XML 144 R28.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Rates and Other Regulatory Activities
12 Months Ended
Dec. 31, 2019
Text Block [Abstract]  
Rates and Other Regulatory Activities RATES AND OTHER REGULATORY ACTIVITIES

Our natural gas and electric distribution operations in Delaware, Maryland and Florida are subject to regulation by their respective PSC; Eastern Shore, our natural gas transmission subsidiary, is subject to regulation by the FERC; and Peninsula Pipeline, our intrastate pipeline subsidiary, is subject to regulation (excluding cost of service) by the Florida PSC.
Delaware
Effect of the TCJA on Customers: In January 2019, the Delaware PSC approved the as-filed Delaware Division Delivery Service Rates reflecting the impact of the TCJA.  The new rates went into effect in March 2019. The refunds, which were retroactive to February 2018, were completed prior to the mandated deadline of June 2019.  The order also provided for a line item billing credit that went into effect in April 2019, for the return of the excess accumulated deferred income taxes ("ADIT"). 
CGS: In August 2019, we filed with the Delaware PSC an application seeking an order that will establish the regulatory accounting treatment and valuation methodology for the acquisition of propane CGS owned by our affiliate, Sharp, and the conversion of the CGS to natural gas service. We propose to acquire each CGS one at a time and to pay replacement cost for each CGS system. In addition, we are requesting authorization to pay for and capitalize the CGS residents’ behind-the-meter conversion costs. Our existing natural gas customers will be protected against subsidizing the acquisitions and conversions of the CGS systems because we will complete only those systems that meet our economic test. In September 2019, the Delaware PSC issued an order to open a docket for the purpose of reviewing our application and to conduct evidentiary hearings on the matter. We are currently responding to discovery requests and an evidentiary hearing is scheduled for the second quarter of 2020.
Maryland
Approval of the Elkton Gas Company Acquisition: In December 2019, we entered into an agreement with SJI to acquire its subsidiary, Elkton Gas Company, which provides natural gas distribution service to approximately 7,000 residential and commercial customers within a franchised area of Cecil County, Maryland. Upon completion of the transaction, Elkton Gas Company will become our wholly-owned subsidiary. The acquisition, which is expected to close in the second half of 2020, is subject to approval by the Maryland PSC. Elkton Gas Company's territory is contiguous to our franchised service territory in Cecil County, Maryland and it will continue to operate out of its existing office with the same local personnel.

