REGULATORY MATTERS - Nuclear Construction (Details) - Georgia Power
$ in Millions
12 Months Ended
Dec. 31, 2020
USD ($)
Dec. 31, 2019
USD ($)
Dec. 31, 2009
utility
MW
Jun. 30, 2018
USD ($)
Loss Contingencies [Line Items]        
Number of construction units approved | utility     2  
Electric generating capacity (mw) | MW     1,100  
Plant Vogtle Units 3 And 4        
Loss Contingencies [Line Items]        
Percent ownership   45.70%    
Construction contingency estimate, subject to rate recovery evaluation   $ 140   $ 366
Construction financing costs   2,200    
Additional base capital costs per month   50    
AFUDC per month   $ 12    
Plant Vogtle Units 3 And 4 | Scenario, Forecast        
Loss Contingencies [Line Items]        
Construction financing costs $ 3,100      
Vogtle Owners | Plant Vogtle Units 3 And 4        
Loss Contingencies [Line Items]        
Period of notice required in the event letters of credit are not renewed   30 days