XML 81 R11.htm IDEA: XBRL DOCUMENT v2.4.0.6
REGULATION
12 Months Ended
Sep. 30, 2012
Regulated Operations [Abstract]  
REGULATION
REGULATION

The Electric Discount and Energy Competition Act (EDECA) is the legal framework for New Jersey's public utility and wholesale energy landscape. NJNG is required, pursuant to a written order by the BPU under EDECA, to open its residential markets to competition from third-party natural gas suppliers. Customers can choose the supplier of their natural gas commodity in NJNG's service territory.

As required by EDECA, NJNG's rates are segregated into two primary components, the commodity portion, which represents the wholesale cost of natural gas, including the cost for interstate pipeline capacity to transport the gas to NJNG's service territory, and the delivery portion, which represents the transportation of the commodity portion through NJNG's gas distribution system to the end-use customer. NJNG does not earn utility gross margin on the commodity portion of its natural gas sales. NJNG earns utility gross margin through the delivery of natural gas to its customers, regardless of whether it or a third-party supplier provides the wholesale natural gas commodity.

Under EDECA, the BPU is required to audit the state's energy utilities every two years. The primary purpose of the audit is to ensure that utilities and their affiliates offering unregulated retail services do not have unfair competitive advantage over nonaffiliated providers of similar retail services. A combined competitive services and management audit of NJNG commenced in November 2006, and a final report on findings and recommendations was approved by the BPU on January 28, 2009. As of September 30, 2011, all recommendations have been implemented by NJNG and a completion letter was received from the BPU on October 24, 2011, that finalized the audit.

NJNG is subject to cost-based regulation, therefore, it is permitted to recover authorized operating expenses and earn a reasonable return on its utility investment based on the BPU's approval, in accordance with accounting guidance applicable to regulated operations. The impact of the ratemaking process and decisions authorized by the BPU allows NJNG to capitalize or defer certain costs that are expected to be recovered from its customers as regulatory assets and to recognize certain obligations representing amounts that are probable future expenditures as regulatory liabilities.

As recovery of regulatory assets is subject to BPU approval, if there are any changes in regulatory positions that indicate recovery is not probable, the related cost would be charged to income in the period of such determination.

Regulatory assets and liabilities included on the Consolidated Balance Sheets as of September 30, are comprised of the following:
(Thousands)
2012
2011
Regulatory assets-current
 
 
Underrecovered gas costs
$
7,053

$

Conservation Incentive Program
25,681

9,178

Derivatives, net

8,452

Total current
$
32,734

$
17,630

Regulatory assets-noncurrent
 
 
Environmental remediation costs
 
 
Expended, net of recoveries
$
59,745

$
75,646

Liability for future expenditures
182,000

182,900

Deferred income taxes
11,405

10,879

Energy Efficiency Program
26,025

11,906

New Jersey Clean Energy Program
5,619

20,144

Postemployment and other benefit costs
142,495

123,827

Other
13,974

8,883

Total noncurrent
$
441,263

$
434,185

Regulatory liability-current
 
 
Overrecovered gas costs
$

$
4,633

Derivatives, net
1,169


Total current
$
1,169

$
4,633

Regulatory liabilities-noncurrent
 
 
Cost of removal obligation
$
65,994

$
59,752

Derivatives, net
1,000


Other
83

85

Total noncurrent
$
67,077

$
59,837


NJNG's recovery of costs is facilitated through its base rates, BGSS and other regulatory riders. NJNG is required to make an annual filing to the BPU by June 1 of each year for review of its BGSS, Conservation Incentive Program (CIP) and various other programs and related rates. Annual rate changes are requested to be effective at the beginning of the following fiscal year. In addition, NJNG is also permitted to request approval of certain rate or program changes on an interim basis. All rate and program changes are subject to proper notification and BPU review and approval.

Gas Costs

NJNG recovers its cost of gas through the BGSS rate component of its customers' bills. NJNG's cost of gas includes the purchased cost of the natural gas commodity, fees paid to pipelines and storage facilities, adjustments as a result of BGSS incentive programs, and hedging transactions. Under-recovered gas costs represent a regulatory asset that generally occurs during periods when NJNG's BGSS rates are lower than actual costs and requests amounts to be recovered from customers in the future. Conversely, over-recovered gas costs represent a regulatory liability that generally occurs when NJNG's BGSS rates are higher than actual costs and requests approval to be returned to customers including interest, when applicable, in accordance with NJNG's approved tariff.

Conservation Incentive Program

The CIP permits NJNG to recover utility gross margin variations related to customer usage resulting from customer conservation efforts and allows NJNG to mitigate the impact of weather on its gross margin. Such utility gross margin variations are recovered in the year following the end of the CIP usage year, without interest, and are subject to additional conditions, including an earnings test and an evaluation of BGSS related savings.

