XML 89 R61.htm IDEA: XBRL DOCUMENT v3.23.2
Regulatory Matters (Tables)
6 Months Ended
Jun. 30, 2023
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at June 30, 2023 and December 31, 2022 were as follows:
Regulatory ClauseBalance Sheet Line ItemJune 30,
2023
December 31, 2022
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory assets, current$20 $47 
Other regulatory assets, deferred40 — 
Rate CNP PPAOther regulatory assets, current17 18 
Other regulatory assets, deferred95 102 
Retail Energy Cost Recovery
Other regulatory assets, current
146 102 
Other regulatory assets, deferred283 520 
Georgia Power
Fuel Cost Recovery(*)
Receivables – under recovered fuel clause revenues
$695 $— 
Deferred under recovered fuel clause revenues1,489 2,056 
Mississippi Power
Fuel Cost Recovery
Receivables – customer accounts, net
$24 $
Ad Valorem Tax
Other regulatory assets, current
6 12 
Other regulatory assets, deferred
16 19 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost under recovery$ $108 
Natural gas cost over recovery161 — 
(*)See "Georgia Power – Fuel Cost Recovery" herein for additional information.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through July 2023 and March 2024, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$10,576 
Construction contingency estimate17 
Total project capital cost forecast(a)(b)
10,593 
Net investment at June 30, 2023(b)
(9,944)
Remaining estimate to complete$649 
(a)Includes approximately $610 million of costs that are not shared with the other Vogtle Owners, including $33 million of construction monitoring costs approved for recovery by the Georgia PSC in its nineteenth VCM order, and approximately $407 million of incremental costs under the cost-sharing and tender provisions of the joint ownership agreements described below. Excludes financing costs expected to be capitalized through AFUDC of approximately $422 million, of which $365 million had been accrued through June 30, 2023.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs and capital projects during the first six months of 2023 were as follows:
UtilityProgram
Six Months
Ended
June 30, 2023
(in millions)
Nicor GasInvesting in Illinois$196 
Virginia Natural GasSAVE37 
Atlanta Gas LightSystem Reinforcement Rider57 
Chattanooga GasPipeline Replacement Program
Total$294