Loss Contingencies [Line Items]        
Litigation Settlement Expense $ 9,000 $ 0 $ 9,000 $ 0
Plum [Member]        
Loss Contingencies [Line Items]        
Payments For Legal Settlements 5,000      
Non Cash Rebate For Legal Settlement $ 4,000   $ 4,000  
Plum [Member] | SunOpta Global Organic Ingredients, Inc [Member]        
Loss Contingencies [Line Items]        
Business Contracts, Manufacturing Contract Date Sep. 21, 2011      
Inventory Recall Date Nov. 08, 2013      
Loss Contingency, Lawsuit Filing Date     3-Feb-15  
Loss Contingency, Name of Defendant     SunOpta Global Organic Ingredients, Inc  
Loss Contingency, Name of Plaintiff     Plum, PBC, a Delaware public benefit corporation (“Plum”)  
Loss Contingency, Amended Lawsuit Filing Date Apr. 13, 2015      
Loss Contingency Allegations     Plum filed an amended complaint adding packaging manufacturer and supplier Cheer Pack North America as a Defendant. Plum alleged it initiated the recall in response to consumer complaints of spoiled packaging of certain products, which could lead to gastrointestinal symptoms and discomfort if consumed. Plum alleged that the spoilage of its products resulted from a post-processing issue at SGOI’s Allentown facility.  
Loss Contingency Actions Taken By Defendant     SGOI asserted counterclaims against Plum and cross-claims against Cheer Pack.  
Loss Contingency Damages Sought     Plum sought unspecified damages equal to the direct costs of the recall and handling of undistributed product, incidental and consequential damages, lost profits and attorneys’ fees.