COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
Mexico Litigation Matters
As of December 31, 2023, $31.2 million in principal is due from the Mexican government associated with amounts that were paid as VAT under Coeur Mexicana, S.A. de C.V.’s (“Coeur Mexicana’s”) prior royalty agreement with a subsidiary of Franco-Nevada Corporation, which was terminated in 2016. Coeur Mexicana applied for and initially received refunds in the normal course of these amounts paid as VAT associated with the royalty payments; however, in 2011 the Mexican tax authorities began denying refunds of these amounts based on the argument that VAT was not legally due on the royalty payments. Accordingly, Coeur Mexicana began to request refunds of these amounts paid as VAT as undue payments, which the Mexican tax authorities also denied. The Company has since been engaged in ongoing efforts to recover these amounts from the Mexican government (including through refiling refund requests as undue payments rather than refunds of VAT that was due, litigation and international arbitration). Despite a favorable ruling from Mexican tax courts in this matter in 2018, litigation of the matter continued at the Mexican administrative, appeals court and supreme court levels for several years, most of which was determined unfavorably to Coeur based on interpretations of applicable law and prior court decisions which the Company and its counsel believe are contrary to legal precedent, conflicting and erroneous. While the Company believes that it remains legally entitled to be refunded the full amount of the receivable and intends to rigorously continue its recovery efforts, based on the continued failure to recover the receivable and unfavorable Mexican court decisions, the Company determined to write down the carrying value of the receivable at September 30, 2021. Coeur has elected to initiate an arbitration proceeding under Chapter 11 of the North American Free Trade Agreement, or NAFTA, to pursue recovery of the unduly paid VAT plus interest and other damages. Outcomes in NAFTA arbitration and the process for recovering funds even if there is a successful outcome in NAFTA arbitration can be lengthy and unpredictable.
In addition, ongoing litigation with the Mexican government associated with enforcement of water rights in Mexico, if unsuccessful, may impact Coeur Mexicana’s ability to access new sources of water to provide sufficient supply for its operations at Palmarejo and, if material, may have a material adverse impact on the Company’s operations and financial results.
Palmarejo Gold Stream
Coeur Mexicana sells 50% of Palmarejo gold production (excluding production from certain properties acquired in 2015) to a subsidiary of Franco-Nevada Corporation (“Franco-Nevada”) under a gold stream agreement for the lesser of $800 or spot price per ounce. In 2016, Coeur Mexicana received a $22.0 million deposit toward future deliveries under the gold stream agreement. In accordance with generally accepted accounting principles, although Coeur Mexicana has satisfied its contractual obligation to repay the deposit to Franco-Nevada, the deposit is accounted for as deferred revenue and is recognized as revenue on a units-of-production basis as ounces are sold to Franco-Nevada. Because there is no minimum obligation associated with the deposit, it is not considered a financing, and each shipment is considered to be a separate performance obligation. The stream agreement represents a contract liability under ASC 606, which requires the Company to ratably recognize a portion of the deposit as revenue for each gold ounce delivered to Franco-Nevada. The remaining unamortized balance is included in Accrued liabilities and other and Other long-term liabilities on the Consolidated Balance Sheet.
The following table presents a roll forward of the Franco-Nevada contract liability balance:
Year Ended December 31,
In thousands202320222021
Opening Balance$7,411 $8,150 $9,376 
Revenue Recognized(469)(739)(1,226)
Closing Balance$6,942 $7,411 $8,150 
Metal Sales Prepayments
In June 2019, Coeur amended its existing sales and purchase contract with a metal sales counterparty for gold concentrate from its Kensington mine (the “Amended Sales Contract”). From time to time thereafter, the Amended Sales Contract has been further amended to allow for additional prepayments. In December 2022, the Company received a $25.0 million prepayment, all of which was recognized as revenue in the first half of 2023. In June 2023, the Company exercised an option to receive a further $25.0 million prepayment, all of which was recognized as revenue in the first half of 2023. In December 2023, the Company received a $25.0 million prepayment. Additionally, in June 2023, the Company entered into sales and purchase contracts with a metal sales counterparty to allow for a $10.0 million prepayment for deliveries of electrolytic cathodic sludge from its Wharf mine and a $10.0 million prepayment for deliveries of gold and silver doré from its Rochester mine, all of which were recognized as revenue in the third quarter of 2023. In September 2023, the contracts related to Wharf and Rochester were amended to increase the maximum amount available in prepayments to $12.5 million and $17.5 million, respectively, all of which were recognized as revenue in the fourth quarter of 2023. In December 2023, Wharf and Rochester received additional prepayments of $12.5 million and $17.5 million, respectively.
