Poinciana Parkway
9 Months Ended
Sep. 30, 2011
Poinciana Parkway [Abstract] 
Poinciana Parkway
Property and Equipment

Property and Equipment are stated at cost and depreciation is computed by the straight-line method over the following estimated useful lives of the assets: land improvements 10 to 25 years; buildings and improvements 8 to 39 years; and machinery, equipment and fixtures 3 to 7 years. Maintenance and operating expenses of equipment utilized in the development of land are capitalized as land inventory cost.  Repairs and maintenance are expensed as incurred.

Property and Equipment includes the cost of amenities, such as club facilities on properties owned by us. The cost of these amenities includes expenditures for land acquisition, construction, land development and direct and allocated costs. Property and Equipment owned and constructed by us also includes interest cost incurred during development and construction.

We review our Property and Equipment quarterly for indicators of impairment in accordance with ASC 360-10. For our amenities, which are located within our housing communities, indicators of potential impairment are similar to those of our housing communities (described above) as these factors may impact our ability to generate revenues at our amenities or cause construction costs to increase. In addition, we factor in the collectability and potential delinquency of the fees due for our amenities.  We did not write down the value of our amenities held in Property and Equipment in the nine or three months ended September 30, 2011. 
 
Poinciana Parkway

In December 2006, we entered into agreements with Osceola County, Florida and Polk County, Florida for us to develop and construct at our cost a 9.66 mile four-lane road (including a 4.15 mile private toll section) in Osceola and Polk Counties to be known as the Poinciana Parkway (the “Poinciana Parkway”). Such agreements have been amended so that we are required to obtain financing and commence construction of the Parkway by February 14, 2012 and complete such construction by May 7, 2014, subject to extension for force majeure.  We have acquired all of the rights of way necessary to construct the Poinciana Parkway and have obtained all material permits for construction.  Such permits do not expire until February, 2018.

If funding and commencement of construction of the Poinciana Parkway is not achieved by February 14, 2012, the Counties have no right to obtain damages or seek specific performance against Avatar; however, (i) a portion of Avatar's land in Osceola County will become subject to Osceola traffic concurrency requirements applicable generally to other home builders in the County and (ii) Avatar will be required to contribute approximately $1,900 towards the construction cost of certain traffic improvements in Osceola County that we otherwise might have been obligated to build or fund if we had not agreed to construct the Poinciana Parkway.  

Osceola County and Avatar are still attempting to locate governmental funds for development of the Poinciana Parkway.  We cannot predict whether any governmental funds will be available. We intend to seek extensions of the deadlines in our agreements with Polk and Osceola Counties.

For the Poinciana Parkway, indicators of impairment are general economic conditions, rate of population growth and estimated change in traffic levels. If indicators are present, we perform an impairment test in which the asset is reviewed for impairment by comparing the estimated future undiscounted cash flows to be generated by the asset to its carrying value. If such cash flows are less than the asset's carrying value, the carrying value is written down to its estimated fair value. In determining estimated future cash flows for purposes of the impairment test, we incorporate current market assumptions based on general economic conditions such as anticipated estimated revenues and estimated costs. These assumptions can significantly affect our estimates of future cash flows.

Our estimate of the right-of-way acquisition, development and construction costs for the Poinciana Parkway approximates $175,000 to $200,000. However, no assurance of the ultimate costs can be given at this stage. As of September 30, 2011, approximately $47,400 has been expended. During fiscal years 2009 and 2008, we recorded impairment charges of $8,108 and $30,228, respectively, associated with the Poinciana Parkway.

We review the recoverability of the carrying value of the Poinciana Parkway on a quarterly basis in accordance with authoritative accounting guidance. Based on our review as of September 30, 2011, we determined the estimated future undiscounted cash flows of the Poinciana Parkway were greater than its carrying value, therefore no impairment losses were recorded during the nine and three months ended September 30, 2011.  Subsequent to September 30, 2011, we were informed that a real estate transaction occurred in the second quarter of 2011 affecting property immediately adjacent to a portion of the right-of-way comprising the Poinciana Parkway that was not reflected in the Public Records.  This transaction, once made public and analyzed by the Company, may result in impairment of the Poinciana Parkway in the fourth quarter of 2011.  The amount of this potential impairment, which cannot exceed the $8,452 carry value, is not presently determinable. Non-capitalizable expenditures of $46 and $0 related to the Poinciana Parkway were expensed during the nine and three months ended September 30, 2011, respectively, and $287 and $22 during the nine and three months ended September 30, 2010, respectively. At September 30, 2011, the carrying value of the Poinciana Parkway is $8,452.