XML 90 R23.htm IDEA: XBRL DOCUMENT v2.4.1.9
Commitments and Contingencies (Notes)
12 Months Ended
Dec. 31, 2014
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
COMMITMENTS AND CONTINGENCIES
Environmental
Air  DTE Electric is subject to the EPA ozone and fine particulate transport and acid rain regulations that limit power plant emissions of sulfur dioxide and nitrogen oxides. The EPA and the State of Michigan have issued emission reduction regulations relating to ozone, fine particulate, regional haze, mercury, and other air pollution. These rules have led to controls on fossil-fueled power plants to reduce nitrogen oxide, sulfur dioxide, mercury and other emissions. To comply with these requirements, DTE Electric spent approximately $2.2 billion through 2014. The Company estimates DTE Electric will make capital expenditures of approximately $100 million in 2015 and up to approximately $30 million of additional capital expenditures through 2019 based on current regulations.
Additional rulemakings are expected over the next few years which could require additional controls for sulfur dioxide, nitrogen oxides and other hazardous air pollutants. The Cross State Air Pollution Rule (CSAPR), requires further reductions of sulfur dioxide and nitrogen oxides emissions effective in January 2015. DTE Electric expects to meet its obligations under CSAPR beginning in 2015.
The Mercury and Air Toxics Standard (MATS) rule, formerly known as the Electric Generating Unit Maximum Achievable Control Technology (EGU MACT) Rule was finalized in December 2011. The MATS rule requires reductions of mercury and other hazardous air pollutants beginning in April 2015, with a potential extension to April 2016. DTE Electric has requested and been granted compliance date extensions for all relevant units to April 2016. DTE Electric has tested technologies to determine technological and economic feasibility as MATS compliance alternatives to Flue Gas Desulfurization (FGD) systems. Implementation of Dry Sorbent Injection (DSI) and Activated Carbon Injection (ACI) technologies will allow several units that would not have been economical for FGD installations to continue operation in compliance with MATS. In November 2014, the Supreme Court agreed to review a challenge to the MATS rule based on a narrowly focused question of how the EPA considered costs in regulating air pollutants emitted by electric utilities. DTE Electric cannot predict the financial impact or outcome of this Supreme Court case, or the timing of its resolution.
The EPA proposed revised air quality standards for ground level ozone in November 2014 and the standards are expected to be finalized by October 2015. DTE Electric will engage with the EPA and other stakeholders in commenting on this rule. DTE Electric cannot predict the financial impact of the proposed ozone standards at this time.
In July 2009, DTE Energy received a NOV/FOV from the EPA alleging, among other things, that five DTE Electric power plants violated New Source Performance standards, Prevention of Significant Deterioration requirements, and operating permit requirements under the Clean Air Act. In June 2010, the EPA issued a NOV/FOV making similar allegations related to a project and outage at Unit 2 of the Monroe Power Plant. In March 2013, DTE Energy received a supplemental NOV from the EPA relating to the July 2009 NOV/FOV. The supplemental NOV alleged additional violations relating to the New Source Review provisions under the Clean Air Act, among other things.
In August 2010, the U.S. Department of Justice, at the request of the EPA, brought a civil suit in the U.S. District Court for the Eastern District of Michigan against DTE Energy and DTE Electric, related to the June 2010 NOV/FOV and the outage work performed at Unit 2 of the Monroe Power Plant, but not relating to the July 2009 NOV/FOV. Among other relief, the EPA requested the court to require DTE Electric to install and operate the best available control technology at Unit 2 of the Monroe Power Plant. Further, the EPA requested the court to issue a preliminary injunction to require DTE Electric to (i) begin the process of obtaining the necessary permits for the Monroe Unit 2 modification and (ii) offset the pollution from Monroe Unit 2 through emissions reductions from DTE Electric's fleet of coal-fired power plants until the new control equipment is operating. On August 23, 2011, the U.S. District Court judge granted DTE Energy's motion for summary judgment in the civil case, dismissing the case and entering judgment in favor of DTE Energy and DTE Electric. In October 2011, the EPA caused to be filed a Notice of Appeal to the U.S. Court of Appeals for the Sixth Circuit. In March 2013, the Court of Appeals remanded the case to the U.S. District Court for review of the procedural component of the New Source Review notification requirements. In September 2013, the EPA caused to be filed a motion seeking leave to amend their complaint regarding the June 2010 NOV/FOV adding additional claims related to outage work performed at the Trenton Channel and Belle River power plants as well as additional claims related to work performed at the Monroe Power Plant. In addition, the Sierra Club caused to be filed a motion to add a claim regarding the River Rouge Power Plant. In March 2014, the U.S. District Court judge granted again DTE Energy's motion for summary judgment dismissing the civil case related to Monroe Unit 2. In April 2014, the U.S. District Court judge granted motions filed by the EPA and the Sierra Club to amend their New Source Review complaint adding additional claims for Monroe Units 1, 2 and 3, Belle River Units 1 and 2, Trenton Channel Unit 9 and denied the claims related to River Rouge that were brought by the Sierra Club. In June 2014, the EPA filed a motion requesting certification for appeal of the March 2014 summary judgment decision. In October 2014, the EPA and the U.S. Department of Justice filed the anticipated notice of appeal of the U.S. District Court judge's dismissal of the Monroe Unit 2 case. This will officially start the appellate process. The amended New Source Review claims are all stayed until the appeal is resolved by the U.S. Court of Appeals for the Sixth Circuit.
DTE Energy and Electric believes that the plants and generating units identified by the EPA and the Sierra Club have complied with all applicable federal environmental regulations. Depending upon the outcome of discussions with the EPA regarding the two NOVs/FOVs, DTE Electric could be required to install additional pollution control equipment at some or all of the power plants in question, implement early retirement of facilities where control equipment is not economical, engage in supplemental environmental programs, and/or pay fines. The Company cannot predict the financial impact or outcome of this matter, or the timing of its resolution.
In 2010, the EPA finalized a new 1-hour sulfur dioxide ambient air quality standard that requires states to submit plans for non-attainment areas to be in compliance by 2017. Michigan's non-attainment area includes DTE Electric facilities in southwest Detroit and areas of Wayne County. Preliminary modeling runs by the MDEQ suggest that emission reductions may be required by significant sources of sulfur dioxide emissions in these areas, including DTE Electric power plants. The state implementation plan process is in the information gathering stage, and DTE Electric is unable to estimate any required emissions reductions at this time.
Water  In response to an EPA regulation, DTE Electric would be required to examine alternatives for reducing the environmental impacts of the cooling water intake structures at several of its facilities. Based on the results of completed studies and expected future studies, DTE Electric may be required to install technologies to reduce the impacts of the water intake structures. A final rule was issued in May 2014. The final rule specifies a time period exceeding three years to complete studies to determine the type of technology needed to reduce impacts to fish. Final compliance for the installation of the required technology will be determined by each state on a case by case basis. We are currently evaluating the compliance options and working with the State of Michigan on evaluating whether any controls are needed. These evaluations/studies may require modifications to some existing intake structures. It is not possible to quantify the impact of this rulemaking at this time.
