Regulatory Matters - GPC Nuclear Construction (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4
$ in Millions
6 Months Ended 12 Months Ended
Jun. 30, 2023
USD ($)
Dec. 31, 2012
utility
MW
Aug. 31, 2018
Loss Contingencies [Line Items]      
Proportionate ownership share 45.70%    
Number of construction units approved | utility   2  
Electric generating capacity in mega watts under consortium agreement | MW   1,100  
Estimated cost to complete, construction contingency estimate, financing costs $ 3,500    
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date 3,400    
Construction contingency estimate 43    
Monthly AFUDC $ 45    
Percentage of ownership interest required for voting for continuing construction     90.00%
Vogtle Owners      
Loss Contingencies [Line Items]      
Period of notice required in the event letters of credit are not renewed 30 days    
Minimum | COVID-19      
Loss Contingencies [Line Items]      
Loss contingency, estimate of possible loss, loss of productivity, term 3 months    
Maximum | COVID-19      
Loss Contingencies [Line Items]      
Loss contingency, estimate of possible loss, loss of productivity, term 4 months    
Estimate of possible loss $ 200