Note F - Property, Plant and Equipment
3 Months Ended
Jun. 30, 2020
Notes to Financial Statements  
Property, Plant and Equipment Disclosure [Text Block]
NOTE F — PROPERTY, PLANT AND EQUIPMENT
 
The Company continued
two
previously announced capital expenditure projects during the
first
quarter of fiscal
2021.
 
The
first
project was a building expansion at the Company's coil processing facility in Hickman, Arkansas that was put into service during
May 2020.
The project added an additional
22,000
square feet of storage space to the facility. This project was completed at an actual cost of approximately
$1,083,000
compared to an original estimated cost of
$1,100,000.
The
second
project involves the purchase and installation of a stretcher leveler coil processing line at the Company's coil processing facility in Decatur, Alabama. This newly acquired equipment will replace the existing processing equipment at the Decatur plant and will expand both the size range and grade of material that the Decatur plant is able to process. The equipment was purchased from and is being constructed, fabricated and installed by Delta Steel Technologies. In
June 2020,
the existing equipment at the Decatur facility was removed to allow the foundation to be prepared for the installation of the new equipment. As part of the equipment removal, the cut-to-length line was sold for scrap resulting in anticipated proceeds of
$30,957
and
$2,688,381
of original cost being removed from machinery and equipment and accumulated depreciation of
$2,657,424
being removed. The temper mill was disassembled with the components being cleaned, cataloged and stored as the Company intends to sell the equipment. The Company currently expects the installation of the new equipment to begin in
October 2020
and expects commercial use of the equipment to begin in
February 2021.
The Company currently estimates the cost of this project to be
$5,800,000.
 
As of
June 30, 2020,
expenditures related to the Decatur project totaled
$3,874,444
with this amount reported as Construction in Process on the Company's Consolidated Balance Sheet.