XML 73 R33.htm IDEA: XBRL DOCUMENT v3.24.1
Newbuildings (Tables)
12 Months Ended
Dec. 31, 2023
Property, Plant and Equipment [Abstract]  
Schedule of newbuildings
The table below sets forth the carrying value of our newbuildings:
(in thousands of $)20232022
As of January 1176,145 83,479 
Installment payments(1)
378,305 88,542 
Capitalized interest7,805 1,780 
Other capitalized costs(2)
8,126 2,344 
Reclassification to Vessels and equipment(3)
(437,735)— 
As of December 31132,646 176,145 

(1)     Installment payments in the year ended December 31, 2023 include $75.7 million for the third and /or fourth installments to New Times Shipyard for newbuildings “Mount Neblina,” “Mount Bandeira,” “Mount Hua,” “Mount Elbrus,” “Mount Denali,” “Mount Aconcagua” and “Mount Emai”, and $302.6 million for the fifth and sixth installments net of address commissions to New Times Shipyard for newbuildings “Mount Norefjell,” “Mount Ita,” “Mount Etna,” “Mount Blanc,” “Mount Matterhorn” and “Mount Neblina.”
Installment payments in the year ended December 31, 2022 include $74.9 million of non-cash payments associated with the third and fourth installment payments to New Times Shipyard for newbuildings “Mount Norefjell,” “Mount Ita,” “Mount Etna,” “Mount Blanc” and “Mount Matterhorn” and the third installment for newbuilding “Mount Neblina”. In December 2022, the Company agreed with New Times Shipyard to defer payments of the third installment on newbuildings “Mount Hua” and “Mount Bandeira” of $13.7 million from December 2022 to March 2023. These deferred amounts were paid in March 2023 following the novation of the sale and leaseback agreements relating to “Mount Bandeira” and “Mount Hua” from CCBFL to Jiangsu and subsequent drawdown on the pre-delivery financing.

The Company has drawn $388.0 million (including the $13.7 million drawn down from Jiangsu described above) and $74.9 million in the years ended December 31, 2023 and 2022, respectively, on the sale leaseback financing to fund these installments and the installment payments were made by AVIC, CCBFL and Jiangsu (as these terms are defined in Note 12) on behalf of the Company.

(2)     Other capitalized costs primarily includes direct costs associated with the supervision of our newbuilding program.

(3)     "Mount Norefjell,” “Mount Ita,” “Mount Etna,” “Mount Blanc,” “Mount Matterhorn” and “Mount Neblina” were delivered in the year ended December 31, 2023 and their corresponding costs were reclassified to Vessels and equipment.
(in thousands of $)Vessels and equipment
Cost
As of January 1, 2022 and 2023— 
Additions437,735 
As of December 31, 2023437,735 
Depreciation and amortization
As of January 1, 2022 and 2023— 
Charge for the period(9,118)
As of December 31, 2023(9,118)
Net book value as of December 31, 2023428,617