Derivatives

Derivatives are utilized by NJNG to manage the price risk associated with its natural gas purchasing activities and to participate in certain BGSS incentive programs. The gains and losses associated with NJNG's derivatives are recoverable through its BGSS, as noted above, without interest. See Note 4. Derivatives.

Environmental Remediation Costs Recovery

NJNG is responsible for the cleanup of certain former gas manufacturing facilities. Actual expenditures are recovered, with interest, over seven year rolling periods, through a RA rate rider. Recovery for NJNG's estimated future liability will be requested and/or recovered when actual expenditures are incurred. See Note 13. Commitments and Contingencies.

Deferred Income Taxes

In 1993, NJNG adopted the provisions of ASC 740, Income Taxes, which changed the method used to determine deferred tax assets and liabilities. Upon adoption, NJNG recognized a transition adjustment and corresponding regulatory asset representing the difference between NJNG's existing deferred tax amounts compared with the deferred tax amounts calculated in accordance with the change in method prescribed by ASC 740. NJNG recovers the regulatory asset associated with these tax impacts through future base rates, without interest.

New Jersey Clean Energy Program (NJCEP)

The NJCEP is a statewide program that encourages energy efficiency and renewable energy. Funding amounts are determined by the BPU and all New Jersey utilities are required to share in the funding obligation. The current NJCEP program is for the calendar years 2009 through 2012. NJNG recovers the costs associated with its portion of the NJCEP obligation, including interest, through its Societal Benefits Clause (SBC) rate rider.

Energy Efficiency Program (EE)

NJNG administers certain programs that supplement the states' NJCEP and that allows NJNG to promote clean energy to its residential and commercial customers, as described further below. NJNG will recover related expenditures and a weighted average cost of capital through an EE rate rider, as approved by the BPU, over a four to ten year period depending upon the initiative and available on-bill financing.
Postemployment and Other Benefit Costs

Postemployment and Other Benefit Costs represents NJNG's underfunded postemployment benefit obligations that the Company began recognizing in fiscal 2006, as a result of changes in the accounting provisions of ASC 715, Compensation and Benefits, as well as a fiscal 2010 tax charge resulting from a change in the deductibility of federal subsidies associated with Medicare D, both of which are deferred as regulatory assets and are recoverable, without interest, in base rates. See Note 10. Employee Benefit Plans.

Other Regulatory Assets

Other regulatory assets consists primarily of deferred costs associated with certain components of NJNG's SBC, as discussed further below, and NJNG's compliance with federal and state mandated pipeline integrity management (PIM) provisions. NJNG's related costs to maintain the operational integrity of its distribution and transmission main are recoverable, subject to BPU review and approval, in its next base rate case. NJNG is limited to recording a regulatory asset associated with PIM that does not exceed $700,000 per year. In addition, to the extent that project costs are lower than the approved PIM annual expense of $1.4 million, NJNG will record a regulatory liability that will be refundable as a credit to customers' gas costs when the net cumulative liability exceeds $1 million. As of September 30, 2012, NJNG has recorded $2.5 million of PIM in other regulatory assets.

Cost of Removal Obligation

NJNG accrues and collects for cost of removal in base rates. A regulatory liability represents the current collections in excess of actual expenditures, which the Company will return to customers over approximately 48 years, through a reduction in the depreciation expense component of NJNG's base rates, as approved by the BPU in NJNG's last base rate case.

The following is a description of regulatory proceedings during fiscal 2011 and 2012:

BGSS and CIP

BGSS rates are normally revised on an annual basis. In addition, in order to manage the fluctuations in wholesale natural gas costs, NJNG has the ability to make two interim filings during the fiscal year to increase residential and small commercial customer BGSS rates on a self-implementing and provisional basis. NJNG is also permitted to refund or credit back a portion of the commodity costs to customers when the natural gas commodity costs decrease in comparison to amounts projected or to amounts previously collected from customers. During fiscal 2012, NJNG provided bill credits of approximately $85.9 million to NJNG's residential and small commercial customers due to a decline in the wholesale prices of natural gas and a change in the methodology used to develop estimates of unaccounted-for gas. Commodity prices were relatively stable during fiscal 2011, therefore, there were no refunds or rate adjustments. On March 9, 2012, NJNG notified the BPU of a 3.6 percent decrease related to its BGSS rate, effective April 1, 2012, which will have an annual impact of approximately $19 million.

