XML 35 R23.htm IDEA: XBRL DOCUMENT v3.22.2
Commitments and Contingencies
6 Months Ended
Jun. 30, 2022
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
Mexico Litigation Matters
As of June 30, 2022, $26.0 million in principal amount is due from the Mexican government associated with VAT that was paid under Coeur Mexicana, S.A. de C.V.’s (“Coeur Mexicana’s”) prior royalty agreement with a subsidiary of Franco-Nevada Corporation, which was terminated in 2016. Coeur Mexicana applied for and initially received VAT refunds associated with the royalty payments in the normal course; however, in 2011 the Mexican tax authorities began denying Coeur Mexicana’s VAT refunds based on the argument that VAT was not legally due on the royalty payments. Accordingly, Coeur Mexicana began to request refunds of the VAT as undue payments, which the Mexican tax authorities also denied. The Company has since been engaged in ongoing efforts to recover the VAT from the Mexican government (including through litigation and potential arbitration as well as refiling VAT refund requests). Despite a favorable ruling from Mexican tax courts in this matter in 2018, litigation has continued at the administrative, appeals court and supreme court levels, most of which has been determined unfavorably to Coeur based on interpretations of applicable law and prior court decisions which the Company and its counsel believe are contrary to legal precedent, conflicting and erroneous. While the Company believes that it remains legally entitled to be refunded the full amount of the VAT receivable and intends to rigorously continue its VAT recovery efforts, based on the continued failure to recover the VAT receivable and recent unfavorable Mexican court decisions, the Company determined to write down the carrying value of the VAT receivable at September 30, 2021. In March 2022, Coeur Mexicana filed an updated notice of intent to initiate an arbitration proceeding under Chapter 11 of the North American Free Trade Agreement, or NAFTA, in connection with this dispute and may elect to formally proceed with arbitration under NAFTA. Outcomes in NAFTA arbitration and the process for recovering funds even if there is a successful outcome in NAFTA arbitration can be lengthy and unpredictable.
In addition, ongoing litigation with the Mexican government associated with enforcement of water rights in Mexico, if unsuccessful, may impact Coeur Mexicana’s ability to access new sources of water to provide sufficient supply for its operations at Palmarejo and, if material, may have a material adverse impact on the Company’s operations and financial results.
Palmarejo Gold Stream
Coeur Mexicana sells 50% of Palmarejo gold production (excluding production from certain properties acquired in 2015) to a subsidiary of Franco-Nevada Corporation (“Franco-Nevada”) under a gold stream agreement for the lesser of $800 or spot price per ounce. In 2016, Coeur Mexicana received a $22.0 million deposit toward future deliveries under the gold stream agreement. In accordance with generally accepted accounting principles, although Coeur Mexicana has satisfied its contractual obligation to repay the deposit to Franco-Nevada, the deposit is accounted for as deferred revenue and is recognized as revenue on a units-of-production basis as ounces are sold to Franco-Nevada. At June 30, 2022 the remaining unamortized balance was $7.7 million, which is included in Accrued liabilities and other and Other long-term liabilities on the Consolidated Balance Sheet.
Kensington Prepayment
In June 2019, Coeur amended its existing sales and purchase contract with a metal sales counterparty for gold concentrate from its Kensington mine (the “Amended Sales Contract”). From time to time thereafter, the Amended Sales Contract has been further amended to allow for additional prepayments, including in June 2021, to provide options for Coeur to receive up to two additional prepayments of up to $15.0 million each. In June 2021 and December 2021, the Company exercised these options and received the $15.0 million June 2021 Prepayment and the $15.0 million December 2021 Prepayment. The June 2021 Prepayment was paid back in full before the December 2021 Prepayment was received. In March 2022, the Amended Sales Contract was further amended to allow for an additional $10.0 million prepayment. The additional $10.0 million prepayment was made in March 2022 (the “March 2022 Prepayment”). The Amended Sales Contract was further amended in June 2022 to consolidate the remaining deliveries of $15.0 million and $10.0 million under the December 2021 Prepayment and March 2022 Prepayment (the “June 2022 Consolidated Prepayment”), to extend the repayment period for the June 2022 Consolidated Prepayment, and to provide for future prepayments of up to $25.0 million on a semi-annual basis
through the end of 2024, provided all prior outstanding prepayment amounts are paid before such future prepayments are made. The remaining deliveries of the June 2022 Consolidated Prepayment are recognized as a deferred revenue liability and are presented in Accrued liabilities and other on the Consolidated Balance Sheet. Under the relevant terms of the Amended Sales Contract, Coeur maintains its exposure to the price of gold and expects to recognize the remaining value of the accrued liability by December 2022.
POA 11 Expansion Project
As of June 30, 2022, the total estimated project capital cost remained approximately $600 million. With the commencement of structural, mechanical, piping, electrical and instrumentation construction work, completion of final major high-voltage electrical contracts and initial commitments for the pre-screen addition to the expanded crusher circuit, the Company has committed approximately $523 million and incurred $350 million of the total estimated project cost through June 30, 2022.
The expansion consists of three major components: (i) a new 300-million-ton leach pad, for which civil work is essentially complete and piping work is near completion; (ii) a Merrill-Crowe process plant with construction completion scheduled for the first half of 2023; and (iii) a new three-stage crushing circuit with construction completion scheduled for mid-2023. These scheduled construction completion dates for the project remain unchanged.
Construction of the Merrill-Crowe process plant ramped up during the second quarter, including completion of concrete work, continuation of equipment setting, and the commencement of building and process plant steel pipe rack erection, as well as piping and cable tray installation.
Work on the crusher corridor included (i) continued civil construction in the primary crusher area, (ii) the completion of concrete work, start of steel construction, and setting of conveyor and equipment in the secondary crusher area, (iii) continued advancement of concrete work and start of steel erection in the secondary stock pile reclaim area, (iv) completion of concrete in the tertiary crusher area, and (v) continuation of concrete in the tertiary reclaim and final product load-out areas. Deliveries of equipment and materials for the project continue to support the overall construction schedule.
The Company also recently advanced detailed engineering on the pre-screens. Equipment procurement and construction contract development is well underway as Coeur continues working to align construction of the pre-screens with the completion of the new crusher. Final cost estimates related to pre-screens are expected in the third quarter.
The Company began installation of pre-screens on the existing crusher corridor on June 23 and commenced commissioning on July 22. Ramp-up of the pilot system as well as optimization of the product size placed under leach is scheduled to take place during the month of August. The experience and knowledge gained from utilizing pre-screens is expected to facilitate the integration of pre-screen technology into the new crusher system flowsheet for POA 11.
Other Commitments and Contingencies
As part of its ongoing business and operations, the Company and its affiliates are required to provide surety bonds, bank letters of credit, bank guarantees and, in some cases, cash as financial support for various purposes, including environmental remediation, reclamation, collateral for gold hedges and other general corporate purposes. As of June 30, 2022 and December 31, 2021, the Company had surety bonds totaling $315.0 million and $315.1 million, respectively, in place as financial support for future reclamation and closure costs. The obligations associated with these instruments are generally related to performance requirements that the Company addresses through its ongoing operations and from time-to-time, the Company may be required to post collateral, including cash or letters of credit which reduce availability under its revolving credit facility, to support these instruments. As the specific requirements are met, the beneficiary of the associated instrument cancels and/or returns the instrument to the issuing entity. Certain of these instruments are associated with operating sites with long-lived assets and will remain outstanding until closure. The Company believes it is in compliance with all applicable bonding obligations and will be able to satisfy future bonding requirements through existing or alternative means, as they arise.