Variable Interest Entities VARIABLE INTEREST ENTITIES
We are the primary beneficiary of the NEOM Green Hydrogen Company joint venture ("NGHC"), a variable interest entity ("VIE") that is consolidated in our Middle East and India segment. We are not the primary beneficiary of any other material VIEs.
Our other material VIEs are those in which we hold variable interests but are not the primary beneficiary. We have an equity interest and exercise significant influence in the Jazan Integrated Gasification and Power Company joint venture ("JIGPC"), which we account for as an equity method investment in our Middle East and India segment. We have no equity interest in World Energy, LLC ("World Energy"), but hold a variable interest through a financing receivable that was fully reserved in fiscal year 2025 in connection with our exit from the SAF expansion project.
Our variable interests in NGHC, JIGPC, and World Energy are further discussed below.
NGHC Joint Venture
The NEOM Green Hydrogen Project is a multi-billion dollar green hydrogen-based ammonia production facility that is being constructed in NEOM City, Saudi Arabia. Owned and operated by NGHC, the facility will be powered by renewable energy to produce green ammonia for Air Products as the exclusive offtaker under a long-term take-if-tendered agreement.
Air Products is an equal owner in NGHC with our joint venture partners, ACWA Power and NEOM Company. While we only hold one-third of the voting interests in the joint venture, substantially all the activities of the joint venture involve or are conducted on behalf of Air Products. Since we have disproportionately few voting rights relative to our economic interests in the joint venture, we determined that NGHC is a VIE. In addition, we determined that we are the primary beneficiary of NGHC since we have the power to unilaterally direct certain significant activities, including key design and construction decisions, and we share power with our joint venture partners related to other activities that are significant to the economic performance of NGHC. Therefore, we consolidate NGHC within the Middle East and India segment.
Under the project financing discussed below, the assets of NGHC can only be used to settle obligations of the joint venture, and creditors of NGHC do not have recourse to the general credit of Air Products. A table summarizing balances associated with NGHC as reflected on our consolidated balance sheets is provided on page 89.
Project Financing
In May 2023, NGHC finalized the $6.7 billion engineering, procurement, and construction agreement, naming Air Products as the main contractor and system integrator for the facility. To support the project, NGHC secured project financing that is non-recourse to Air Products of approximately $6.1 billion, which is expected to fund about 73% of the project and will be drawn over the construction period. At the same time, NGHC secured additional credit facilities totaling approximately $500, primarily for NGHC's working capital needs. These facilities are also non-recourse to Air Products.
Total principal borrowings were $4.9 billion and $3.3 billion as of 30 September 2025 and 2024, respectively. These balances include short-term borrowings of $24.0 and $51.6, respectively, under a variable-rate Saudi Riyal facility, which carried an interest rate of 6.30% as of 30 September 2025. The remaining borrowings are from long-term facilities, which are reflected net of unamortized discounts and debt issuance costs within "Long-term debt" on our consolidated balance sheets. A summary of NGHC's long-term borrowings is provided in the table below:
30 SeptemberFiscal Year Maturities20252024
Payable in U.S. Dollars
U.S. Dollar variable-rate facilities 5.49%(A)
2027 to 2053$2,911.0 $1,945.2 
U.S. Dollar variable-rate facility 5.14%(A)
2027 to 2041630.6 345.5 
U.S. Dollar stated-rate facility 5.00%
2027 to 2053368.0 245.9 
Total Payable in U.S. Dollars
$3,909.6 $2,536.6 
Payable in Other Currencies
Saudi Riyal stated-rate facility 2.00%
2028 to 20411,000.1 735.2 
Total Principal Amount
$4,909.7 $3,271.8 
Less: Unamortized discount and debt issuance costs(B)
232.1 218.5 
Total NGHC Long-term Debt$4,677.6 $3,053.3 
(A)Reflects a daily compounded SOFR as of 30 September 2025 plus an annual margin of 1.31% and 0.96%, respectively. These rates do not include the impact of our floating-to-fixed interest rate swaps, which result in an overall lower interest rate for the borrowings. Additional information regarding these instruments is provided below.
(B)Our consolidated balance sheets as of 30 September 2025 and 2024 also included $3.8 and $4.6, respectively, for remaining project financing fees that were eligible for deferral as a noncurrent asset. As additional borrowings are drawn, the unamortized balance is reclassified as an offset to the outstanding debt.
Interest Rate Swaps
In May 2023, NGHC entered into floating-to-fixed interest rate swaps designed to hedge the long-term variable rate debt facilities available under the project financing during the construction period of the project. We discontinued cash flow hedge accounting for certain swaps during the third quarter of fiscal year 2024 due to changes in the anticipated drawdown timeline for the hedged borrowings. As a result of the de-designation, unrealized gains and losses are recorded to "Other non-operating income (expense), net" on our consolidated income statements as summarized in the table below:
Fiscal Year Ended 30 September202520242023
Gain (loss) on de-designation of cash flow hedges$27.0 ($16.3)$— 
Amount attributable to noncontrolling partners in NGHC17.6 (10.6)— 
Amount attributable to Air Products after tax7.2 (4.3)— 
We re-designated certain affected swaps as outstanding borrowings under the available project financing became commensurate with the swaps’ notional values. The remaining de-designated swaps will continue to be excluded from hedge accounting until additional borrowings align with their notional amounts, at which point they may re-qualify for cash flow hedge accounting.