The metal sales prepayments represent a contract liability under ASC 606, which requires the Company to recognize ratably a portion of the deposit as revenue for each gold and silver ounce delivered to the customer. The remaining contract liability is included in Accrued liabilities and other on the Consolidated Balance Sheet. Under the relevant terms of the Amended Sales Contract, Coeur maintains its exposure to the price of gold and expects to recognize the remaining value of the accrued liability by December 2024.
The following table presents a roll forward of the prepayment contract liability balance:
Year Ended December 31,
In thousands202320222021
Opening Balance$25,016 $15,016 $15,003 
Additions130,066 36,020 30,013 
Revenue Recognized(100,000)(26,020)(30,000)
Closing Balance$55,082 $25,016 $15,016 
Kensington Royalty Matter
The Company’s subsidiary Coeur Alaska, Inc. (“Coeur Alaska”) is currently engaged in litigation with Maverix Metals Inc. and Maverix Metals (Nevada) Inc. (collectively “Maverix”) regarding the appropriate costs to be included in the cost recoupment calculation under a royalty deed before the royalty is payable on production from a portion of the Kensington mine
property (the “Maverix Litigation”). While the Company continues to believe in the validity of its claims and counterclaims in the matter, it has determined that settlement is appropriate given the inherent uncertainty presented in litigation matters. Accordingly, on February 15, 2024, Coeur Alaska and Maverix entered into a settlement agreement term sheet (“Settlement Term Sheet”) and the court granted their joint request to vacate the upcoming trial date and pretrial deadlines while the parties finalize definitive documentation of the settlement. Although the Settlement Term Sheet outlines key terms for dismissing the Maverix Litigation, definitive documentation has not yet been finalized. The Company believes that it is reasonably possible that the final terms of the settlement could result in a potential loss that the Company estimates to be between $1 million and $7 million.
Mining Concession
On November 20, 2023, Coeur Mexicana S.A. de C.V. signed a purchase agreement with a subsidiary of Fresnillo plc to acquire mining concessions adjacent to the Palmarejo mine. Total consideration includes a cash payment of approximately $25 million, with $10 million due at closing, an additional $10 million payable 12 months after closing, and an additional $5 million payable 24 months after closing. The concessions will be subject to an inflation-adjusted royalty payment of $25 per ounce for each new gold-equivalent ounce of resource discovered between 450,000 and two million gold equivalent ounces. Closing is subject to applicable regulatory approvals in Mexico.
Other Commitments and Contingencies
As part of its ongoing business and operations, the Company and its affiliates are required to provide surety bonds, bank letters of credit, bank guarantees and, in some cases, cash as financial support for various purposes, including environmental remediation, reclamation, collateral for gold and silver hedges and other general corporate purposes. As of December 31, 2023 and December 31, 2022, the Company had surety bonds totaling $324.8 million and $326.8 million, respectively, in place as financial support for future reclamation and closure costs. The obligations associated with these instruments are generally related to performance requirements that the Company addresses through its ongoing operations and, from time-to-time, the Company may be required to post collateral, including cash or letters of credit which reduce availability under its revolving credit facility, to support these instruments. As the specific requirements are met, the beneficiary of the associated instrument cancels and/or returns the instrument to the issuing entity. Certain of these instruments are associated with operating sites with long-lived assets and will remain outstanding until closure. The Company believes it is in compliance with all applicable bonding obligations and will be able to satisfy future bonding requirements through existing or alternative means, as they arise.