Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - USD ($)
$ in Millions
3 Months Ended 6 Months Ended 9 Months Ended
Sep. 30, 2022
Jun. 30, 2022
Dec. 31, 2021
Jun. 30, 2021
Sep. 30, 2022
Loss Contingencies [Line Items]          
Pre-tax charge to income $ (102) $ 16 $ 440   $ 353
Plant Vogtle Units 3 And 4          
Loss Contingencies [Line Items]          
Base project capital cost forecast 10,334       10,334
Construction contingency estimate 49       49
Total project capital cost forecast 10,383       10,383
Net investment as of end of the period (9,280)       (9,280)
Remaining estimate to complete 1,103       1,103
Estimated cost to complete, costs not shared with other owners 590       590
Expected capitalized costs         385
Capitalized interest accrued $ 275       $ 275
Plant Vogtle Units 3 And 4 | Twenty Fifth Vogtle Construction Monitoring Report          
Loss Contingencies [Line Items]          
Guarantor obligations       $ 1,700  
Customer refund       $ 188