Florida
Electric Limited Proceeding-Storm Recovery (Pre-Hurricane Michael): In February 2018, FPU filed a petition with the Florida PSC, requesting recovery of incremental storm restoration costs related to several hurricanes and tropical storms, along with the replenishment of the storm reserve to its pre-storm level of $1.5 million. As a result of these hurricanes and tropical storms, FPU’s storm reserve was depleted and, at the time of filing the petition, had a deficit of $0.8 million. This matter went to hearing in December 2018 and was subsequently approved at the March 2019 Agenda with the Final Order issued on March 25, 2019. FPU received approval to begin a surcharge on customer bills for two years beginning in April 2019, to recover storm-related costs and replenish the storm reserve.
Hurricane Michael: In October 2018, Hurricane Michael passed through FPU's electric distribution operation's service territory in Northwest Florida. The hurricane caused widespread and severe damage to FPU's infrastructure resulting in the loss of electric service to 100 percent of its customers in the Northwest Florida service territory. FPU, after exerting extraordinary hurricane restoration efforts, restored service to those customers who were able to accept it. FPU expended more than $65.0 million to restore service, which was recorded as new plant and equipment, charged against FPU’s accumulated depreciation or charged against FPU’s storm reserve. Additionally, amounts currently being reviewed by the Florida PSC for regulatory asset treatment have been recorded as receivables and other deferred charges. In December 2018 and January 2019, we executed two 13-month unsecured term loans as temporary financing for the Hurricane Michael-related expenditures, each in the amount of $30.0 million. The interest cost associated with these loans is the one-month LIBOR rate plus 75 basis points. In December 2019, we utilized the proceeds from the issuance of uncollateralized senior notes to repay the term notes issued in December 2018.
In August 2019, FPU filed a limited proceeding requesting recovery of storm-related costs associated with Hurricane Michael (capital and expenses) through a change in base rates. FPU also requested treatment and recovery of certain storm-related costs as regulatory assets for items currently not allowed to be recovered through the storm reserve as well as the recovery of capital replaced as a result of the storm. Recovery of these costs includes a component of an overall return on capital additions and regulatory assets. In the fourth quarter of 2019, FPU along with the Office of Public Counsel in Florida, filed a joint motion with the Florida PSC to approve an interim rate increase, subject to refund, pending the final ruling on the recovery of the restoration costs incurred. The petition was approved by the Florida PSC in November 2019 and temporary rate increases were implemented effective January 2020. FPU continues to work with the Florida PSC and expects to reach a final ruling in the second half of 2020.
Effect of the TCJA on Customers: In February 2018, the Florida PSC opened dockets to consider the impacts associated with the TCJA. In May 2018, FPU’s natural gas divisions filed petitions and supporting testimony regarding the disposition of the related impacts of the TCJA. Hearings on this matter took place in November 2018, and the staff's recommendation was approved by the Florida PSC at the February 2019 Agenda and final orders were issued on February 25, 2019. Staff’s recommendations are summarized in the table at the end of this section.
Electric Depreciation Study: In September 2019, FPU filed a petition, with the Florida PSC, for approval of its consolidated electric depreciation rates. The new rates will be effective January 1, 2020. The petition has not been scheduled for approval by the Florida PSC.
Natural Gas Depreciation Study: In March 2019, FPU filed a petition, with the Florida PSC, for approval of its consolidated natural gas depreciation rates. The petition was approved by the Florida PSC at Agenda on October 3, 2019. The new rates were effective retroactive to January 1, 2019, and are expected to decrease depreciation expense by approximately $0.9 million annually.
Auburndale Project: In June 2019, Peninsula Pipeline filed with the Florida PSC for approval of its Transportation Service Agreement with the Florida Division of Chesapeake Utilities. Peninsula Pipeline will purchase an existing pipeline owned by the Florida Division of Chesapeake Utilities and Calpine and construct pipeline facilities in Polk County, Florida. Peninsula Pipeline will provide transportation service to the Florida Division of Chesapeake Utilities increasing both delivery capacity and downstream pressure as well as introducing a secondary source of natural gas for the Florida Division of Chesapeake Utilities' distribution system. The petition was approved by the Florida PSC at the August 6, 2019 Agenda. The project was placed in service in the third quarter of 2019.
Palm Beach Expansion Project: In June 2019, Peninsula Pipeline filed with the Florida PSC for approval of its Transportation Service Agreement with FPU. Peninsula Pipeline will construct several new interconnection points and pipeline expansions in Palm Beach County, Florida, which will enable FPU to serve an industrial research park and several new residential developments. Peninsula Pipeline will provide transportation service to FPU, increasing reliability, system pressure as well as introducing diversity in fuel source for natural gas to serve the increased demand in these areas. The petition was approved by the Florida PSC at the August 6, 2019 Agenda. Interim services began in the fourth quarter of 2019.
Callahan Pipeline Project, Nassau County: In July 2019, Peninsula Pipeline filed a petition for approval of the firm transportation service agreement with FPU and the restructuring of the business and operational agreements between Peoples Gas, FPU and Seacoast Gas Transmission. Peninsula Pipeline will construct and jointly own 26 miles of 16 inch steel pipeline with Seacoast Gas Transmission and interconnect to the Cypress Pipeline interstate system in western Nassau County. The Callahan pipeline will terminate into the existing Peninsula Pipeline-Peoples Gas jointly owned pipeline, which serves Amelia Island and the Peoples Gas distribution system. Callahan pipeline will enhance FPU’s ability to expand service into Nassau County and will enable Peoples Gas to enhance its system pressure and reliability of its service in Duval County. This petition was approved by the Florida PSC at the December 10, 2019 Agenda. The project is expected to be placed in-service during the third quarter of 2020.
Eastern Shore
Del-Mar Energy Pathway Project: In December 2019, the FERC issued an order approving the construction of the Del-Mar Energy Pathway project. The order, which was applied for in September 2018 by Eastern Shore, approved the construction and operation of new facilities that will provide an additional 14,300 Dts/d of firm service to four customers. Facilities to be constructed include six miles of pipeline looping in Delaware; 13 miles of new mainline extension in Sussex County, Delaware and Wicomico and Somerset counties in Maryland; and new pressure control and delivery stations in these counties. The benefits of this project include: (i) additional natural gas transmission pipeline infrastructure in eastern Sussex County, Delaware, and (ii) extension of Eastern Shore’s pipeline system, for the first time, into Somerset County, Maryland. Eastern Shore anticipates that this project will be fully in-service by the beginning of the fourth quarter of 2021.
Renewable Natural Gas Tariff: In October 2019, Eastern Shore filed an application with the FERC to include renewable natural gas (biogas) utilization and standards in its tariff. Eastern Shore had proposed changes to its gas quality specifications that would enable it to accommodate renewable natural gas at various receipt points on its system. Changes to the gas quality specifications would ensure interchangeability of renewable natural gas with the natural gas currently delivered to Eastern Shore. The tariffs became effective November 2019 after the end of 30 days of no opposing comments.

