COMMITMENTS AND CONTINGENCIES
Environmental
DTE Electric
Air — DTE Electric is subject to the EPA ozone and fine particulate transport and acid rain regulations that limit power plant emissions of sulfur dioxide and nitrogen oxides. The EPA and the State of Michigan have issued emission reduction regulations relating to ozone, fine particulate, regional haze, mercury, and other air pollution. These rules have led to controls on fossil-fueled power plants to reduce nitrogen oxide, sulfur dioxide, mercury and other emissions. Additional rulemakings are expected over the next few years which could require additional controls for sulfur dioxide, nitrogen oxides, and hazardous air pollutants.
The Mercury and Air Toxics Standards (MATS) rule, formerly known as the Electric Generating Unit Maximum Achievable Control Technology (EGU MACT) Rule was finalized in December 2011. The MATS rule required reductions of mercury and other hazardous air pollutants beginning in April 2015. DTE Electric requested and was granted compliance date extensions for all relevant units to April 2016. In November 2014, the U.S. Supreme Court agreed to review a challenge to the MATS rule based on a narrowly focused question of how the EPA considered costs in regulating air pollutants emitted by electric utilities. In June 2015, the U.S. Supreme Court reversed the decision of the Court of Appeals for the D.C. District and remanded the MATS rule to the Court of Appeals for further consideration based on their decision that the EPA must consider costs prior to deciding to regulate under the provisions of the Clean Air Act. Subsequently, in December 2015, the Court of Appeals ordered a remand of the MATS rule back to the EPA without staying the rule. DTE Electric does not expect this decision to have a material effect on its compliance plans at this time.
In July 2009, DTE Energy received a NOV/FOV from the EPA alleging, among other things, that five DTE Electric power plants violated New Source Performance standards, Prevention of Significant Deterioration requirements, and operating permit requirements under the Clean Air Act. In June 2010, the EPA issued a NOV/FOV making similar allegations related to a project and outage at Unit 2 of the Monroe Power Plant. In March 2013, DTE Energy received a supplemental NOV from the EPA relating to the July 2009 NOV/FOV. The supplemental NOV alleged additional violations relating to the New Source Review provisions under the Clean Air Act, among other things.
In August 2010, the U.S. Department of Justice, at the request of the EPA, brought a civil suit in the U.S. District Court for the Eastern District of Michigan against DTE Energy and DTE Electric, related to the June 2010 NOV/FOV and the outage work performed at Unit 2 of the Monroe Power Plant. In August 2011, the U.S. District Court judge granted DTE Energy's motion for summary judgment in the civil case, dismissing the case and entering judgment in favor of DTE Energy and DTE Electric. In October 2011, the EPA caused to be filed a Notice of Appeal to the Court of Appeals for the Sixth Circuit. In March 2013, the Court of Appeals remanded the case to the U.S. District Court for review of the procedural component of the New Source Review notification requirements. In September 2013, the EPA caused to be filed a motion seeking leave to amend their complaint regarding the June 2010 NOV/FOV adding additional claims related to outage work performed at the Trenton Channel and Belle River Power Plants as well as additional claims related to work performed at the Monroe Power Plant. In March 2014, the U.S. District Court judge granted again DTE Energy's motion for summary judgment dismissing the civil case related to Monroe Unit 2. In April 2014, the U.S. District Court judge granted motions filed by the EPA and the Sierra Club to amend their New Source Review complaint adding additional claims for Monroe Units 1, 2 and 3, Belle River Units 1 and 2, and Trenton Channel Unit 9. In October 2014, the EPA and the U.S. Department of Justice filed a notice of appeal of the U.S. District Court judge's dismissal of the Monroe Unit 2 case. The amended New Source Review claims are all stayed until the appeal is resolved by the Court of Appeals for the Sixth Circuit. Oral arguments for the appeal occurred in December 2015.
The Registrants believe that the plants and generating units identified by the EPA and the Sierra Club have complied with all applicable federal environmental regulations. Depending upon the outcome of discussions with the EPA regarding the two NOVs/FOVs, DTE Electric could be required to install additional pollution control equipment at some or all of the power plants in question, implement early retirement of facilities where control equipment is not economical, engage in supplemental environmental programs, and/or pay fines. The Registrants cannot predict the financial impact or outcome of this matter, or the timing of its resolution.
The EPA is implementing regulatory actions under the Clean Air Act to address emissions of GHGs from the utility sector and other sectors of the economy. Among these actions, the EPA finalized performance standards for emissions of carbon dioxide from new and existing electric generating units (EGUs). The carbon standards for new sources are not expected to have a material impact on DTE Electric, since DTE Electric has no plans to build new coal-fired generation and any potential new gas generation will be able to comply with the standards. In February 2016, the U.S. Supreme Court granted petitioners' requests for a stay of the carbon rules for existing EGUs (also known as the EPA Clean Power Plan) pending final review by the courts. The Clean Power Plan has no legal effect while the stay is in place. It is not possible to determine the potential impact of the EPA Clean Power Plan on existing sources at this time. Pending or future legislation or other regulatory actions could have a material impact on DTE Electric's operations and financial position and the rates charged to its customers. Impacts include expenditures for environmental equipment beyond what is currently planned, financing costs related to additional capital expenditures, the purchase of emission credits from market sources, higher costs of purchased power, and the retirement of facilities where control equipment is not economical. DTE Electric would seek to recover these incremental costs through increased rates charged to its utility customers, as authorized by the MPSC.
To comply with air pollution requirements, DTE Electric spent approximately $2.3 billion through 2015. DTE Electric estimates making capital expenditures of approximately $45 million in 2016.
