XML 29 R12.htm IDEA: XBRL DOCUMENT v3.5.0.2
Regulatory Matters
9 Months Ended
Sep. 30, 2016
Public Utilities, General Disclosures [Abstract]  
Regulatory Matters
REGULATORY MATTERS
2016 Electric Rate Case Filing
DTE Electric filed a rate case with the MPSC on February 1, 2016 requesting an increase in base rates of $344 million based on a projected twelve-month period ending July 31, 2017. The requested increase in base rates is due primarily to an increase in net plant resulting from infrastructure investments, environmental compliance, and reliability improvement projects. The rate filing also includes projected changes in sales, operation and maintenance expenses, and working capital. The rate filing also requests an increase in return on equity from 10.3% to 10.5% on a capital structure of 50% equity and 50% debt. On August 1, 2016, DTE Electric self-implemented a base rate increase of $245 million. An MPSC final order in this case is expected by February 2017.
2015 DTE Gas Rate Case Filing
DTE Gas filed a rate case with the MPSC on December 18, 2015 requesting an increase in base rates of $183 million, inclusive of $41 million of existing IRM surcharges which are expected to be converted into base rates, based on a projected twelve-month period ending October 31, 2017. The requested increase in base rates is due primarily to an increase in net plant, inclusive of IRM capital investments being recovered through approved IRM surcharge filings. The rate filing also includes projected changes in sales, operation and maintenance expenses, and working capital. The rate filing also requests an increase in return on equity from 10.5% to 10.75% on a capital structure of 52% equity and 48% debt. Concurrent with the MPSC order in this rate case, the existing IRM surcharge being billed will be terminated. However, DTE Gas requested to implement a new IRM surcharge of approximately $9 million to become effective in January 2017. On May 11, 2016, DTE Gas filed an application with the MPSC for a $103 million self-implemented base rate increase effective November 1, 2016. An MPSC final order in this case is expected by December 2016.