Summary TCJA Table
 
 
Regulatory Liabilities related to ADIT
 
 
Operation and Regulatory Jurisdiction
 
Amount (in thousands)
Status
 
Status of Customer Rate impact related to lower federal corporate income tax rate
Eastern Shore (FERC)
 
$34,190
Will be addressed in Eastern Shore's next rate case filing.
 
Implemented one-time bill credit (totaling $0.9 million) in April 2018. Customer rates were adjusted in April 2018.
Delaware Division (Delaware PSC)
 
$12,847
PSC approved amortization of ADIT in January 2019.
 
Implemented one-time bill credit (totaling $1.5 million) in April 2019. Customer rates were adjusted in March 2019.
Maryland Division (Maryland PSC)
 
$4,087
PSC approved amortization of ADIT in May 2018.
 
Implemented one-time bill credit (totaling $0.4 million) in July 2018. Customer rates were adjusted in May 2018.
Sandpiper Energy (Maryland PSC)
 
$3,765
PSC approved amortization of ADIT in May 2018.
 
Implemented one-time bill credit (totaling $0.6 million) in July 2018. Customer rates were adjusted in May 2018.
Chesapeake Florida Gas Division/Central Florida Gas (Florida PSC)
 
$8,304
PSC issued order authorizing amortization and retention of net ADIT liability by the Company in February 2019.
 
Florida PSC's final order was issued in February 2019. Excluding GRIP, tax savings arising from the TCJA rate reduction will be retained by the Company.

GRIP: Tax savings for 2018 will be refunded to customers in 2020 through the annual GRIP cost recovery mechanism. Future customer GRIP surcharges will be adjusted to reflect tax savings associated with TCJA.
FPU Natural Gas (excludes Fort Meade and Indiantown) (Florida PSC)
 
$19,218
Same treatment on a net basis as Chesapeake Florida Gas Division (above).
 
Same treatment on a net basis as Chesapeake Florida Gas Division (above).
FPU Fort Meade and Indiantown Divisions
 
$294
Same treatment on a net basis as Chesapeake Florida Gas Division (above).
 
Tax rate reduction: The impact was immaterial for the divisions.

GRIP (Applicable to Fort Meade division only): Same treatment as Chesapeake Florida Gas Division (above).
FPU Electric (Florida PSC)
 
$5,769
In January 2019, PSC issued order approving amortization of ADIT through purchased power cost recovery, storm reserve and rates.
 