In April 2013, the EPA proposed revised steam electric effluent guidelines regulating wastewater streams from coal-fired power plants including multiple possible options for compliance. The rules are expected to be finalized by September 2015. It is not possible at this time to quantify the impacts of these developing requirements.
Contaminated and Other Sites — Prior to the construction of major interstate natural gas pipelines, gas for heating and other uses was manufactured locally from processes involving coal, coke or oil. The facilities, which produced gas, have been designated as MGP sites. DTE Electric conducted remedial investigations at contaminated sites, including three former MGP sites. The investigations have revealed contamination related to the by-products of gas manufacturing at each MGP site. In addition to the MGP sites, the Company is also in the process of cleaning up other contaminated sites, including the area surrounding an ash landfill, electrical distribution substations, electric generating power plants, and underground and aboveground storage tank locations. The findings of these investigations indicated that the estimated cost to remediate these sites is expected to be incurred over the next several years. At December 31, 2014 and 2013, the Company had $10 million and $8 million accrued for remediation, respectively. Any change in assumptions, such as remediation techniques, nature and extent of contamination and regulatory requirements, could impact the estimate of remedial action costs for the sites and affect the Company’s financial position and cash flows. The Company believes the likelihood of a material change to the accrued amount is remote based on current knowledge of the conditions at each site.
In December 2014, the EPA released a pre-publication version of a rule to regulate coal ash. This rule is based on the continued listing of ash as a non-hazardous waste, and relies on various self-implementation design and performance standards. The rule is still being evaluated and it is not possible to quantify its impact at this time. DTE Electric owns and operates three permitted engineered ash storage facilities to dispose of fly ash from coal fired power plants and operates a number of smaller impoundments at its power plants.
Nuclear Operations
Property Insurance
DTE Electric maintains property insurance policies specifically for the Fermi 2 plant. These policies cover such items as replacement power and property damage. The NEIL is the primary supplier of the insurance policies.
DTE Electric maintains a policy for extra expenses, including replacement power costs necessitated by Fermi 2's unavailability due to an insured event. This policy has a 12-week waiting period and provides an aggregate $490 million of coverage over a three-year period.
DTE Electric has $1.5 billion in primary coverage and $1.25 billion of excess coverage for stabilization, decontamination, debris removal, repair and/or replacement of property and decommissioning. The combined coverage limit for total property damage is $2.75 billion, subject to a $1 million deductible. The total limit for property damage for non-nuclear events is $2 billion and an aggregate of $328 million of coverage for extra expenses over a two-year period.
On January 13, 2015, the Terrorism Risk Insurance Program Reauthorization Act of 2015 was signed, extending TRIA through December 31, 2020. For multiple terrorism losses caused by acts of terrorism not covered under the TRIA occurring within one year after the first loss from terrorism, the NEIL policies would make available to all insured entities up to $3.2 billion, plus any amounts recovered from reinsurance, government indemnity, or other sources to cover losses.
Under NEIL policies, DTE Electric could be liable for maximum assessments of up to approximately $35 million per event if the loss associated with any one event at any nuclear plant should exceed the accumulated funds available to NEIL.
Public Liability Insurance
As required by federal law, DTE Electric maintains $375 million of public liability insurance for a nuclear incident. For liabilities arising from a terrorist act outside the scope of TRIA, the policy is subject to one industry aggregate limit of $300 million. Further, under the Price-Anderson Amendments Act of 2005, deferred premium charges up to $127 million could be levied against each licensed nuclear facility, but not more than $19 million per year per facility. Thus, deferred premium charges could be levied against all owners of licensed nuclear facilities in the event of a nuclear incident at any of these facilities.
Nuclear Fuel Disposal Costs
In accordance with the Federal Nuclear Waste Policy Act of 1982, DTE Electric has a contract with the DOE for the future storage and disposal of spent nuclear fuel from Fermi 2 that required DTE Electric to pay the DOE a fee of 1 mill per kWh of Fermi 2 electricity generated and sold. The fee was a component of nuclear fuel expense. The DOE's Yucca Mountain Nuclear Waste Repository program for the acceptance and disposal of spent nuclear fuel was terminated in 2011. DTE Electric is a party in the litigation against the DOE for both past and future costs associated with the DOE's failure to accept spent nuclear fuel under the timetable set forth in the Federal Nuclear Waste Policy Act of 1982. In July 2012, DTE Electric executed a settlement agreement with the federal government for costs associated with the DOE's delay in acceptance of spent nuclear fuel from Fermi 2 for permanent storage. The settlement agreement, including extensions, provides for a claims process and payment of delay-related costs experienced by DTE Electric through 2016. DTE Electric's claims are being settled and paid on a timely basis. The settlement proceeds reduce the cost of the dry cask storage facility assets and provide reimbursement for related operating expenses. The 1 mill per kWh fee was reduced to zero effective May 16, 2014.
DTE Electric currently employs a spent nuclear fuel storage strategy utilizing a fuel pool and a newly completed dry cask storage facility. The initial dry cask loading campaign planned for 2014 has been completed. The dry cask storage facility is expected to provide sufficient spent fuel storage capability for the life of the plant as defined by the original operating license.
The federal government continues to maintain its legal obligation to accept spent nuclear fuel from Fermi 2 for permanent storage. Issues relating to long-term waste disposal policy and to the disposition of funds contributed by DTE Electric ratepayers to the federal waste fund await future governmental action.
Guarantees
In certain limited circumstances, the Company enters into contractual guarantees. The Company may guarantee another entity’s obligation in the event it fails to perform. The Company may provide guarantees in certain indemnification agreements. Finally, the Company may provide indirect guarantees for the indebtedness of others.
Labor Contracts
There are several bargaining units for the Company's approximately 2,600 represented employees. The majority of the represented employees are under contracts that expire in 2016 and 2017.
Purchase Commitments
As of December 31, 2014, the Company was party to numerous long-term purchase commitments relating to a variety of goods and services required for the Company’s business. These agreements primarily consist of fuel supply commitments and renewable energy contracts. The Company estimates that these commitments will be approximately $2.4 billion from 2015 through 2033 as detailed in the following table:
 
