16. Commitments and Contingencies

 

Guarantee for SPI

 

On March 6, 2024, the Group’s related party, SPI Energy Co., Ltd. (“SPI”) entered into a Deed of Settlement with its creditor, Streeterville Capital, LLC (“Streeterville”) to settle the unpaid balances of certain convertible notes via installment payments as agreed in the Deed of Settlement. As of part of this Deed of Settlement, the Company, as the guarantor, covenants to Streeterville to pay and satisfy on demand all liabilities due from SPI to Streeterville with a total amount of $14,980. The Group assessed the accounting treatment of this guarantee under ASC 460 and ASC 450 and considered that the possibility for the Group to incur actual liability under this guarantee is remote so there is no guarantee liabilities accrued as of March 31, 2024. On September 6, 2024, prior to the issuance of the condensed consolidated financial statements, the guarantee was released and canceled without any actual liabilities incurred by the Group.

 

Commitments — As of March 31, 2024, the Group had other commitments of approximately $815. These commitments were solely related to contracts signed with vendors for research and development by the Group and are expected to be paid in one year. As part of the Proterra acquisition (Note 4), the Group also took the responsibility to provide Proterra transit business unit employees job offers at acquisition closing date and keep those employees for at least one year, with an estimated total employee salary of over $20,000.

 

Contingency — In the ordinary course of business, the Group may be subject to legal proceedings regarding contractual and employment relationships and a variety of other matters. The Group records contingent liabilities resulting from such claims, when a loss is assessed to be probable and the amount of the loss is reasonably estimable. In April 2024, there was a dispute with the landlord of Folsom warehouse which the landlord seeks to recover damages in excess of $250. However, the lawsuit is in its early stage and the final outcome, including the potential amount of any losses, is uncertain. As a result, no reasonable estimate on the loss can be made as of March 31, 2024 and the Group is currently negotiating on settlement with the landlord.

 

In the opinion of management, there were no other material pending or threatened claims and litigation as of March 31, 2024 and through the issuance date of these condensed consolidated financial statements.