XML 63 R13.htm IDEA: XBRL DOCUMENT v2.4.0.8
Rates and Other Regulatory Activities
6 Months Ended
Jun. 30, 2014
Regulated Operations [Abstract]  
Rates and Other Regulatory Activities
Rates and Other Regulatory Activities
Our natural gas and electric distribution operations in Delaware, Maryland and Florida are subject to regulation by their respective PSC; Eastern Shore, our natural gas transmission subsidiary, is subject to regulation by the FERC; and Peninsula Pipeline, our intrastate pipeline subsidiary, is subject to regulation by the Florida PSC. Chesapeake’s Florida natural gas distribution division and FPU’s natural gas and electric distribution operations continue to be subject to regulation by the Florida PSC as separate entities.
Delaware
There were no rates and other regulatory activities in Delaware during the first six months of 2014.
Maryland
On March 24, 2014, Sandpiper filed a depreciation study with the Maryland PSC regarding the assets purchased in the ESG acquisition. This depreciation study was filed in accordance with the order dated May 29, 2013, which allowed Sandpiper to recommend the proper depreciation rates and accumulated depreciation associated with the acquired assets. Sandpiper recommended slightly lower depreciation rates to be applied prospectively and a reduction of $4.5 million in accumulated depreciation. On June 20, 2014, the Maryland PSC staff recommended lower depreciation rates than those recommended by Sandpiper and a reduction of $5.5 million in accumulated depreciation. The Office of People’s Counsel also recommended lower depreciation rates and no adjustment to accumulated depreciation. The parties are currently discussing a potential settlement in advance of an evidentiary hearing in August 2014.

Florida
On April 28, 2014, FPU filed a base rate proceeding for its electric distribution operation. FPU requested interim rate relief of approximately $2.4 million and final rate relief of approximately $5.9 million. The interim rate relief requested is based on the twelve-month period ended September 30, 2013. At the July 10, 2014 Agenda Conference, the Florida PSC approved interim rate relief of approximately $2.2 million, as recommended by the Florida PSC staff. The interim rates are effective for meter readings on or after August 10, 2014. Any increase to our rates as a result of this interim rate relief may be subject to refund, depending on the outcome of the final rate relief request. The base rate proceeding hearing is currently scheduled for September 15-18, 2014. The revenue requirement will be determined at the Agenda Conference, currently scheduled for November 25, 2014, and final rates will be determined at the Agenda Conference, currently scheduled for December 16, 2014. Final rates are expected to be effective in January 2015.
On January 13, 2014, FPU's natural gas divisions and Chesapeake's Florida natural gas distribution division filed a consolidated natural gas depreciation study with the Florida PSC. We also filed for approval to establish a regulatory asset and related amortization to address the costs associated with the development of this study. Depending on the results of this proceeding, we may be required to change depreciation expense for our Florida natural gas distribution operations. The PSC agenda date for the depreciation study has not yet been set.
On November 15, 2013, Chesapeake's Florida natural gas distribution division petitioned the Florida PSC for an extension to its surcharge to recover an additional $381,000 in estimated remaining environmental cleanup costs that have not yet been recovered. This extension would be effective for two years, beginning January 1, 2014. The Florida PSC approved the extension of the surcharge and the additional amount for recovery at the Agenda Conference on January 7, 2014.

Eastern Shore
The following are regulatory activities involving FERC orders applicable to Eastern Shore and the expansions of Eastern Shore’s transmission system:

TETLP Expansion Project: On January 31, 2014, Eastern Shore submitted to the FERC a request for prior notice authorization regarding a project that included certain improvements at Eastern Shore’s existing interconnection with TETLP near Honey Brook, Pennsylvania. This project will allow Eastern Shore to increase its capacity to receive natural gas from TETLP by 57,000 Dts/d to a total capacity of 107,000 Dts/d, but this requested improvement will not result in an increase in Eastern Shore’s overall system capacity. On April 8, 2014, the FERC approved Eastern Shore’s prior notice application, and Eastern Shore made this additional receipt point capacity available to an existing industrial customer.

White Oak Lateral Project Filing: On June 13, 2013, Eastern Shore submitted to the FERC an application for a CP, seeking authorization to construct the White Oak lateral project located in Kent County, Delaware. The project consists of installing approximately 5.5 miles of 16-inch diameter pipeline, metering facilities and miscellaneous appurtenances, extending from Eastern Shore's mainline system near its North Dover City Gate Station to the Garrison Oak Technical Park, all located in Dover, Delaware. This project is designed to provide 55,200 Dts/d of delivery lateral firm transportation service to an industrial customer facility currently under construction. The total cost of the project is estimated to be approximately $11.5 million.

On August 9, 2013, the FERC issued a notice of intent to prepare an environmental assessment for the project. The comment period concluded on September 9, 2013, with no comments being filed in the docket. The environmental assessment was issued on October 4, 2013, and FERC staff recommended a finding of no significant impact. Eastern Shore filed the implementation plan and acceptance of conditions, stating that it will comply with all environmental conditions as set forth in the order. On November 27, 2013, the FERC issued a CP for this project. On January 17, 2014, the FERC issued its notice to allow construction to proceed, and Eastern Shore began construction activities for this project on January 22, 2014, for a planned in-service date of January 1, 2015.

Other matters: Eastern Shore also had developments in the following FERC matters:

On May 30, 2014, Eastern Shore submitted to the FERC a combined filing of its FRP and Cash-Out Refund for a twelve-month period from April 2013 to March 2014. In this filing, Eastern Shore proposed an FRP rate of 0.62 percent. During the period, Eastern Shore experienced an under-recovery of $494,000 in its Deferred Gas Required for Operations costs and an over-recovery of $160,000 in its Deferred Cash-Out costs. Eastern Shore proposed to incorporate the Cash-Out Refund into its FRP to mitigate the effect of the increase in the FRP to its customers.