(In millions)
2015
$
496

2016
330

2017
278

2018
125

2019
106

2020 and thereafter
1,063

 
$
2,398


The Company also estimates that 2015 capital expenditures will be approximately $1.9 billion. The Company has made certain commitments in connection with expected capital expenditures.
Bankruptcies
The Company purchases and sells electricity from and to governmental entities and numerous companies operating in the steel, automotive, energy, retail and other industries. Certain of its customers have filed for bankruptcy protection under the U.S. Bankruptcy Code. The Company regularly reviews contingent matters relating to these customers and its purchase and sale contracts and records provisions for amounts considered at risk of probable loss. The Company believes its accrued amounts are adequate for probable loss.
Other Contingencies
The Company is involved in certain other legal, regulatory, administrative and environmental proceedings before various courts, arbitration panels and governmental agencies concerning claims arising in the ordinary course of business. These proceedings include certain contract disputes, additional environmental reviews and investigations, audits, inquiries from various regulators, and pending judicial matters. The Company cannot predict the final disposition of such proceedings. The Company regularly reviews legal matters and records provisions for claims that it can estimate and are considered probable of loss. The resolution of these pending proceedings is not expected to have a material effect on the Company’s operations or financial statements in the periods they are resolved.
For a discussion of contingencies related to regulatory matters see Note 7 to the Consolidated Financial Statements, "Regulatory Matters".