The following table summarizes charges for business and asset actions within our consolidated income statements. These charges were not recorded in segment results.
Fiscal Year Ended 30 September (Millions of U.S. Dollars)
202620252024
Project exit decisions$3,151.9 $3,623.3 $— 
Global cost reduction plan— 123.7 57.0 
Charges recorded to operating income/loss$3,151.9 $3,747.0 $57.0 
Project exit-related non-operating charges(A)
8.3 6.8 — 
Charges recorded to income/loss from continuing operations before taxes$3,160.2 $3,753.8 $57.0 
Income tax benefit
680.3 695.2 13.2 
Amount attributable to noncontrolling interests40.3 10.7 — 
Charges attributable to Air Products, after-tax$2,439.6 $3,047.9 $43.8 
(A)Non-operating expenses in fiscal year 2026 were primarily recorded through "Other non-operating income (expense), net" for losses on cross-currency interest rate swaps terminated in connection with the early repayment of intercompany loans for a coal gasification plant in China. Non-operating expenses in fiscal year 2025 were recorded through "Equity affiliates' income" and reflected an other-than-temporary impairment of a joint venture in China that had been formed to develop clean hydrogen infrastructure.
Project Exit Decisions
The Company approved actions in fiscal years 2025 and 2026 to exit certain projects in order to focus resources on projects we believe will deliver the greatest value to our shareholders. The following table summarizes cumulative charges associated with our project exit decisions by major type of cost through 30 September 2026, categorized based on the fiscal year in which the underlying decisions were made. These decisions did not result in the impairment of goodwill or intangible assets.
(Millions of U.S. Dollars)FY2026
Project Exit Decisions
FY2025
Project Exit Decisions(A)
Total
Project Exit Decisions
Asset write-downs (primarily plant and equipment)$2,234.5 $3,542.9 $5,777.4 
Other exit costs(B)
662.4 350.5 1,012.9 
Cumulative charges through 30 September 2026$2,896.9 $3,893.4 $6,790.3 
(A) Charges related to FY2025 Project Exit Decisions include $3,630.1 million recorded in fiscal year 2025 and $263.3 million recorded in fiscal year 2026. The charges recorded in fiscal year 2026 were primarily recorded during the fourth quarter and related to updated estimates associated with two coal gasification plants in China.
(B) Primarily reflects estimated costs to terminate contractual commitments and settle asset retirement obligations.
FY2026 Project Exit Decisions
In June 2026, the Company made the decision to cancel a clean energy complex under construction in Louisiana within the Americas segment that had been designed to produce low-carbon hydrogen and ammonia. The decision was based on the determination that the expected financial returns from the project would not meet the Company's return criteria. In addition, the Company approved the exit of a green hydrogen production facility under construction in Casa Grande, Arizona, within the Americas segment, as well as certain other smaller-scale projects supporting clean energy distribution. These decisions reflected challenging commercial conditions, project-specific economic factors, and slower-than-expected development in certain end markets.
Certain plant and equipment associated with these project exits is not in use and does not meet the criteria for classification as held for sale. Refer to Note 14, Fair Value Measurements, for additional information, including the methodology for determining fair value.
FY2025 Project Exit Decisions
In February 2025, the Company approved the exit of certain projects, primarily involving clean-energy generation and distribution initiatives. These actions included three U.S.-based projects within the Americas segment, several smaller-scale projects across the global portfolio, and two coal gasification plants in China.
Due to customer-related challenges, we committed to a plan to market the coal gasification plants in China for sale. The related disposal groups were classified as held for sale and measured at the lower of carrying amount or fair value less costs to sell, resulting in an initial noncash impairment charge of approximately $425 million in fiscal year 2025, primarily related to plant and equipment. As of 30 September 2025, assets held for sale associated with these disposal groups totaled $427.7 million and primarily included plant and equipment reported within the Asia segment. Related liabilities held for sale were $50.5 million.
During the fourth quarter of fiscal year 2026, we recorded additional noncash impairment charges of $231.2 million, primarily related to plant and equipment, to update our estimates of fair value less costs to sell based on information obtained through the marketing process for each disposal group. For one disposal group, we fully impaired the remaining assets due to limited buyer interest. Any potential recovery related to this disposal group will be recognized in the period in which the applicable recognition criteria are met. For the other disposal group, the carrying amount was updated to reflect the terms of a sales agreement entered into on 1 October 2026. As of 30 September 2026, assets and liabilities held for sale related to this disposal group totaled $272.8 million and $25.2 million, respectively. The assets held for sale primarily consisted of plant and equipment. Refer to Note 14, Fair Value Measurements, for additional information regarding the measurement of these assets.
In October 2026, we completed the sale of the disposal group subject to the sales agreement for total consideration of approximately $275 million.
The table below provides a reconciliation of the Company's accrued liability associated with project exit decisions included within "Payables and Accrued Liabilities" on the consolidated balance sheets:
(Millions of U.S. Dollars)FY2026
Project Exit Decisions
FY2025
Project Exit Decisions
Total
Project Exit Decisions
Liability as of 30 September 2024$— $— $— 
Estimated project exit costs accrued— 340.6 340.6 
Cash payments
— (174.4)(174.4)
Currency translation adjustment— 12.1 12.1 
Liability as of 30 September 2025$— $178.3 $178.3 
Estimated project exit costs accrued662.4 — 662.4 
Changes in estimates— (13.3)(13.3)
Cash payments
(68.3)(90.7)(159.0)
Currency translation adjustment
— 1.1 1.1 
Liability as of 30 September 2026
$594.1 $75.4 $669.5 
Estimates related to project exit decisions reflect management's best judgment based on information available when the charges were recorded. Actual results may differ from current estimates due to the resolution of contractual matters, the commercialization, redeployment, or disposition of assets, and other events that could materially impact future-period results. Certain activities associated with project exit decisions remain ongoing, including efforts to maximize the redeployment of assets to existing or future projects or the sale of assets to third parties, and to reduce exposure under existing contractual arrangements.
Global Cost Reduction Plan
In June 2023, we initiated a global cost reduction plan that provides severance and other postemployment benefits to employees designated for involuntary separation. In accordance with our accounting policy, we recognize related costs in the period management formally commits to a defined set of actions under the plan. Benefits are determined based on the terms of our established ongoing benefit arrangements. Since the plan was initiated, we have incurred cumulative costs totaling $207.7 million for over 3,600 employees globally.
The table below provides a reconciliation of the beginning and ending liability balances associated with our global cost reduction plan, which are reflected within "Payables and Accrued Liabilities" on our consolidated balance sheets:
(Millions of U.S. Dollars)
Liability as of 30 September 2023$19.8 
Estimated separation costs accrued57.0 
Cash payments(43.6)
Currency translation adjustment0.8 
Liability as of 30 September 2024
$34.0 
Estimated separation costs accrued123.7 
Cash payments(57.5)
Currency translation adjustment1.4 
Liability as of 30 September 2025
$101.6 
Cash payments(63.3)
Currency translation adjustment(0.6)
Liability as of 30 September 2026
$37.7 

The remaining liability as of 30 September 2026 primarily relates to employees identified for separation whose terminations have not yet been completed. The timing and settlement of these obligations vary based on operational considerations and applicable legal requirements in the relevant jurisdictions; however, we expect the remaining liability to be substantially settled within the next twelve months.