Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4
$ in Millions
3 Months Ended
Mar. 31, 2024
USD ($)
Loss Contingencies [Line Items]  
Total project capital cost forecast $ 10,753
Net investment as of end of the period (10,608)
Remaining estimate to complete 145
Estimated cost to complete, costs not shared with other owners 610
Estimated cost to complete, construction monitoring costs approved for recovery 33
Pre-tax charge to income 567
Expected capitalized costs 440
Capitalized interest accrued 435
Twenty Fifth Vogtle Construction Monitoring Report  
Loss Contingencies [Line Items]  
Guarantor obligations 1,700
Customer refund $ 188