TCJA benefit will flow back to its customers through a combination of reductions to the fuel cost recovery rate, base rates, as well as application to the storm reserve over the next several years.


Regulatory Assets and Liabilities
At December 31, 2019 and 2018, our regulated utility operations had recorded the following regulatory assets and liabilities included in our consolidated balance sheets. These assets and liabilities will be recognized as revenues and expenses in future periods as they are reflected in customers’ rates.
 
As of December 31,
 
2019
 
2018
(in thousands)
 
 
 
Regulatory Assets
 
 
 
Under-recovered purchased fuel and conservation cost recovery (1)
$
5,144

 
$
4,631

Under-recovered GRIP revenue (2)

 
165

Deferred postretirement benefits (3)
16,311

 
15,517

Deferred conversion and development costs (1)
20,881

 
16,727

Environmental regulatory assets and expenditures (4)
2,241

 
2,731

Acquisition adjustment (5)
30,329

 
33,255

Loss on reacquired debt (6)
869

 
942

Other
2,776

 
3,250

Total Regulatory Assets
$
78,551

 
$
77,218

 
 
 
 
 
 
 
 
Regulatory Liabilities
 
 
 
Self-insurance (7)
$
873

 
$
947

Over-recovered purchased fuel and conservation cost recovery (1)
2,724

 
5,856

Over-recovered GRIP revenue (2)
2,668

 
1,563

Storm reserve (7)
1,437

 
677

Accrued asset removal cost (8)
36,767

 
42,401

Deferred income taxes due to rate change (9)
89,191

 
91,236

Other
75

 
242

Total Regulatory Liabilities
$
133,735

 
$
142,922

 
 
 
 
(1) We are allowed to recover the asset or are required to pay the liability in rates. We do not earn an overall rate of return on these assets.
(2) The Florida PSC allowed us to recover through a surcharge, capital and other program-related-costs, inclusive of an appropriate return on investment, associated with accelerating the replacement of qualifying distribution mains and services (defined as any material other than coated steel or plastic) in FPU’s natural gas distribution, Fort Meade division and Chesapeake Utilities’ Central Florida Gas division. We are allowed to recover the asset or are required to pay the liability in rates related to GRIP.
(3) The Florida PSC allowed FPU to treat as a regulatory asset the portion of the unrecognized costs pursuant to ASC Topic 715, Compensation - Retirement Benefits, related to its regulated operations. In 2019, we recorded as a regulatory asset the portion of pension settlement expense associated with the de-risking of the Chesapeake Pension Plan pursuant to an order from the FERC that allowed us to defer Eastern Shore's portion. See Note 17, Employee Benefit Plans, for additional information.
(4) All of our environmental expenditures incurred to date and our current estimate of future environmental expenditures have been approved by various PSCs for recovery. See Note 20, Environmental Commitments and Contingencies, for additional information on our environmental contingencies.
(5) We are allowed to include the premiums paid in various natural gas utility acquisitions in Florida in our rate bases and recover them over a specific time period pursuant to the Florida PSC approvals. We paid $34.2 million of the premium in 2009, including a gross up for income tax, because it is not tax deductible, and $0.7 million of the premium paid by FPU in 2010.
(6) Gains and losses resulting from the reacquisition of long-term debt are amortized over future periods as adjustments to interest expense in accordance with established regulatory practice.
(7) We have self-insurance and storm reserves in our Florida regulated energy operations that allow us to collect through rates amounts to be used against general claims, storm restoration costs and other losses as they are incurred.
(8) See Note 1, Summary of Significant Accounting Policies, for additional information on our asset removal cost policies.
(9) We recorded a regulatory liability for our regulated businesses related to the revaluation of accumulated deferred tax assets/liabilities as a result of the TCJA. Based upon the regulatory proceedings, we will pass back the respective portion of the excess accumulated deferred taxes to rate payers. See Note 12, Income Taxes, for additional information.