Concurrent with the annual BGSS filing, NJNG files for an annual review of its CIP. The CIP was initially approved as a three-year program through September 2009. During fiscal 2010, the BPU approved an extension of the program through September 30, 2013. It is anticipated that NJNG will file for an extension of its CIP in fiscal 2013. NJNG's annual BGSS and CIP filings are summarized as follows:

June 2010 BGSS/CIP filing - In April 2011, the BPU issued their final order approving NJNG's request to reduce rates for a 3.5 percent decrease for the average residential heating customer related to the BGSS rate, effective September 16, 2010. This offset NJNG's request for an increase in the CIP recovery rate, approved by the BPU effective October 1, 2010, allowing for a total annual recovery of $12.1 million representing CIP amounts accrued and estimated through September 30, 2010.

June 2011 BGSS/CIP filing - NJNG proposed to reduce BGSS rates for a 9.1 percent decrease for the average residential heating customer as a result of cost control and natural gas purchasing strategies, as well as lower natural gas prices. In addition, NJNG requested approval to modify its CIP recovery rates resulting in a decrease to the total annual recovery of $3 million. The proposed CIP rates result in an increase to all classes except residential heat, which represents a decrease. In May 2012, the BPU approved the changes effective October 4, 2011.

June 2012 BGSS/CIP filing - NJNG proposed to maintain its current BGSS rate. In addition, NJNG requested approval to decrease the CIP rate for residential non-heating customers and increase the CIP rates for residential heating and commercial customers, which were approved on a provisional basis effective October 12, 2012, which increased an average residential heating customer bill by 2.4 percent.
Infrastructure Programs

NJNG has significant annual capital expenditures associated with the management of its natural gas distribution and transmission system and its associated pipeline integrity.

During fiscal 2009, NJNG implemented its Accelerated Infrastructure Programs (AIP) commencing construction on fourteen infrastructure projects at a BPU approved cost of $70.8 million (AIP I). AIP was initially approved by the BPU as a two-year program, to enhance the reliability of NJNG's gas distribution system and to support economic development and job growth in New Jersey. During fiscal 2011, the BPU approved an extension to NJNG's AIP, allowing for additional capital investments of $60.2 million (AIP II) to be made through October 31, 2012. NJNG defers the costs associated with the AIP projects, including NJNG's weighted cost of capital, and upon regulatory approval recovers these investments through its base rates.

Annual filings include the following:

June 2011 AIP filing - NJNG filed for AIP base rate cost recovery, which represented an increase of $4.7 million related to AIP I and AIP II infrastructure investments installed in NJNG's distribution and transmission systems. A settlement was reached and approved by the BPU effective October 1, 2011. The rate changes included a weighted average cost of capital of 7.12 percent for AIP II. The existing weighted average cost of capital for AIP I remained the same at 7.76 percent. The requested base rate change was approved on a final basis in August 2012.

November 2012 AIP filing - NJNG filed for AIP base rate cost recovery, requesting an increase of $6.9 million, which represents a cumulative impact of $15.8 million annually, related to AIP I and AIP II infrastructure investments installed in NJNG's distribution and transmission systems through October 31, 2012. The existing weighted average cost of capital remained the same for both AIP I and AIP II. The base rate change is requested to be approved in March 2013.

On March 20, 2012, NJNG filed a petition with the BPU seeking to implement a Safety Acceleration and Facility Enhancement (SAFE) program, whereby NJNG would invest up to $204 million over a five-year period to replace portions of NJNG's gas distribution unprotected steel and cast iron infrastructure in order to improve the safety and reliability of the gas distribution system. NJNG entered into a stipulation with the BPU Staff and Rate Counsel, which was approved by the BPU on October 23, 2012, to include a four-year incremental investment program of $130 million, exclusive of AFUDC accruals. The approved SAFE Program will include the deferral of infrastructure costs subject to review in NJNG's next base rate case to be filed no later than November 2015, the deferral of depreciation expense on SAFE investments and recognizes an overall rate of return on infrastructure investments of 6.9 percent. The deferred cost recovery will include accruals for both debt and equity components of AFUDC while construction is in progress. When construction is completed and plant is placed in service, NJNG will accrue an AFUDC rate at 6.9 percent per year until such time that NJNG receives approval for recovery of all costs through base rates.

BGSS Incentive Programs

NJNG is eligible to receive financial incentives for reducing BGSS costs through a series of utility gross margin-sharing programs that include off-system sales, capacity release, storage incentive and Financial Risk Management (FRM) programs. In August 2011, the BPU approved an extension of NJNG's BGSS incentive programs for four years through October 31, 2015, maintaining the existing margin-sharing percentages. This agreement also permits the Company to annually propose a process to evaluate and discuss alternative incentive programs, should performance of the existing incentives or market conditions warrant re-evaluation.

