XML 152 R108.htm IDEA: XBRL DOCUMENT v3.22.0.1
REGULATORY MATTERS - APC Certificate of Convenience and Necessity and RGC (Details)
$ in Millions
3 Months Ended 12 Months Ended
Sep. 23, 2021
USD ($)
MW
Mar. 31, 2024
agreement
Dec. 31, 2021
USD ($)
project
agreement
MW
Dec. 31, 2020
USD ($)
Aug. 31, 2020
USD ($)
MW
Dec. 31, 2019
MW
Schedule of Regulatory Assets and Liabilities [Line Items]            
Construction work in progress | $     $ 8,771 $ 8,697    
Alabama Power            
Schedule of Regulatory Assets and Liabilities [Line Items]            
Approved additional generating capacity, demand-side management and distributed energy resource programs         200  
Additional generating capacity, petitioned megawatts, total           2,400
Construction work in progress | $     $ 1,147 $ 866    
Renewable generation certificate, authorized generating capacity (in MWs)     500      
Renewable generation certificate, generating capacity (in MWs)     250      
Renewable generation certificate, number of projects approved | project     5      
Renewable generation certificate, number of projects | project     2      
Renewable generation certificate, generating capacity owned by parent (in MWs)     18      
Number of purchase power agreements | agreement     3      
Alabama Power | Scenario, Forecast            
Schedule of Regulatory Assets and Liabilities [Line Items]            
Number of purchase power agreements commencing in period | agreement   2        
Alabama Power | Calhoun Power Company, LLC            
Schedule of Regulatory Assets and Liabilities [Line Items]            
Approximate nameplate capacity (in MWs) 743          
Consideration transferred | $ $ 180          
Alabama Power | Year 2020            
Schedule of Regulatory Assets and Liabilities [Line Items]            
PPA, additional generating capacity (in MWs)         240  
Alabama Power | Years 2015            
Schedule of Regulatory Assets and Liabilities [Line Items]            
PPA, additional generating capacity (in MWs)     400      
Plant Barry Unit 8 | Alabama Power            
Schedule of Regulatory Assets and Liabilities [Line Items]            
Approximate nameplate capacity (in MWs)         720  
Costs incurred, percentage of estimated in-service cost         5.00%  
Estimated in-service cost | $         $ 652  
Construction work in progress | $     $ 304