Rates and Other Regulatory Activities
9 Months Ended
Sep. 30, 2016
Regulated Operations [Abstract]  
Rates and Other Regulatory Activities
Rates and Other Regulatory Activities
Our natural gas and electric distribution operations in Delaware, Maryland and Florida are subject to regulation by their respective PSC; Eastern Shore, our natural gas transmission subsidiary, is subject to regulation by the FERC; and Peninsula Pipeline, our intrastate pipeline subsidiary, is subject to regulation by the Florida PSC. Chesapeake Utilities' Florida natural gas distribution division and FPU’s natural gas and electric distribution operations continue to be subject to regulation by the Florida PSC as separate entities.
Delaware
Rate Case Filing: On December 21, 2015, our Delaware Division filed an application with the Delaware PSC for a base rate increase and certain other changes to its tariff. We proposed an increase of approximately $4.7 million, or nearly ten percent, in our revenue requirement based on the test period ending March 31, 2016. We also proposed new service offerings to promote growth and a revenue normalization mechanism for residential and small commercial customers. We expect a decision on the application during the first quarter of 2017. Pending the decision, our Delaware Division increased rates on an interim basis based on the $2.5 million annualized interim rates approved by the Delaware PSC, effective February 19, 2016 ("Phase I"). We recognized incremental revenue of approximately $469,000 ($280,000 net of tax) and $1.4 million ($817,000 net of tax) for the three and nine months ended September 30, 2016, respectively.
In addition, our Delaware Division requested and received approval on July 26, 2016, from the Delaware PSC to implement revised interim rates totaling $4.7 million (equal to the initial rate increase in our application) annualized for usage on and after August 1, 2016 ("Phase II"). These revised interim rates represent a five-percent increase over Phase I rates. Revenue associated with these rates collected prior to a final Delaware PSC decision is subject to refund and, although the final decision is expected during the first quarter of 2017, we cannot predict the revenue requirement the Delaware PSC will ultimately authorize or forecast the timing of a final decision. Consequently, we will not recognize the impact of the potential additional revenue related to the Phase II rate increase until the Delaware PSC issues its approval in a final ruling.
Maryland
Sandpiper Rate Case Filing: On December 1, 2015, Sandpiper filed an application with the Maryland PSC for a base rate increase and certain other changes to its tariff. We proposed an increase of $950,000, or approximately five- percent, in our revenue requirement, based on the test period ended December 31, 2015. We also proposed a stratification of rate classes, based on cost of service, and a revenue normalization mechanism for residential and small commercial customers. The procedural schedule was suspended in early May 2016 to allow for the continuation of settlement discussions between Sandpiper, Maryland PSC Staff and the Maryland Office of People's Counsel. The parties reached a settlement agreement, which Sandpiper filed with the Commission on August 10, 2016. The terms of the agreement include revenue neutral rates for the first year, followed by a schedule of rate reductions in subsequent years based upon the projected rate of propane to natural gas conversions. A revenue normalization mechanism and stratification of rate classes were also included in the settlement agreement. On September 28, 2016, the Public Utility Law Judge issued a proposed order recommending approval of the settlement terms. The order became final on October 29, 2016 and the new rates will be in effect on December 1, 2016.
Florida
On September 1, 2015, FPU’s electric division filed to recover the cost of the proposed Florida Power & Light Company interconnect project through FPU's annual Fuel and Purchased Power Cost Recovery Clause filing. The interconnect project will enable FPU's electric division to negotiate a new power purchase agreement that will mitigate fuel costs for its Northeast division. This action was approved by the Florida PSC at its Agenda Conference held on December 3, 2015. On January 22, 2016, the Office of Public Counsel filed an appeal of the Florida PSC's decision with the Florida Supreme Court. Legal briefs have been filed, but no decision has been reached at this time.

On February 2, 2016, FPU’s natural gas division filed a petition with the Florida PSC for approval of an amendment to its existing transportation agreement with the City of Lake Worth, located in Palm Beach County, Florida. The amendment allows the city to resell natural gas distributed by FPU to the city’s compressed natural gas station. The city will then resell the natural gas, after compression, to its customers. The amendment to the transportation agreement was approved by the Florida PSC at its Agenda Conference held April 5, 2016.

On April 11, 2016, FPU’s natural gas divisions and Chesapeake Utilities' Florida division filed a joint petition for approval to allow FPU and Chesapeake Utilities to expand the cost allocation of the intrastate and unreleased capacity-related components currently embedded in the purchased gas adjustment and operational balancing account, which is currently allocated to a limited number of customers. The expanded allocation of these costs includes additional customers, primarily transportation customers, benefiting from these costs but not currently paying for them. This petition was approved by the Florida PSC at its Agenda Conference in September 2016.

Eastern Shore
White Oak Mainline Expansion Project: On November 21, 2014, Eastern Shore submitted an application to the FERCseeking authorization to construct, own and operate certain expansion facilities designed to provide 45,000 Dts/d of firm transportation service to an electric power generator in Kent County, Delaware. Eastern Shore proposes to construct approximately 7.2 miles of 16-inch diameter pipeline looping in Chester County, Pennsylvania and 3,550 horsepower of additional compression at Eastern Shore’s existing Delaware City compressor station in New Castle County, Delaware.

