Regulatory Matters - GPC Nuclear Construction (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4
$ in Millions
12 Months Ended
Dec. 31, 2012
utility
MW
Mar. 31, 2024
USD ($)
Dec. 31, 2009
Loss Contingencies [Line Items]      
Proportionate ownership share     45.70%
Number of construction units approved | utility 2    
Electric generating capacity in mega watts under consortium agreement | MW 1,100    
Estimated cost to complete, construction contingency estimate, financing costs   $ 3,530  
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date   3,520  
Costs recovered to date   $ 3,070