, among other considerations. Actual losses arising from claims in these and related matters could exceed the amount provided. With the spin-off of GE Vernova on April 2, 2024, the liabilities associated with these matters transferred to GE Vernova.

Shareholder and related lawsuits. Since November 2017, several putative shareholder class actions under the federal securities laws were filed against GE and certain affiliated individuals and consolidated into a single action currently pending in the U.S. District Court for the Southern District of New York (the Hachem case, also referred to as the Sjunde AP-Fonden case). The complaint against defendants GE and current and former GE executive officers alleged violations of Sections 10(b) and 20(a) and Rule 10b-5 of the Securities Exchange Act of 1934 related to insurance reserves and accounting for long-term service agreements and seeks damages on behalf of shareholders who acquired GE stock between February 27, 2013 and January 23, 2018. GE filed a motion to dismiss in December 2019. In January 2021, the court granted the motion to dismiss as to the majority of the claims. Specifically, the court dismissed all claims related to insurance reserves, as well as all claims related to accounting for long-term service agreements, with the exception of certain claims about historic disclosures related to factoring in the Power business that survive as to GE and its former CFO Jeffrey S. Bornstein. All other individual defendants have been dismissed from the case. In April 2022, the court granted the plaintiffs' motion for class certification for shareholders who acquired stock between February 26, 2016 and January 23, 2018. In September 2022, GE filed a motion for summary judgment on the plaintiffs' remaining claims, which the court denied in September 2023, except as to claims arising from disclosures made between November 2017 and January 2018. In April 2024, the court scheduled a trial date for November 2024.

GE Retirement Savings Plan class actions. In 2017, four putative class action lawsuits were filed regarding the oversight of the GE RSP, and those class actions were consolidated into a single action in the U.S. District Court for the District of Massachusetts. The consolidated complaint named as defendants GE, GE Asset Management, current and former GE and GE Asset Management executive officers and employees who served on fiduciary bodies responsible for aspects of the GE RSP during the class period. Like similar lawsuits that were brought against other companies in recent years, this action alleged that the defendants breached their fiduciary duties under the Employee Retirement Income Security Act (ERISA) in their oversight of the GE RSP, principally by retaining five proprietary funds that plaintiffs alleged were underperforming as investment options for plan participants and by charging higher management fees than some alternative funds. The plaintiffs sought unspecified damages on behalf of a class of GE RSP participants and beneficiaries from September 26, 2011 through the date of any judgment. In March 2024, the court granted final approval of the previously reported class action settlement.

Bank BPH. As previously reported, Bank BPH, along with other Polish banks, has been subject to ongoing litigation in Poland related to its portfolio of floating rate residential mortgage loans, with cases brought by individual borrowers seeking relief related to their foreign currency indexed or denominated mortgage loans in various courts throughout Poland. For a number of years, we have observed an increase in the total number of lawsuits being brought against Bank BPH and other banks in Poland by current and former borrowers, and we expect this to continue in future reporting periods. As previously reported, GE and Bank BPH approved the adoption of a settlement program and recorded an additional charge of $1,014 million in the quarter ended June 30, 2023. The estimate of total losses for borrower litigation at Bank BPH was $2,517 million and $2,669 million as of March 31, 2024 and December 31, 2023, respectively. The estimate accounts for the costs of payments to borrowers who we estimate will participate in the settlement program, as well as estimates for the results of litigation with other borrowers, which in either case can exceed the value of the current loan balance, and represents our best estimate of the total losses we expect to incur over time. However, there are a number of factors that could affect the estimate in the future; refer to the disclosure about Bank BPH in our Annual Report on Form 10-K for the year ended December 31, 2023.

ENVIRONMENTAL, HEALTH AND SAFETY MATTERS. Our operations, like operations of other companies engaged in similar businesses, involve the use, disposal and cleanup of substances regulated under environmental protection laws and nuclear decommissioning regulations. We record reserves for obligations for ongoing and future environmental remediation activities, such as the Housatonic River cleanup, and for additional liabilities we expect to incur in connection with previously remediated sites, such as natural resource damages for the Hudson River where GE completed dredging in 2019. Additionally, like many other industrial companies, we and our subsidiaries are defendants in various lawsuits related to alleged exposure by workers and others to asbestos or other hazardous materials. Liabilities for environmental remediation, nuclear decommissioning and worker exposure claims exclude possible insurance recoveries. It is reasonably possible that our exposure will exceed amounts accrued. However, due to uncertainties about the status of laws, regulations, technology and information related to individual sites and lawsuits, such amounts are not reasonably estimable. Total reserves related to environmental remediation, nuclear decommissioning and worker exposure claims were $2,537 million and $2,465 million at March 31, 2024 and December 31, 2023, respectively.