Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - USD ($)
$ in Millions
3 Months Ended 6 Months Ended
Jun. 30, 2022
Dec. 31, 2021
Jun. 30, 2022
Jun. 30, 2021
Loss Contingencies [Line Items]        
Pre-tax charge to income $ 16 $ 440 $ 455  
Plant Vogtle Units 3 And 4        
Loss Contingencies [Line Items]        
Base project capital cost forecast 10,393   10,393  
Construction contingency estimate 60   60  
Total project capital cost forecast 10,453   10,453  
Net investment as of end of the period (8,966)   (8,966)  
Remaining estimate to complete 1,487   1,487  
Estimated cost to complete, costs not shared with other owners 590   590  
Expected capitalized costs     385  
Capitalized interest accrued $ 247   $ 247  
Plant Vogtle Units 3 And 4 | Twenty Fifth Vogtle Construction Monitoring Report        
Loss Contingencies [Line Items]        
Guarantor obligations       $ 1,700
Customer refund       $ 188