Investment in Nonconsolidated Entity (Details)
$ in Millions
1 Months Ended 6 Months Ended
Sep. 30, 2018
USD ($)
Jul. 31, 2018
USD ($)
May 31, 2018
USD ($)
Apr. 30, 2018
USD ($)
Jun. 30, 2018
USD ($)
mi
Dec. 31, 2020
mi
Schedule of Equity Method Investments [Line Items]            
Percent interest to require approval         66.67%  
Issuance of performance guarantee         $ 91.0  
Variable Interest Entity, Not Primary Beneficiary | MVP Joint Venture            
Schedule of Equity Method Investments [Line Items]            
Maximum financial statement exposure         $ 1,094.0  
MVP Joint Venture            
Schedule of Equity Method Investments [Line Items]            
Capital call notice     $ 445.9      
MVP Joint Venture | Scenario, Forecast            
Schedule of Equity Method Investments [Line Items]            
Capital call notice paid $ 252.5          
MVP Joint Venture | Subsequent Event            
Schedule of Equity Method Investments [Line Items]            
Capital call notice paid   $ 193.4        
MVP Joint Venture | EQM            
Schedule of Equity Method Investments [Line Items]            
Ownership percentage         45.50%  
Mountain Valley Pipeline            
Schedule of Equity Method Investments [Line Items]            
Natural gas interstate pipeline (in miles) | mi         300  
Mountain Valley Pipeline | Minimum            
Schedule of Equity Method Investments [Line Items]            
Estimated project cost       $ 3,500.0    
Mountain Valley Pipeline | Maximum            
Schedule of Equity Method Investments [Line Items]            
Estimated project cost       3,700.0    
MVP Southgate Project | Minimum            
Schedule of Equity Method Investments [Line Items]            
Estimated project cost       350.0    
MVP Southgate Project | Maximum            
Schedule of Equity Method Investments [Line Items]            
Estimated project cost       $ 500.0    
MVP Southgate Project | Scenario, Forecast            
Schedule of Equity Method Investments [Line Items]            
Natural gas interstate pipeline (in miles) | mi           70
MVP Southgate Project | MVP Joint Venture | EQM | Scenario, Forecast | Minimum            
Schedule of Equity Method Investments [Line Items]            
Ownership percentage           33.00%
MVP Southgate Project | MVP Joint Venture | EQM | Scenario, Forecast | Maximum            
Schedule of Equity Method Investments [Line Items]            
Ownership percentage           48.00%