Garland Solar Storage            
Business Acquisition [Line Items]            
Approximate Nameplate Capacity (MW)         88  
PPA Contract Period       20 years    
Nameplate capacity placed in service (in MWs)   15     15 73
Tranquillity Solar Storage            
Business Acquisition [Line Items]            
Approximate Nameplate Capacity (MW)         72  
PPA Contract Period     20 years      