XML 52 R32.htm IDEA: XBRL DOCUMENT v3.25.2
Commitments and Contingencies (Tables)
6 Months Ended
Jun. 30, 2025
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
At June 30, 2025, estimated capital expenditures, on an accrual basis, for the remainder of 2025 through 2029 were as follows:

 
Remainder of 2025
2026202720282029Total
 (millions)
FPL:
Generation:(a)
New(b)
$1,035 $3,925 $3,385 $3,385 $3,510 $15,240 
Existing4251,1601,3251,2751,2755,460 
Transmission and distribution(c)
2,1104,2554,0804,3254,71019,480 
Nuclear fuel1553003053953751,530 
General and other4708808107907153,665 
Total$4,195 $10,520 $9,905 $10,170 $10,585 $45,375 
NEER:(d)
      
Wind(e)
$1,440 $2,470 $475 $75 $50 $4,510 
Solar(f)
3,810 5,670 2,040 1,570 — 13,090 
Other clean energy(g)
945 1,935 1,370 95 — 4,345 
Nuclear, including nuclear fuel
215 385 420 425 420 1,865 
Rate-regulated transmission
720 1,095 700 365 710 3,590 
Other
250 340 270 250 265 1,375 
Total$7,380 $11,895 $5,275 $2,780 $1,445 $28,775 
———————————————
(a)Includes AFUDC of approximately $75 million, $170 million, $180 million, $175 million and $160 million for the remainder of 2025 through 2029, respectively.
(b)Includes land, generation structures, transmission interconnection and integration and licensing.
(c)Includes AFUDC of approximately $30 million, $80 million, $75 million, $110 million and $140 million for the remainder of 2025 through 2029, respectively.
(d)Represents capital expenditures for which applicable internal approvals and also, if required, regulatory approvals have been received.
(e)Consists of capital expenditures for new wind projects and repowering of existing wind projects totaling approximately 2,911 MW, and related transmission.
(f)Includes capital expenditures for new solar projects (including solar plus battery storage projects) totaling approximately 11,888 MW and related transmission.
(g)Includes capital expenditures primarily for battery storage projects totaling approximately 3,795 MW and related transmission, as well as renewable fuels projects.
Required capacity and/or minimum payments under contracts
The required capacity and/or minimum payments under contracts, including those discussed above, at June 30, 2025 were estimated as follows:

Remainder of 20252026202720282029Thereafter
(millions)
FPL(a)
$595 $1,165 $1,135 $1,100 $1,090 $7,290 
NEER(b)(c)
$3,510 $2,615 $515 $240 $125 $425 
———————————————
(a)Includes approximately $205 million, $400 million, $400 million, $400 million, $395 million and $4,765 million for the remainder of 2025 through 2029 and thereafter, respectively, of firm commitments related to natural gas transportation agreements with affiliates. The charges associated with these agreements are recoverable through the fuel clause. For the three and six months ended June 30, 2025, the charges associated with these agreements totaled approximately $104 million and $204 million, respectively. For the three and six months ended June 30, 2024, the charges associated with these agreements totaled approximately $102 million and $203 million, respectively, of which $24 million and $48 million, respectively, were eliminated in consolidation at NEE.
(b)Includes approximately $165 million of commitments to invest in technology and other investments through 2032. See Note 6 – Other.
(c)Includes approximately $875 million and $190 million for the remainder of 2025 and 2026, respectively, of joint obligations of NEECH and NEER.