Energy Efficiency Programs (EE)

NJNG commenced its EE programs during fiscal 2009, allowing it to promote energy efficiency to its residential and commercial customers while stimulating state and local economies through the creation of jobs. Depending on the specific initiative, NJNG recovers costs associated with the programs over a four to ten-year period to facilitate home energy audits and to provide financing alternatives including rebates and other incentives designed to encourage the installation of high efficiency heating and cooling equipment. In September 2010, NJNG received BPU approval for recovery of an additional $9.6 million in energy efficiency investments, effective January 1, 2011, to be recovered over a five to ten-year period, depending on the rebate or financing initiative. The approval allowed for an extension of certain existing initiatives, as well as new or expanded funding incentives for commercial customers. In January 2011, NJNG notified the BPU that its proposed solar incentive component was withdrawn. On July 15, 2011, NJNG filed a separate EE petition, approved by the BPU in January 2012, to extend its current EE programs through January 18, 2013. As of September 30, 2012, the BPU approved total EE expenditures of $35.3 million, of which, NJNG has spent a total of $29.2 million.
The EE program investments and costs are filed with the BPU on an annual basis and include the following:

June 2011 EE filing - NJNG requested that the existing EE rate remain the same through an amended filing on July 15, 2011. On January 18, 2012, the BPU approved an extension of NJNG's EE program for one year with an additional $10.4 million of investments in customer incentives and rebates, earning a weighted average cost of capital of 7.1 percent, including a cost of equity of 10.3 percent.

June 2012 EE filing - On July 9, 2012, NJNG filed two petitions with the BPU related to The SAVEGREEN Project® (SAVEGREEN) EE programs. The petitions include the 2012 rate filing, which represents a reconciliation of BPU approved actual costs for EE programs and a petition related to the extension of NJNG's EE programs over a four-year program, with modifications to include certain new programs. The Company's petition requests a BPU decision in early 2013. The rate impact will incorporate the existing Savegreen programs and the extension of the new Savegreen programs over a four to ten-year period.

Societal Benefits Clause (SBC)

The SBC is comprised of three primary riders that allow NJNG to recover costs associated with USF, which is a permanent statewide program for all natural gas and electric utilities for the benefit of income-eligible customers, manufactured gas plant (MGP) remediation, and the NJCEP. NJNG has submitted the following filings to the BPU, which includes a report of program expenditures incurred each program year:

June 2010 SBC filing - NJNG filed an application to maintain the existing MGP factor and NJCEP rate. In November 2011, NJNG, the BPU and Rate Counsel executed a stipulation agreeing to maintain the existing MGP and NJCEP rates. On January 18, 2012, the BPU approved the filing, in which NJNG requested approval of its MGP remediation expenditures incurred through June 30, 2009, which maintained the expected annual recovery at approximately $20 million. In addition, natural gas utilities in the State of New Jersey collectively filed with the BPU to increase the statewide USF rate to be effective October 1, 2010. Effective November 1, 2010, the BPU approved the recovery of the USF program year budget, resulting in an overall increase to the average monthly bill of a residential heating customer by .03 percent, and the recovery of deferred USF administrative costs.

June 2011 USF filing - NJNG filed to reduce the annual USF recovery rate, which was approved by the BPU, effective November 1, 2011.

February 2012 SBC filing - NJNG filed an application requesting approval of its MGP expenditures incurred through June 30, 2011, which continued its existing overall SBC rate and recovery.

June 2012 USF filing - NJNG filed to reduce the USF recovery rate resulting in a .1 percent decrease for the average residential heating customer. The rate was approved by the BPU effective October 1, 2012.

Other Regulatory Initiatives

On June 18, 2012, the BPU approved a pilot program for NJNG to invest up to $10 million to build compressed natural gas vehicle refueling stations in Monmouth, Ocean and Morris counties. NJNG intends to begin construction of the stations within one year and submit a cost recovery filing to the BPU in the spring of 2013, requesting a base rate change to be effective in the summer of 2013, earning an overall weighted average cost of capital of 7.1 percent, including a cost of equity of 10.3 percent. A portion of the proceeds from the utilization of the CNG equipment, along with any available federal and state incentives, will be credited back to ratepayers to help offset the cost of this investment.

On November 19, 2012, NJNG filed a petition with the BPU requesting deferral accounting for actually incurred uninsured incremental operating and maintenance costs associated with Post Tropical Cyclone Sandy, commonly referred to as Superstorm Sandy (Superstorm Sandy). In addition, NJNG requested the review of and the appropriate amortization period for such deferred expenses be addressed in the Company's next base rate case.