XML 25 R13.htm IDEA: XBRL DOCUMENT v3.5.0.2
Rates and Other Regulatory Activities
6 Months Ended
Jun. 30, 2016
Regulated Operations [Abstract]  
Rates and Other Regulatory Activities
Rates and Other Regulatory Activities
Our natural gas and electric distribution operations in Delaware, Maryland and Florida are subject to regulation by their respective PSC; Eastern Shore, our natural gas transmission subsidiary, is subject to regulation by the FERC; and Peninsula Pipeline, our intrastate pipeline subsidiary, is subject to regulation by the Florida PSC. Chesapeake Utilities' Florida natural gas distribution division and FPU’s natural gas and electric distribution operations continue to be subject to regulation by the Florida PSC as separate entities.
Delaware
Rate Case Filing: On December 21, 2015, our Delaware division filed an application with the Delaware PSC for a base rate increase and certain other changes to its tariff. We proposed an increase of approximately $4.7 million, or nearly ten percent, in our revenue requirement based on the test period ending March 31, 2016. We also proposed new service offerings to promote growth and a revenue normalization mechanism for residential and small commercial customers. We expect a decision on the application during the first quarter of 2017. Pending the decision, our Delaware division increased rates on an interim basis based on the $2.5 million annualized interim rates approved by the Delaware PSC, effective February 19, 2016. We recognized incremental revenue of approximately $555,000 ($332,000 net of tax) and $878,000 ($526,000 net of tax) for the three and six months ended June 30, 2016, respectively. In addition, our Delaware division requested and received approval on July 26, 2016 from the Delaware PSC to implement revised interim rates of $4.7 million annualized for usage on and after August 1, 2016. Revenue collected prior to a final Delaware PSC decision is subject to refund. Although the final decision is expected during the first quarter of 2017, we cannot predict the revenue requirement the Delaware PSC will ultimately authorize or forecast the timing of a final decision. These rates, which are subject to refund, represent a five percent increase over current rates.
 
Maryland
Sandpiper Rate Case Filing: On December 1, 2015, Sandpiper filed an application with the Maryland PSC for a base rate increase and certain other changes to its tariff. We proposed an increase of $950,000, or approximately five percent, in our revenue requirement, based on the test period ended December 31, 2015. We also proposed a stratification of rate classes, based on cost of service, and a revenue normalization mechanism for residential and small commercial customers. The procedural schedule was suspended in early May 2016 to allow for the continuation of settlement discussions between Sandpiper, Maryland PSC Staff and Maryland Office of People's Counsel. We expect a decision on the application during the third quarter of 2016.
Florida
On September 1, 2015, FPU’s electric division filed to recover the cost of the proposed Florida Power & Light Company interconnect project through FPU's annual Fuel and Purchased Power Cost Recovery Clause filing. The interconnect project will enable FPU's electric division to negotiate a new power purchase agreement that will mitigate fuel costs for its Northeast division. This action was approved by the Florida PSC at its Agenda Conference held on December 3, 2015. On January 22, 2016, the Office of Public Counsel filed an appeal of the Florida PSC's decision with the Florida Supreme Court. Legal briefs have been filed, but no decision has been reached at this time.

On February 2, 2016, FPU’s natural gas division filed a petition with the Florida PSC for approval of an amendment to its existing transportation agreement with the City of Lake Worth, located in Palm Beach County, Florida. The amendment allows the city to resell natural gas distributed by FPU to the city’s compressed natural gas station. The city will then resell the natural gas, after compression, to its customers. The amendment to the transportation agreement was approved by the Florida PSC at its Agenda Conference held April 5, 2016.

On April 11, 2016, FPU’s natural gas divisions and Chesapeake Utilities' Florida division filed a joint petition for approval to allow FPU and Chesapeake Utilities to expand the cost allocation of the intrastate and unreleased capacity-related components currently embedded in the purchased gas adjustment and operational balancing account, which is currently allocated to a limited number of customers. The proposed new allocation of these costs would include additional customers, primarily transportation customers, benefiting from these costs but not currently paying for them. We expect the petition to be approved by the Florida PSC in late 2016.