On November 18, 2015, Eastern Shore filed an amendment to this application, which indicated the preferred pipeline route and shortened the total miles of the proposed pipeline to 5.4 miles. On February 10, 2016, the FERC issued a notice combining the White Oak Mainline Expansion Project and the System Reliability Project into a single environmental assessment.


On July 21, 2016, the FERC issued a certificate of public convenience and necessity authorizing Eastern Shore to construct and operate the proposed White Oak Mainline Project. The FERC denied Eastern Shore’s request for a pre-determination of rolled-in rate treatment in the certificate proceeding. However, FERC’s determination is without prejudice to Eastern Shore filing for and fully supporting rolled-in rate treatment of these project facilities in a future general rate case. The certificate required Eastern Shore to comply with 19 environmental conditions.

On July 29, 2016, Eastern Shore accepted the certificate of public convenience and necessity and, on August 2, 2016, filed its Implementation Plan to comply with each environmental condition and to request approval to begin construction. On August 4, 2016, the FERC issued a “Notice to Proceed,” and Eastern Shore commenced construction during August 2016. Eastern Shore continues to file weekly status reports in compliance with one of the environmental conditions.
System Reliability Project: On May 22, 2015, Eastern Shore submitted an application to the FERC seeking authorization to construct, own and operate approximately 10.1 miles of 16-inch pipeline looping and auxiliary facilities in New Castle and Kent Counties, Delaware and a new compressor at its existing Bridgeville compressor station in Sussex County, Delaware. Eastern Shore further proposed to reinforce critical points on its pipeline system. The total project will benefit all of Eastern Shore’s customers by modifying the pipeline system to respond to severe operational conditions experienced during actual winter peak days in 2014 and 2015. Since the project is intended to improve system reliability, Eastern Shore requested a predetermination of rolled-in rate treatment for the costs of the project.
On July 21, 2016, the FERC issued a certificate of public convenience and necessity authorizing Eastern Shore to construct and operate the proposed System Reliability Project. The FERC granted Eastern Shore’s request for a pre-determination of rolled-in rate treatment in its next rate base proceeding and required Eastern Shore to comply with 19 environmental conditions.

On July 29, 2016, Eastern Shore accepted the certificate and on August 5, 2016 filed its Implementation Plan to comply with each environmental condition and to request approval to begin construction. On August 12, 2016, the FERC issued a “Partial Notice to Proceed” approving construction for certain portions of the System Reliability Project. On September 15, 2016, the FERC granted approval to start construction on the remaining portion of the Project. Construction commenced on the Bridgeville Compressor Station and the Porter Road Loop in August 2016, and on the Dover Loop, in September 2016 and is ongoing. Eastern Shore continues to file weekly status reports in compliance with one of the environmental conditions.
TETLP Capacity Expansion Project: On October 13, 2015, Eastern Shore submitted an application to the FERC to make certain measurement and related improvements at its TETLP interconnect facilities, which would enable Eastern Shore to increase natural gas receipts from TETLP by 53,000 Dts/d, for a total capacity of 160,000 Dts/d. On December 22, 2015, the FERC authorized Eastern Shore to proceed with the project. On March 11, 2016, the capacity expansion project was placed into service.
2017 Expansion Project: On May 12, 2016, Eastern Shore submitted a request to the FERC to initiate the FERC’s pre-filing review procedures for Eastern Shore's 2017 expansion project. The expansion project consists of approximately 33 miles of pipeline looping in Pennsylvania, Maryland and Delaware; upgrades to existing metering facilities in Lancaster County, Pennsylvania; installation of an additional 3,550 horsepower compressor unit at Eastern Shore’s existing Daleville compressor station in Chester County, Pennsylvania; and approximately 17 miles of new mainline extension and two pressure control stations in Sussex County, Delaware. The expansion project is necessary to provide up to 86,437 Dts/d of additional firm natural gas transportation capacity to meet anticipated market demand. On May 17, 2016, the FERC approved Eastern Shore’s request to commence the pre-filing review process. Eastern Shore is currently working through the pre-filing process and anticipates filing, in December 2016, its application for a certificate of public convenience and necessity, seeking authorization to construct the expansion facilities.
Since the time the pre-filing was initiated, Eastern Shore has finalized market participation for the project. Seven of Eastern Shore’s existing customers have signed Precedent Agreements. As a result, the project will provide 61,162 Dts/d of additional firm natural gas transportation deliverability on Eastern Shore’s pipeline system. To provide this additional capacity, the project’s final facilities will consist of approximately 23 miles of pipeline looping in Pennsylvania, Maryland and Delaware; upgrades to existing metering facilities in Lancaster County, Pennsylvania; installation of an additional 3,550 horsepower compressor unit at Eastern Shore’s existing Daleville compressor station in Chester County, Pennsylvania; and approximately 17 miles of new mainline extension and two pressure control stations in Sussex County, Delaware.
2017 Rate Case Filing
In January 2017, Eastern Shore intends to file a base rate proceeding with the FERC, as required by the terms of its 2012 settlement agreement.