XML 47 R35.htm IDEA: XBRL DOCUMENT v3.7.0.1
Rates and Other Regulatory Activities - Additional Information (Detail)
$ in Thousands
3 Months Ended 6 Months Ended
Jun. 30, 2017
USD ($)
dekatherm / d
unit
mi
Jun. 30, 2016
USD ($)
Jun. 30, 2017
USD ($)
dekatherm / d
unit
customer
in
mi
Jun. 30, 2016
USD ($)
Rates and Other Regulatory Activities [Line Items]        
Revenues $ 125,084 $ 102,342 $ 310,244 $ 248,638
Federal Energy Regulatory Commission Comment Period     30 days  
Number Of Federal and State Bodies To Submit Comments | unit     4  
Number of Private Parties To Submit Comments | unit     2  
DELAWARE        
Rates and Other Regulatory Activities [Line Items]        
Public Utilities, Approved Rate Increase (Decrease), Amount $ 2,250      
Electric Distribution [Member]        
Rates and Other Regulatory Activities [Line Items]        
Estimated Capital Cost     $ 59,800  
Number of Years in Project     5 years  
Eastern Shore [Member]        
Rates and Other Regulatory Activities [Line Items]        
Number Of Intervening Parties     14  
Cost of Services     $ 60,000  
Public Utilities, Requested Rate Increase (Decrease), Amount     $ 18,900  
Public Utilities, Requested Return on Equity, Percentage     13.75%  
Parties Filing Protest     6  
Number of Months Rates Suspended     5 months  
White Oak Lateral Mainline Expansion [Member] | Eastern Shore [Member]        
Rates and Other Regulatory Activities [Line Items]        
Estimated Capital Cost     $ 41,000  
Volume The Expansion Project Is Expected to Provide | dekatherm / d     45,000  
Number of pipeline miles requested | mi 7.2   7.2  
Lateral diamater of pipeline to be installed | in     16  
Revised Miles Of Natural Gas Pipeline | mi 5.4   5.4  
System Reliability Project [Member] | Eastern Shore [Member]        
Rates and Other Regulatory Activities [Line Items]        
Estimated Capital Cost     $ 38,000  
Number of pipeline miles requested | mi 10.1   10.1  
Lateral diamater of pipeline to be installed | in     16  
Number Of Environmental Conditions | unit 22   22  
2017 Expansion Project [Member] | Eastern Shore [Member]        
Rates and Other Regulatory Activities [Line Items]        
Estimated Capital Cost     $ 98,600  
Number of pipeline miles requested | mi 23   23  
Revised Miles Of Natural Gas Pipeline | mi 17   17  
Pressure Control Stations     2  
Firm natural gas transportation deliverability | dekatherm / d 61,162      
Additional Firm Natural Gas Transportation Deliverability | dekatherm / d     52,500  
Subscribers [Member] | 2017 Expansion Project [Member] | Eastern Shore [Member]        
Rates and Other Regulatory Activities [Line Items]        
Number of Customers intervened | customer     6  
Number of customers     7  
Number of affiliates | unit     3