Environmental Remedies [Table Text Block]
Jurisdiction
MGP Site
Status
Cost to Clean up
Recovery through Rates
Florida
West Palm Beach
Remedial actions approved by the FDEP have been implemented on the east parcel of the site. We expect to implement similar remedial actions on other remaining portions, including the anticipated demolition of buildings on the site's west parcel in 2018.
Between $4.5 million to $15.4 million, including costs associated with the relocation of FPU’s operations at this site, which is necessary to implement the remedial plan, and any potential costs associated with future redevelopment of the properties.
Yes
Florida
Sanford
In March 2018, the EPA approved a "site-wide ready for anticipated use" status, which is the final step before delisting a site. Construction has been completed and restrictive covenants are in place to ensure protection of human health. The only remaining activity is long-term groundwater monitoring. It is unlikely that FPU will incur any significant future costs associated with the site.
FPU's remaining remediation expenses, including attorneys' fees and costs, are anticipated to be less than $10,000.
Yes
Florida
Winter Haven
Remediation is ongoing.
Not expected to exceed $425,000, which includes costs of implementing institutional controls at the site.
Yes
Delaware
Seaford
Proposed plan for implementation approved by the DNREC in July 2017. Site assessment is ongoing.
Between $273,000 and $465,000.
Yes
Maryland
Cambridge
Currently in discussions with the MDE.
Unable to estimate.
N/A