REGULATORY MATTERS - GPC Nuclear Construction (Details)
$ in Millions
3 Months Ended 12 Months Ended
Dec. 31, 2022
USD ($)
Sep. 30, 2022
USD ($)
Jun. 30, 2022
USD ($)
Dec. 31, 2021
USD ($)
Dec. 31, 2022
USD ($)
Dec. 31, 2021
USD ($)
Dec. 31, 2020
USD ($)
Dec. 31, 2012
utility
MW
Public Utilities, General Disclosures [Line Items]                
Estimated loss on Plant Vogtle Units 3 and 4         $ 183 $ 1,692 $ 325  
Georgia Power                
Public Utilities, General Disclosures [Line Items]                
Number of construction units approved | utility               2
Electric generating capacity (in MWs) | MW               1,100
Estimated cost to complete, pre-tax charge to income $ 148 $ 32 $ 36          
Estimated cost to complete, pre-tax charge to income, net of tax 110 24 27          
Estimated loss on Plant Vogtle Units 3 and 4         183 $ 1,692 $ 325  
Pre-tax charge to income 53 (102) 16 $ 440 $ 407      
After tax charge to income $ 40 $ (76) $ 12 $ 328        
Plant Vogtle Units 3 and 4 | Georgia Power                
Public Utilities, General Disclosures [Line Items]                
Percent ownership 45.70%       45.70%      
Estimated construction financing costs $ 3,500       $ 3,500      
Construction financing costs incurred to date 3,200       3,200      
Estimated cost to complete, construction contingency estimate and additional costs 307       307      
Estimated cost to complete, additional construction contingency estimate 125       125      
Estimated cost to complete, additional construction monitoring costs 9       $ 9      
Plant Vogtle Units 3 and 4 | Georgia Power | Minimum | COVID-19                
Public Utilities, General Disclosures [Line Items]                
Estimated months of productivity loss         3 months      
Construction financing costs 160       $ 160      
Plant Vogtle Units 3 and 4 | Georgia Power | Maximum | COVID-19                
Public Utilities, General Disclosures [Line Items]                
Estimated months of productivity loss         4 months      
Construction financing costs $ 200       $ 200      
Plant Vogtle Units 3 and 4 | Georgia Power | Vogtle Owners                
Public Utilities, General Disclosures [Line Items]                
Period of notice required in the event letters of credit are not renewed         30 days      
Plant Vogtle Unit 3 | Georgia Power                
Public Utilities, General Disclosures [Line Items]                
Additional base capital costs per month (up to)         $ 15      
Plant Watson Unit 4 | Georgia Power                
Public Utilities, General Disclosures [Line Items]                
Additional base capital costs per month (up to)         $ 35