Land Lease
The green hydrogen-based ammonia production facility is being constructed on land owned by our joint venture partner, NEOM Company. NGHC signed a 50-year lease agreement for the site, which commenced during the third quarter of fiscal year 2023. As a result, we recognized an operating lease with a right-of-use asset and corresponding liability of $223, of which $209 was paid as a lump-sum in August 2023. Additional lease payments are due after the first 30 years of the lease term.
NGHC Balance Sheet
The table below summarizes balances associated with NGHC as reflected on our consolidated balance sheets:
30 September 30 September
20252024
Assets
Cash and cash items$40.3 $34.5 
Trade receivables, net1.1 6.7 
Prepaid expenses20.7 31.2 
Other receivables and current assets107.2 120.6 
Total Current Assets$169.3 $193.0 
Plant and equipment, net6,593.9 3,929.9 
Operating lease right-of-use assets, net218.0 233.9 
Other noncurrent assets153.5 37.1 
Total Noncurrent Assets$6,965.4 $4,200.9 
Total Assets$7,134.7 $4,393.9 
Liabilities
Payables and accrued liabilities$201.7 $308.4 
Accrued income taxes1.2 2.0 
Short-term borrowings24.0 51.6 
Total Current Liabilities$226.9 $362.0 
Long-term debt4,677.6 3,053.3 
Noncurrent operating lease liabilities17.8 24.5 
Other noncurrent liabilities1.6 30.4 
Deferred income taxes13.8 3.2 
Total Noncurrent Liabilities$4,710.8 $3,111.4 
Total Liabilities$4,937.7 $3,473.4 
Equity
Accumulated other comprehensive income$38.3 $13.8 
Noncontrolling interests1,493.6 937.6 
JIGPC Joint Venture
JIGPC is a joint venture with Saudi Aramco Power Company (a subsidiary of Aramco), ACWA Power, and Air Products Qudra (“APQ”). JIGPC entered into project financing to purchase power blocks, gasifiers, air separation units, syngas cleanup assets, and utilities to supply electricity, steam, hydrogen, and utilities to Aramco’s refinery and terminal complex under a 25-year agreement, which commenced in the first quarter of fiscal year 2022. JIGPC recorded financing receivables upon acquisition of the assets and recognizes financing income over the supply term.
We determined JIGPC is a VIE for which we exercise significant influence but are not the primary beneficiary as we do not have the power to direct the activities that are most significant to its economic performance. Instead, these activities, including plant dispatch, operating and maintenance decisions, budgeting, capital expenditures, and financing, require unanimous approval of the owners or are controlled by the customer. Accordingly, we account for our 55% investment, which includes 4% that is attributable to the noncontrolling partner of APQ, under the equity method within the Middle East and India segment.
Our loss exposure is limited to our investment in the joint venture. The carrying value of our investment, including amounts attributable to noncontrolling interests, totaled $3.1 billion and $2.9 billion as of 30 September 2025 and 2024, respectively. The balance as of 30 September 2025 reflects a final investment of approximately $115 that we completed during the second quarter of fiscal year 2025. This investment was made in the form of a shareholder loan, which the joint venture used to purchase the remaining project assets.
Our total investment in JIGPC primarily consists of shareholder loans that qualify as in-substance common stock in the joint venture. Certain shareholders receive a preferred cash distribution pursuant to the joint venture agreement, which specifies each shareholder’s share of income after considering the amount of cash available for distribution. As such, the earnings attributable to Air Products may not be proportionate to our ownership interest in the venture.
World Energy
In November 2023, we purchased a sustainable aviation fuel (“SAF”) facility in Paramount, California, from World Energy and accounted for the transaction as a financing arrangement because the agreement contained an embedded sales-type lease. As of 30 September 2024, the related financing receivable had a carrying value of approximately $300. Additionally, we entered into a Master Project Agreement ("MPA") that included terms for operation of the acquired facility as well as amended terms for the construction and operation of an SAF expansion project subject to construction at the same location. The MPA also included a tolling arrangement whereby we would receive feedstock from and produce renewable fuels for World Energy over a term to conclude 15 years after onstream of the expansion project with the option to renew for two five-year terms. Subsequently, the expansion project was put on hold pending receipt of permits.
We determined that World Energy is a VIE, and our financing receivable represented a variable interest in World Energy. We are not the primary beneficiary as we do not have control over their key operating decisions, including feedstock supply, production of renewable fuels, and negotiating and executing supply agreements with customers.
During the second quarter of fiscal year 2025, we terminated the MPA and announced our decision to exit the project. In connection with this decision, we recorded project exit charges totaling approximately $1.9 billion, the majority of which were recognized at the time of the announcement. The charges included approximately $1.6 billion to write down assets that had primarily been reflected within "Plant and equipment, net" and $300 to establish an allowance for credit loss equal to the value of the financing receivable, which had previously been placed on non-accrual status. The remaining charge primarily reflects estimated costs to terminate contractual commitments and satisfy other obligations associated with exiting the site. We have no further loss exposure related to our variable interest in World Energy as of 30 September 2025; however, there could be future impacts to earnings as we finalize our exit from the project.