REGULATORY MATTERS - GPC Schedule of Nuclear Construction Cost and Schedule (Details) - USD ($)
$ in Millions
3 Months Ended 12 Months Ended
Dec. 31, 2021
Dec. 31, 2021
Dec. 31, 2020
Dec. 31, 2019
Commitments [Line Items]        
Total AFUDC and interest capitalized   $ 282 $ 230 $ 202
Georgia Power        
Commitments [Line Items]        
Total AFUDC and interest capitalized   190 $ 138 $ 103
Pre-tax charge to income $ 440      
Georgia Power | Plant Vogtle Units 3 and 4        
Commitments [Line Items]        
Base project capital cost forecast 10,251 10,251    
Construction contingency estimate 150 150    
Total project capital cost forecast 10,401 10,401    
Net investment (8,442) (8,442)    
Remaining estimate to complete 1,959 1,959    
Estimated cost to complete, costs not shared with other owners 590 590    
Total AFUDC and interest capitalized   375    
Total AFUDC and interest capitalized, accrual amount $ 195 $ 195