Note F - Property, Plant and Equipment
9 Months Ended
Dec. 31, 2019
Notes to Financial Statements  
Property, Plant and Equipment Disclosure [Text Block]
NOTE F – PROPERTY, PLANT AND EQUIPMENT
 
The Company commenced
two
capital expenditure projects during the
three
months ended
December 31, 2019.
 
The
first
project is a building expansion at the Company’s coil processing facility in Hickman, Arkansas. The project will add an additional
22,000
square feet of storage space to the facility. This project is estimated to be complete by
April 2020
with an estimated cost of
$1,100,000.
 
The
second
project involves the installation of a stretcher leveler coil processing line at the Company’s coil processing facility in Decatur, Alabama. This equipment will replace the existing processing equipment that is currently present at the Decatur plant and will expand both the size range and grade of material that Decatur is able to process. The equipment is being constructed, fabricated and installed by Delta Steel Technologies. The Company currently expects installation of the new equipment to begin in
October 2020
and expects commercial use to begin in
February 2021.
The Company currently estimates the cost of this project to be
$5,800,000.
 
As of
December 31, 2019,
expenditures related to these projects totaled
$2,114,123
with this amount reported as Construction in Progress on the Company’s Condensed Consolidated Balance Sheet.