Coal Combustion Residuals and Effluent Limitations Guidelines — A final EPA rule for the disposal of coal combustion residuals, commonly known as coal ash, became effective in October 2015. DTE Electric owns and operates three permitted engineered coal ash storage facilities to dispose of coal ash from coal-fired power plants and operates a number of smaller impoundments at its power plants. At certain facilities, the rule requires the installation of monitoring wells, compliance with groundwater standards, and the closure of basins at the end of the useful life of the associated power plant. At other facilities, the rule requires ash laden waters be moved from earthen basins to steel and concrete tanks.
In November 2015, the EPA finalized effluent limitations guidelines for the steam electric power generating industry which may require additional controls to be installed between 2018 and 2023. Compliance schedules for individual facilities and individual waste streams are determined through issuance of new wastewater permits by the State of Michigan. No new permits have been issued, consequently no compliance timelines have been established. Certain effluent limitations guidelines requirements will be required to be performed in conjunction with the coal combustion residuals requirements. Costs associated with the building of new facilities over the next seven years to comply with coal combustion residuals requirements and effluent limitations guidelines are estimated to be approximately $290 million.
Non-utility
DTE Energy's non-utility businesses are subject to a number of environmental laws and regulations dealing with the protection of the environment from various pollutants.
The Shenango coke battery received two NOVs from the Pennsylvania Department of Environmental Protection (PADEP) in 2010 alleging violations of the permit for the Pennsylvania coke battery facility in connection with coal pile storm water runoff. DTE Energy settled the alleged violations by implementing best management practices to address the issues and repair/upgrade its wastewater treatment plant. DTE Energy received a construction permit to upgrade its existing waste water treatment system. Due to the December 2015 decision to close the Shenango coke battery in January 2016, DTE Energy will not proceed with the upgrade to its wastewater treatment system.
The decision to close the Shenango facility has prompted the PADEP, the EPA, and the Allegheny County, PA Health Department to submit demand letters under the 2012 consent decree for stipulated penalties related to water and air matters since 2012. The stipulated penalties totaling $534,000 have been assessed to the facility of which $189,000 remains unpaid as of March 31, 2016. DTE Energy is currently working with the respective regulatory agencies to settle all matters.
Nuclear Operations
Nuclear Fuel Disposal Costs
DTE Electric currently employs a spent nuclear fuel storage strategy utilizing a fuel pool and a newly completed dry cask storage facility. The dry cask storage facility is expected to provide sufficient spent fuel storage capability for the life of the plant as defined by the original operating license.
The federal government continues to maintain its legal obligation to accept spent nuclear fuel from Fermi 2 for permanent storage. Issues relating to long-term waste disposal policy and to the disposition of funds contributed by DTE Electric ratepayers to the federal waste fund await future governmental action.
Synthetic Fuel Guarantees
DTE Energy discontinued the operations of its synthetic fuel production facilities throughout the United States as of December 31, 2007. DTE Energy provided certain guarantees and indemnities in conjunction with the sales of interests in its synfuel facilities. The guarantees cover potential commercial, environmental, oil price, and tax-related obligations that will survive until 90 days after expiration of all applicable statutes of limitations. DTE Energy estimates that its maximum potential liability under these guarantees at March 31, 2016 is approximately $850 million. Payment under these guarantees is considered remote.
REF Guarantees
DTE Energy has provided certain guarantees and indemnities in conjunction with the sales of interests in or lease of its REF facilities. The guarantees cover potential commercial, environmental, and tax-related obligations that will survive until 90 days after expiration of all applicable statutes of limitations. DTE Energy estimates that its maximum potential liability under these guarantees at March 31, 2016 is approximately $270 million. Payment under these guarantees is considered remote.
Other Guarantees
In certain limited circumstances, the Registrants enter into contractual guarantees. The Registrants may guarantee another entity’s obligation in the event it fails to perform and may provide guarantees in certain indemnification agreements. Finally, the Registrants may provide indirect guarantees for the indebtedness of others. DTE Energy’s guarantees are not individually material with maximum potential payments totaling $56 million at March 31, 2016. Payment under these guarantees is considered remote.
DTE Energy is periodically required to obtain performance surety bonds in support of obligations to various governmental entities and other companies in connection with its operations. As of March 31, 2016, DTE Energy had approximately $56 million of performance bonds outstanding. In the event that such bonds are called for nonperformance, DTE Energy would be obligated to reimburse the issuer of the performance bond. DTE Energy is released from the performance bonds as the contractual performance is completed and does not believe that a material amount of any currently outstanding performance bonds will be called.
Bankruptcies
Certain of the Registrants' customers and suppliers have filed for bankruptcy protection under the U.S. Bankruptcy Code. The Registrants regularly review contingent matters relating to these customers and suppliers and their purchase and sale contracts, and record provisions for amounts considered at risk of probable loss in the allowance for doubtful accounts. The Registrants believe their accrued amounts are adequate for probable loss.
Other Contingencies
The Registrants are involved in certain other legal, regulatory, administrative, and environmental proceedings before various courts, arbitration panels, and governmental agencies concerning claims arising in the ordinary course of business. These proceedings include certain contract disputes, additional environmental reviews and investigations, audits, inquiries from various regulators, and pending judicial matters. The Registrants cannot predict the final disposition of such proceedings. The Registrants regularly review legal matters and record provisions for claims that they can estimate and are considered probable of loss. The resolution of these pending proceedings is not expected to have a material effect on the Registrants' Consolidated Financial Statements in the periods they are resolved.