Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4 - USD ($)
$ in Millions
3 Months Ended 6 Months Ended
Mar. 31, 2021
Jun. 30, 2020
Loss Contingencies [Line Items]    
Base project capital cost forecast $ 8,619  
Construction contingency estimate 136  
Total project capital cost forecast 8,755  
Net investment as of March 31, 2021 (7,560)  
Remaining estimate to complete 1,195  
Expected capitalized costs 250  
Capitalized interest accrued 118  
Twenty Third Vogtle Construction Monitoring Report    
Loss Contingencies [Line Items]    
Guarantor obligations 1,700 $ 1,700
Customer refund $ 188 $ 188