XML 83 R64.htm IDEA: XBRL DOCUMENT v3.3.1.900
COMMITMENTS AND CONTINGENCIES (Detail)
$ in Thousands
12 Months Ended
Dec. 15, 2008
Dec. 15, 2005
Dec. 31, 2015
USD ($)
item
MW
Dec. 31, 2014
USD ($)
Dec. 31, 2013
USD ($)
Commitments and Contingencies          
Period of the average cost that is used as a basis for determining the maximum annual payments   20 years      
Electric | Power Plant Mercury And Air Toxics Rule          
Commitments and Contingencies          
Construction costs year to date     $ 159,600    
Cost related to pre-engineering, site preparation activities and contract cost year to date       $ 112,100  
Electric | Low end of range | Power Plant Mercury And Air Toxics Rule          
Commitments and Contingencies          
Estimated project cost     165,000    
Electric | High end of range | Power Plant Mercury And Air Toxics Rule          
Commitments and Contingencies          
Estimated project cost     175,000    
Firm Physical gas and transportation contracts          
Commitments and Contingencies          
January 1, 2016 through December 31, 2016     26,700    
January 1, 2017 through December 31, 2018     37,400    
January 1, 2019 through December 31, 2020     28,800    
January 1, 2021 and beyond     45,700    
Coal and coal transportation contracts          
Commitments and Contingencies          
January 1, 2016 through December 31, 2016     18,000    
January 1, 2017 through December 31, 2018     27,500    
January 1, 2019 through December 31, 2020     $ 10,800    
Purchased power | Plum Point Energy Station          
Commitments and Contingencies          
Energy capacity (in megawatts) | MW     670    
Amount of energy capacity owned (in megawatts) | MW     50    
Additional capacity under long-term contract agreement (in megawatts) | MW     50    
Amount of long-term contract obligation     $ 277,600    
Amount of energy capacity under option to purchase (in megawatts) | MW     50    
Purchased power | Cloud County Windfarm          
Commitments and Contingencies          
Energy capacity (in megawatts) | MW     105    
Period of the average cost that is used as a basis for determining the maximum annual payments 20 years        
Purchased power | Cloud County Windfarm | Low end of range          
Commitments and Contingencies          
Amount of annual payments contingent upon output of the facility     $ 0    
Purchased power | Cloud County Windfarm | High end of range          
Commitments and Contingencies          
Amount of annual payments contingent upon output of the facility     $ 14,600    
Purchased power | Elk River Windfarm          
Commitments and Contingencies          
Energy capacity (in megawatts) | MW     150    
Purchased power | Elk River Windfarm | Low end of range          
Commitments and Contingencies          
Amount of annual payments contingent upon output of the facility     $ 0    
Purchased power | Elk River Windfarm | High end of range          
Commitments and Contingencies          
Amount of annual payments contingent upon output of the facility     16,900    
Leases          
Commitments and Contingencies          
Gross amount of assets recorded under capital leases     5,300    
Capital leases, 2016     554    
Capital leases, 2017     551    
Capital leases, 2018     551    
Capital leases, 2019     550    
Capital leases, 2020     546    
Capital leases, thereafter     2,460    
Capital leases, total minimum payments     5,212    
Capital leases, amount representing interest     1,322    
Capital leases, present value of net minimum lease payments     3,890    
Operating leases, 2016     734    
Operating leases, 2017     689    
Operating leases, 2018     648    
Operating leases, 2019     484    
Operating leases, total minimum payments     2,555    
Expenses incurred related to operating leases     800 800 $ 800
Accumulated amount of amortization of capital leases     $ 1,900 $ 1,500  
Leases | Electric          
Commitments and Contingencies          
Number of unit trains under short-term operating leases | item     2    
Leases | Gas          
Commitments and Contingencies          
Number of office facilities under short-term operating leases | item     1    
Leases | Plum Point Energy Station          
Commitments and Contingencies          
Number of railcars under capital leases | item     108