Eastern Shore
White Oak Mainline Expansion Project: On November 21, 2014, Eastern Shore submitted an application to the FERC seeking authorization to construct, own and operate certain expansion facilities designed to provide 45,000 Dts/d of firm transportation service to an electric power generator in Kent County, Delaware. Eastern Shore proposes to construct approximately 7.2 miles of 16-inch diameter pipeline looping in Chester County, Pennsylvania and 3,550 horsepower of additional compression at Eastern Shore’s existing Delaware City compressor station in New Castle County, Delaware.
On January 22, 2015, the FERC issued a notice of intent to prepare an environmental assessment for this project. In February, April and May 2015, Eastern Shore filed environmental data in response to comments regarding the evaluation of alternate routes for a segment of the pipeline route in the vicinity of the Historic District of Kemblesville, Pennsylvania. On June 2, 2015, a field meeting was conducted to review the proposed route and alternate routes. In response to comments received from the National Park Service and other stakeholders, the FERC requested that Eastern Shore conduct an additional investigation in relation to Eastern Shore's existing right-of-way. On July 9, 2015, the FERC issued a 30-day public scoping notice, in advance of issuing an environmental assessment, in order to solicit comments from the public regarding construction of the Kemblesville loop. On August 18, 2015, Eastern Shore submitted supplemental information to the FERC regarding the results of its investigation of the Kemblesville loop.
On November 18, 2015, Eastern Shore filed an amendment to this application, which indicated the preferred pipeline route and shortened the total miles of the proposed pipeline to 5.4 miles. On February 10, 2016, the FERC issued a notice combining the White Oak Mainline Expansion Project and the System Reliability Project into a single environmental assessment. On March 2, 2016, the FERC issued a revised notice, rescheduling the issuance of the combined environmental assessment to April 25, 2016, with a 90-day authorization decision to be issued no later than July 24, 2016.

On March 28, 2016, subsequent to the issuance of the schedule, the FERC issued another environmental data request concerning the United States Department of Agriculture and an agricultural conservation easement on a tract of land where the White Oak Mainline Project would install a portion of the pipeline in its existing right-of way. On April 4, 2016, Eastern Shore responded to the data request. Subsequently, Eastern Shore revised the construction workspace configuration to mutual agreement of both parties.

On July 21, 2016, the FERC issued a certificate of public convenience and necessity authorizing Eastern Shore to construct and operate the proposed White Oak Mainline Project. The FERC denied Eastern Shore’s request for a pre-determination of rolled-in rate treatment and requires Eastern Shore to comply with 19 environmental conditions.

System Reliability Project: On May 22, 2015, Eastern Shore submitted an application to the FERC seeking authorization to construct, own and operate approximately 10.1 miles of 16-inch pipeline looping and auxiliary facilities in New Castle and Kent Counties, Delaware and a new compressor at its existing Bridgeville compressor station in Sussex County, Delaware. Eastern Shore further proposes to reinforce critical points on its pipeline system. The total project will benefit all of Eastern Shore’s customers by modifying the pipeline system to respond to severe operational conditions experienced during actual winter peak days in 2014 and 2015. Since the project is intended to improve system reliability, Eastern Shore requested a predetermination of rolled-in rate treatment for the costs of the project.
On June 8, 2015, the FERC filed a notice of the application, and the comment period ended on June 29, 2015. Two interested parties filed comments and protests with the FERC. Eastern Shore has filed answers to the comments and protests from the two parties.

On September 4, 2015, the FERC issued a notice of intent to prepare an environmental assessment, and Eastern Shore responded to the FERC Staff's environmental data requests. On February 10, 2016, the FERC issued a notice combining the System Reliability Project and White Oak Mainline Expansion project into a single environmental assessment. On March 2, 2016, the FERC issued a revised notice rescheduling the issuance of the combined environmental assessment to April 25, 2016, with the 90-day authorization decision to be issued no later than July 24, 2016. On July 21, 2016, the FERC issued a certificate of public convenience and necessity authorizing Eastern Shore to construct and operate the proposed System Reliability Project. The FERC granted Eastern Shore’s request for a pre-determination of rolled-in rate treatment in its next rate base proceeding and requires Eastern Shore to comply with 19 environmental conditions.

TETLP Capacity Expansion Project: On October 13, 2015, Eastern Shore submitted an application to the FERC to make certain measurement and related improvements at its TETLP interconnect facilities, which would enable Eastern Shore to increase natural gas receipts from TETLP by 53,000 Dts/d, for a total capacity of 160,000 Dts/d. On December 22, 2015, the FERC authorized Eastern Shore to proceed with the project. On March 11, 2016, the capacity expansion project was placed into service.

2017 Expansion Project: On May 12, 2016, Eastern Shore submitted a request to the FERC to initiate the FERC’s pre-filing review procedures for Eastern Shore's 2017 expansion project. The expansion project consists of approximately 33 miles of pipeline looping in Pennsylvania, Maryland and Delaware; upgrades to existing metering facilities in Lancaster County, Pennsylvania; installation of an additional 3,550 horsepower compressor unit at Eastern Shore’s existing Daleville compressor station in Chester County, Pennsylvania; and approximately 17 miles of new mainline extension and two pressure control stations in Sussex County, Delaware. The expansion project is necessary to provide up to 86,437 Dts/d of additional firm natural gas transportation capacity to meet anticipated market demand. On May 17, 2016, the FERC approved Eastern Shore’s request to commence the pre-filing review process. Eastern Shore is currently working through the pre-filing process and anticipates filing a certificate of public convenience and necessity seeking authorization to construct the project in November 2016.

2017 Rate Case Filing
In January 2017, Eastern Shore intends to file a base rate proceeding with the FERC as required by the terms of its 2012 settlement agreement.