XML 90 R65.htm IDEA: XBRL DOCUMENT v3.25.2
Regulatory Matters (Tables)
6 Months Ended
Jun. 30, 2025
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The fuel and natural gas cost recovery balances for the traditional electric operating companies and Southern Company Gas, respectively, at June 30, 2025 and December 31, 2024 were as follows:
Regulatory ClauseBalance Sheet Line ItemAt June 30, 2025At December 31, 2024
(in millions)
Alabama Power
Rate ECROther regulatory assets, deferred$62 $— 
Other regulatory liabilities, current
 29 
Georgia Power
Fuel Cost Recovery
Receivables – under recovered retail fuel clause revenues
$655 $713 
Deferred under recovered retail fuel clause revenues325 453 
Mississippi Power
Fuel Cost Recovery(*)
Receivables – customer accounts, net$28 $— 
Deferred under recovered retail fuel clause revenues 32 
Over recovered retail fuel clause revenues
 32 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost over recovery$107 $193 
(*)Mississippi Power also has wholesale MRA and Market Based (MB) fuel cost recovery factors. At June 30, 2025 and December 31, 2024, wholesale MRA fuel costs were over recovered $5 million and $19 million, respectively, and were included in other current liabilities on Mississippi Power's balance sheets. The wholesale MB fuel cost recovery was immaterial for both periods presented.
Nuclear Construction Cost and Schedule Georgia Power's net capital costs incurred through June 30, 2025 in connection with Plant Vogtle Units 3 and 4, and its approximate proportionate share of remaining capital costs to be incurred after June 30, 2025, is as follows:
(in millions)
Total project capital cost forecast(a)(b)
$10,732 
Net investment at June 30, 2025(b)
(10,690)
Remaining estimate to complete$42 
(a)Includes approximately $1.2 billion of costs that are not shared with the other Vogtle Owners. Excludes financing costs capitalized through AFUDC of approximately $440 million accrued through Unit 4's in-service date.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Construction Projects
Project
Resource
Approximate Nameplate Capacity
(MW)
Projected COD
Regulatory Approval
Projects Under Construction at June 30, 2025
McGrau Ford
Battery energy storage
265
Fourth quarter 2026
2022 IRP
Plant Yates Units 8 through 10
Combustion turbine
1,326
Fourth quarter 2026 through third quarter 2027
2023 IRP Update
Various facilities
Battery energy storage
500
Second quarter 2026 through fourth quarter 2026
2023 IRP Update