Regulatory Matters - GPC Nuclear Construction Regulatory Matters (Details) - Plant Vogtle Units 3 And 4 - GEORGIA POWER CO
$ in Millions
6 Months Ended 12 Months Ended 12003 Months Ended
Feb. 16, 2023
USD ($)
Jan. 01, 2023
USD ($)
Jan. 01, 2021
Jan. 01, 2020
Jan. 11, 2018
USD ($)
Jan. 01, 2016
Jun. 30, 2023
USD ($)
Jun. 30, 2022
USD ($)
claim
Dec. 31, 2024
USD ($)
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Dec. 31, 2009
USD ($)
Dec. 31, 2022
USD ($)
Jun. 30, 2021
report
Jun. 30, 2018
USD ($)
Dec. 31, 2013
Public Utilities, General Disclosures [Line Items]                                
Estimated in-service capital cost                       $ 4,418        
Financing costs collected, net of tax             $ 3,000                  
Increase in tariff   $ 36                            
Additional construction capital costs         $ 3,300               $ 345      
Payments for contractor settlement agreement         300                      
Amendment to estimated in-service capital cost         $ 5,680                      
Retail rate of return on common equity                               10.95%
Public utilities, approved return on equity percentage     5.30% 8.30%   10.00%                    
Public utilities, approved return on equity, monthly percentage decrease             0.10%                  
Return on equity reduction, negative impact on earnings                     $ 300          
Increase to base capital cost forecast not seeking recovery                             $ 700  
Twenty Fourth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Cost settlement agreement revised forecast, net of payments             $ 7,300                  
Twenty Fifth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Number of approved construction management reports | report                           25    
Requested capital construction costs             7,900                  
Guarantor obligations             1,700                  
Customer refund             188                  
Twenty Sixth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Requested capital construction costs               $ 1,100                
Number of additional reports reviewed | claim               2                
Twenty Seventh Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Requested capital construction costs $ 461                              
Twenty Ninth Vogtle Construction Monitoring Report                                
Public Utilities, General Disclosures [Line Items]                                
Requested capital construction costs             $ 390                  
Scenario, Forecast                                
Public Utilities, General Disclosures [Line Items]                                
Return on equity reduction, negative impact on earnings                 $ 60 $ 290