XML 55 R61.htm IDEA: XBRL DOCUMENT v2.4.0.6
Cost Of Contracts (Detail) (USD $)
In Millions, unless otherwise specified
Dec. 31, 2012
Dec. 31, 2011
Contracts In Process [Line Items]    
Contract costs and estimated profits $ 8,162 $ 18,807
Other contract costs 1,089 959
Costs in excess of billings on uncompleted contracts or programs, total 9,251 19,766
Advances and progress payments (4,287) (14,598)
Total contracts in process 4,964 5,168
Percent of contracts-in-process not expected to be billed in 2013 15.00%  
Canadian Maritime Helicopter Project (MHP)
   
Contracts In Process [Line Items]    
Contracts-in-process not expected to bill in 2013 $ 365